HIGHWAYS SCHEMES APPLICATION

Agreed Committee 2 papers

Highways Advisory Committee agreed this item on Tuesday 19 June 2012. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

Decision SECTION A - Highway scheme proposals with funding in place H1 A1306 New Road Junction with Wennington Road, provide traffic islands to prevent overtaking through junction. AGREED H2 Ferry Lane At Any Time (Double Yellow Lines) - new section linking into Coldharbour Lane AGREED H3 Crow Lane Speed table at junction with Seabrook Gardens and new development site. AGREED H4 Manor Road Make temporary road closure associated with Heath Park Road Railway Bridge permanent REJECTED H5 Romford Casualty Reduction Package Review of casualties in North Street, London Road, Brentwood Road, Balgores Lane and Main Road AGREED SECTION B - Highway scheme proposals without funding available H6 Marks Road (west) 20mph speed limit and road hump at fire gate at Pretoria Road to reduce speed of residents. REJECTED 7 to 1 H7 Collier Row Lane Set of speed humps to reduce traffic speed on section either side and between Kenway and Mawney Road as existing islands and signs have not worked. REJECTED
Word for word from the decision Havering published for this meeting. Source: democracy.havering.gov.uk

Follow this further

Built from Havering's papers

What the report saysPro

Report to Highways Advisory Committee

1 of 3

London Borough of Havering Traffic & Engineering - StreetCare Highways Advisory Committee Highway Schemes Applications Schedule 19th June 2012

Scheme Date Item Funding Likely Origin/ Requested/ Scheme Description Officer Advice CRM / Contact Ref Source Budget Request Placed on from List SECTION A - Highway scheme proposals with funding in place

Junction with Wennington Road, Provision of traffic islands would assist in Mark S106 and Mark Philpotts H1 A1306 New Road provide traffic islands to prevent local speed reduction and prevent £18k Philpotts LBH 11/05/2012 TFL LIP LBH StreetCare overtaking through junction. dangerous overtaking. StreetCare

Rest of Ferry Lane is already subject to At Any Time (Double Yellow same controls and continuance would be H2 Ferry Lane Lines) - new section linking into Developer £1,500 Rainham BID 11/05/2012 Rainham BID appropriate and consistent. Supported by Coldharbour Lane BID and police SNT.

Speed table proposed by developer in order to overcome depth of cover Speed table at junction with restriction on two 132KV power cables Developer David Ballm, H3 Crow Lane Seabrook Gardens and new running past site. Speed table will assist Developer £20k (Raven Close 11/05/2012 LBH StreetCare development site. in providing sufficient cover to power Site) mains. Speed table will also assist with local traffic speed reduction.

W:\data03\ENGINEER\T&T\Committees & Liaison\Highways Advisory Committee (QJ043)\Highway Schemes Applications Reports\Highway Schemes Applications.xls19th June 2012 2 of 3

London Borough of Havering Traffic & Engineering - StreetCare Highways Advisory Committee Highway Schemes Applications Schedule 19th June 2012

Scheme Date Item Funding Likely Origin/ Requested/ Scheme Description Officer Advice CRM / Contact Ref Source Budget Request Placed on from List

Road closed using temporary powers. Permanent closure requires use of different powers and statutory LBH Make temporary road closure consultation. Currently, 2 people have Highways Resident H4 Manor Road associated with Heath Park written in support and 8 against (moving Structures £1k 11/05/2012 (Manor Road) Road Railway Bridge permanent problem to other streets) and officers Manageme have received several telephone calls nt against. Original intention was to remove closure when 3 tonne limit lifted.

Review of casualties in North Additional in-year funding made available Mark Romford Casualty Street, London Road, Brentwood Mark Philpotts H5 by TfL. Romford Package is first reserve TfL LIP £50k Philpotts LBH 11/05/2012 Reduction Package Road, Balgores Lane and Main LBH StreetCare scheme StreetCare Road

SECTION B - Highway scheme proposals without funding available

20mph speed limit and road Feasible. Not funded. More than one hump at fire gate at Pretoria H6 Marks Road (west) hump probably required for proper None £8k Resident 08/06/2012 Resident Road to reduce speed of scheme. residents.

W:\data03\ENGINEER\T&T\Committees & Liaison\Highways Advisory Committee (QJ043)\Highway Schemes Applications Reports\Highway Schemes Applications.xls19th June 2012 3 of 3

London Borough of Havering Traffic & Engineering - StreetCare Highways Advisory Committee Highway Schemes Applications Schedule 19th June 2012

Scheme Date Item Funding Likely Origin/ Requested/ Scheme Description Officer Advice CRM / Contact Ref Source Budget Request Placed on from List

Collier Row Lane is a bus and emergency Set of speed humps to reduce services route and speed humps are not traffic speed on section either advisable. Flat-topped speed tables might £10k - H7 Collier Row Lane side and between Kenway and help, but not funded and likely to create None Resident 08/06/2012 Resident £20k Mawney Road as existing islands complaints about vibration due to vehicle and signs have not worked. flow. Speed cushions might be an option, but again, unfunded.

SECTION C - Highway scheme proposals on hold for future discussion (for Noting)

None to report

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
120619 Highway Schemes ApplicationsReport 28 KB DownloadRead as text
PDF
HIGHWAYS SCHEMES APPLICATIONReport 93 KB Download

At this meeting

Whole meeting

On this subject at Havering

Search all
  1. HIGHWAYS SCHEMES APPLICATIONThis decision
  2. Highways schemes application - works programmeRefused
  3. Highways schemes application - works programmeRefused
  4. Highways schemes application - works programmeAgreed
  5. Highways schemes application - works programmeDeferred
  6. Highways schemes applicationsAgreed

More from Havering Highways Advisory Committee

All decisions
MeetingDecisionOutcome
8 Mar 2022 Electric vehicles charging point programme - approval to proceed to formal consultationRESOLVED to recommend to the Cabinet Member for Environment in consultation with the Leader of the Council to: · The ... Decided Open
8 Feb 2022 St helens court parking and housing enforcement scheme objectionsRESOLVED to recommend to the Cabinet Members for Environment and Housing in consultation with the Leader of the Counc... Agreed Open
8 Feb 2022 Stanley close, romford - permit parking measures implementation requestRESOLVED to recommend to the Cabinet Member for Environment in consultation with the Leader of the Council to: 1. agr... Agreed Open
8 Feb 2022 Grass verges - recommendationsRESOLVED to recommend to the Cabinet Member for Environment in consultation with the Leader of the Council that: 1. o... Noted Open
11 Jan 2022 School streets (ss) phase 1 - request to convert the scheme from experimental to permanentRESOLVED to recommend to the Cabinet Member for Public Realm in consultation with the Leader of the Council that: · t... Decided Open