RESOLVED that subject to no contrary direction by the Secretary of State exercising powers to call-in the application following the notification of the application to Secretary of State that the proposal be granted planning permission subject to the conditions as set out in the report, and amendment to conditions 4, 6 and 7 to reflect phasing and drawing numbers, on expiry of a period of 21 days beginning with the date which the Secretary of State told the authority in writing is the date they received the material specified in paragraph 10 of Circular 02/2009.
Word for word from the decision Havering published for this meeting.Source: democracy.havering.gov.uk
This planning application proposes the material change of use of approximately 5.8 hectares of land on the eastern side of Upminster Cemetery from agricultural use to a cemetery. The proposal would include the installation of sub-level structures and plant, intended to reduce groundwater levels, and the erection of seven buildings: six of which would house groundwater pumping equipment, and the other a toilet block. The proposal would provide for 5,716 burials spaces.
Recommendations
That subject to no contrary direction by the Secretary of State exercising powers to call-in the application following the notification of the application to Secretary of State in line with Circular 02/2009 Town and Country Planning (Consultation) (England) Direction 2009 that the proposal be granted planning permission subject to the following conditions on expiry of the a period of 21 days beginning with the date which the Secretary of State tells the authority in writing is the date she received the material specified in paragraph 10 of Circular 02/2009.
1. Time Limit - The development to which this permission relates must be commenced not later than three years from the date of this permission.
Reason:-
To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2. Approved Plans - The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans, particulars and specifications.
Reason:-
The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
3. Highways - The development shall not be brought into use until a review of bus stop accessibility, traffic signs, road markings, and visibility at the site exit onto Ockendon Road, have been submitted to and approved in writing by the Local Planning Authority, and the recommendations of these reviews implemented.
Reason: To ensure the interests of highway safety and amenity and to accord with Policy DC32.
4. Archaeology - A) No development shall take place until the applicant has secured the implementation of a programme of archaeological works in accordance with a Written Scheme of Investigation which has been submitted by the applicant and approved by the local planning authority.
B) No development or demolition shall take place other than in accordance with the Written Scheme of Investigation approved under Part (A).
C) The development shall not be occupied until the site investigation and post investigation assessment has been completed in accordance with the programme set out in the Written Scheme of Investigation approved under Part (A), and the provision made for analysis, publication and dissemination of the results and archive deposition has been secured.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
P1991.22 - 73 brentwood road, romfordRESOLVED that PLANNING PERMISSION BE GRANTED with the revised conditions in the report. The vote for the resolution t...
P0867.22 corbets tey road upminsterRESOLVED that PLANNING PERMISSION BE GRANTED . The vote for the resolution to grant planning permission was granted u...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.