To recommend to the Cabinet Member for Community Empowerment that the various elements be implemented as detailed on Drawing QK063/02/05 that the green spaces adjacent to property numbers 84, 94, 145, 169 and the RSPCA Clinic Chippenham Road, be converted into parking bays. that the kerb from East Dene Drive to no. 124 Chippenham Road be lowered to approximately 50mm where possible, to provide improved access to footway parking bays. Install ‘at any time’ waiting restrictions to improve traffic flow, prevent obstructive parking and improve road safety. Relocation of lighting columns to accommodate the half on footway parking – in all cases this would involve the upgrading of lanterns which was in line with the Council’s energy efficiency programme. 2. That it be noted that the estimated cost of £264,000 would be met by funding from the Harold Hill Ambitions programme budget.
Word for word from the decision Havering published for this meeting.Source: democracy.havering.gov.uk
This report sets out the results of the public consultation concerning the proposals for the provision of parking improvements in Chippenham Road, as part of the Harold Hill Ambitions programme.
This scheme is within the Gooshays ward. RECOMMENDATIONS
1. That the Committee having considered the responses and information set out in this report recommends to the Cabinet Member for Community Empowerment that the various elements be implemented as follows and set out below and shown on Drawing QK063/02/05
a. that the green spaces adjacent to property numbers 84, 94, 145, 169 and the RSPCA Clinic Chippenham Road, are converted into parking bays.
b. that the kerb from East Dene Drive to no. 124 Chippenham Road to be lowered to approximately 50mm where possible, to provide improved access to footway parking bays.
c. Install „at any time‟ waiting restrictions to improve traffic flow, prevent obstructive parking and improve road safety.
d. Relocation of lighting columns to accommodate the half on footway parking – in all cases this will involve the upgrading of lanterns which is in line with the Councils‟ energy efficiency programme.
2. That it be noted that the estimated cost of £264,000 will be met by funding from the Harold Hill Ambitions programme budget.
REPORT DETAIL
Background
1.1As part of the Councils‟ on going design review of the Hilldene Shopping Centre area and how it can best operate, the section of Chippenham Road between East Dene Drive and the RSPCA Clinic has been identified as an area lacking in parking for residents, a problem which is further exacerbated by properties that have no road frontage.
1.2Due to the areas high parking demand, it would be common to find double sided carriageway parking in this location despite the narrow road with, making visibility and manoeuvrability difficult whilst potentially causing problems for refuse and emergency vehicles to gain access. 1.3 It has been noted that much of the carriageway parking occurs because of the high kerbs making it difficult for drivers to “bump up” the kerb and use the available part on footway parking bays in some locations.
1.4Throughout this section of Chippenham Road it is apparent that there is much unused green space and it is proposed to provide an increase in parking provision by utilising these areas where possible.
1.5In taking forward the proposals, approximately 100 Letters were hand- delivered to those potentially affected by the proposals on 28th December 2012. The closing date for comments was 25th January 2013 and in addition notices were advertised in the local newspaper.
2.0Outcome of Public Consultation
2.1By the close of consultation, 5 responses had been received and are outlined in appendix A of this report.
2.2In summary, the main concerns were for the provision of new and extending existing vehicle crossovers as part of the proposed footway works and in many cases residents were keen for the proposals to be carried out before the Chippenham Gardens development commences.
3.0Staff Comments
3.1The utilisation of the available green space for parking on Chippenham Road will help to alleviate the existing capacity issues and the reduction of kerb heights will allow for footway parking so that carriageway widths and visibility can be maintained. Staff therefore recommend that the scheme proceeds as advertised.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.