RESOLVED : 1.To recommend to the Cabinet Member for Community Empowerment that the work to the pedestrian crossing facility outside Rainham Village Primary School be approved for implementation as shown on drawing: QK009/NC/41.A 2.To recommend to the Cabinet Member for Community Empowerment that the addition of two new bus stop clear ways on Upminster Road South and in the vicinity of Rainham Village Primary School be approved for implementation the position of the east bound bus stop is to be the subject of a further review by the Head of Street care in conjunction with London Buses whose findings will be presented to this in a further report to this committee. 3.That it be noted that the estimated cost of the scheme would be £600 which would be met from the 2011/12 Transport for London Local Implementation Plan allocation for School Travel Plans Implementation.
Word for word from the decision Havering published for this meeting.Source: democracy.havering.gov.uk
This report recommends improvement works to the school crossing facility outside Rainham Village Primary School following the completion of public consultation.
This scheme is within Rainham and Wennington ward. Highways Advisory Committee, 21 February 2012
Recommendations
1. That the Committee having considered the information set out in this report recommends to the Cabinet Member for Community Empowerment that the work to the pedestrian crossing facility outside Rainham Village Primary School is approved for implementation as detailed in this report and shown on the following drawing:
QK009/NC/41.A
2. That the Committee having considered the information set out in this report recommends to the Cabinet Member for Community Empowerment that the addition of two new bus stop clear ways on Upminster Road South and in the vicinity of Rainham Village Primary School are approved for implementation as detailed in this report and shown on the following drawing:
QK009/NC/41.A
3. That it be noted that the estimated cost of the scheme will be £600 which will be met from the 2011/12 Transport for London Local Implementation Plan allocation for School Travel Plans Implementation.
REPORT DETAIL
Background
1.1Rainham Village Primary School fronts Upminster Road South, and lies within a 20mph speed zone. Traffic cushions have been installed within the vicinity of the school and a Puffin crossing facility with a school crossing patrol serves the school.
1.2The school made representations to StreetCare following ongoing safety issues resulting from parents parking illegally on the Puffin crossing zigzags, during the school run, and a general problem with vehicles parking close to the school throughout the day.
1.3To assist the school crossing patrol and keep the school frontage clear of vehicles during school times it is proposed to:
a. extend the Puffin crossing zigzags by 4 markings on both sides; and b. place a 37.56m school keep clear marking outside the school. Highways Advisory Committee, 21 February 2012
1.4Staff noted that during school pupil leaving times, vehicles parked (legally) on both sides of Upminster Road South act to impede the flow traffic; specifically buses and other large vehicles.
1.5There are two bus stops on Upminster Road South, serving bus routes 165 & 287. The bus stops are unrestricted, meaning that there are no parking restrictions currently in place to prevent vehicles parking at the stops. To assist in the prevention of parking at the bus stops and to enable buses to stop safely it is proposed that clearways be placed at the two bus stops.
2.0Outcome of Public Consultation
2.1Staff hand delivered forty letters on the 8th December 2011 to residents living within the vicinity of the scheme and being potentially affected by the scheme. The closing date for comments was 6th January 2011.
2.2The statutory elements of the scheme were publicly advertised in the Romford recorder and in the London Gazette on 9th December 2011. The closing date for comments was 6th January 2011.
2.3By the close of consultation no responses had been received. Highways Advisory Committee, 21 February 2012
IMPLICATIONS AND RISKS
Financial implications and risks: That it be noted that the estimated cost of the scheme will be £600 which will be met from the 2011/12 Transport for London Local Implementation Plan allocation for School Travel Plans Implementation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.