P1136.12 - 1A HILLVIEW AVENUE HORNCHURCH - SINGLE STOREY HOUSE (OUTLINE APPLICATION)

Agreed Planning 1 paper

Planning Committee agreed this item on Thursday 9 January 2014. Below is the council's own wording, with the papers it was decided on.

Item197

Resolved

RESOLVED that the proposal was unacceptable as it stood but would be acceptable subject to the developer / owner(s) entering into a Legal Agreement under Section 106 of the Town and Country Planning Act 1990 (as amended), to secure the following: Prior to commencement of the proposed dwelling in question, the land to the south-east corner of the adjoining church and the south-west corner of No.1 Hillview Avenue as indicated in the submitted ‘Private Access and pedestrian visibility splay plan’ and plan number 910/03A, both dated 10 September 2013, shall remain as clear and unobstructed pedestrian visibility splays for the lifetime of the development. No obstruction above 0.6 meters in height shall be placed within these visibility splays. A financial contribution of £6k per dwelling unit towards the infrastructure costs arising from the development would be required at the time of the reserved matter application to fulfil the requirements of the Planning Obligations SPD. All contribution sums shall include interest to the due date of expenditure and all contribution sums to be subject to indexation from the date of completion of the Section 106 agreement to the date of receipt by the Council. The Developer/Owner to pay the Council’s reasonable legal costs associated with the Legal Agreement prior to the completion of the agreement irrespective of whether the agreement is completed. · Payment of the appropriate planning obligations monitoring fee prior to the completion of the agreement. That staff be authorised to enter into a legal agreement to secure the above and upon completion of that agreement, grant planning permission subject to the conditions as set out in the report.
Word for word from the decision Havering published for this meeting. Source: democracy.havering.gov.uk

Follow this further

Built from Havering's papers

What the report saysPro

Report to Planning Committee

Summary

The application was originally reported to Committee on 3 October 2013, where it was resolved to grant permission subject to the completion of legal agreement.

The application is being re-reported to Committee to seek authority to alter the obligation wording in connection with the provision of visibility splays.

As before, the application seeks outline permission for a single storey 2 bedroom dwelling for details regarding access, layout and scale. Landscaping and appearance would be subject to reserved matters. This application is considered to be acceptable in all material respects and, subject to the prior completion of a S106 legal agreement to secure the payment of the Planning Obligations Contribution, it is recommended that planning permission is granted subject to conditions.

Recommendations

That the Committee notes that the development proposed is liable for the Mayor’s Community Infrastructure Levy (CIL) in accordance with London Plan Policy 8.3 and that the applicable charge would be calculated at the submission of reserved matters application.

That the proposal is unacceptable as it stands but would be acceptable subject to the developer / owner(s) entering into a Legal Agreement under Section 106 of the Town and Country Planning Act 1990 (as amended), to secure the following:

 Prior to commencement of the proposed dwelling in question, the land to the south-east corner of the adjoining church and the south-west corner of No.1 Hillview Avenue as indicated in the submitted ‘Private Access and pedestrian visibility splay plan’ and plan number 910/03A, both dated 10 September 2013, shall remain as clear and unobstructed pedestrian visibility splays for the lifetime of the development. No obstruction above 0.6 meters in height shall be placed within these visibility splays.

 A financial contribution of £6k per dwelling unit towards the infrastructure costs arising from the development would be required at the time of the reserved matter application to fulfil the requirements of the Planning Obligations SPD.

 All contribution sums shall include interest to the due date of expenditure and all contribution sums to be subject to indexation from the date of completion of the Section 106 agreement to the date of receipt by the Council.

 The Developer/Owner to pay the Council’s reasonable legal costs associated with the Legal Agreement prior to the completion of the agreement irrespective of whether the agreement is completed.

 Payment of the appropriate planning obligations monitoring fee prior to the completion of the agreement.

That Staff be authorised to enter into a legal agreement to secure the above and upon completion of that agreement, grant planning permission subject to the conditions set out below.

It is recommended that planning permission be granted subject to the following conditions: 1. Approval of details: The development hereby permitted may only be carried out in accordance with detailed plans and particulars which shall previously have been submitted to and approved by the Local Planning Authority, showing the appearance of the buildings and landscaping, including all matters defined as "landscaping" in the Town and Country Planning (Development Management Procedure) (England) Order 2010 (herein after called "the reserved matters").

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
P1136.12: 1A HILLVIEW AVENUE HORNCHURCH: SINGLE STOREY HOUSE (OUTLINE APPLICATION)Report 274 KB DownloadRead as text

At this meeting

Whole meeting

More from Havering Planning Committee

All decisions
MeetingDecisionOutcome
13 Mar 2025 Quarterly planning performance update - items for informationRESOLVED to note the contents of the report. Members were advised to contact officers directly if there are any enqui... Noted Open
6 Jul 2023 Land to the rear of 158-160 victoria roadRESOLVED that PLANNING PERMISSION BE GRANTED subject to conditions in the report. The vote for the resolution to gran... Decided Open
13 Apr 2023 P1991.22 - 73 brentwood road, romfordRESOLVED that PLANNING PERMISSION BE GRANTED with the revised conditions in the report. The vote for the resolution t... Decided Open
13 Apr 2023 P0229.22 - land to the rear of 88 harrow drive, hornchurchRESOLVED that PLANNING PERMISSION BE GRANTED with the revised condition of a wheel washing facility. The vote for the... Decided Open
13 Apr 2023 P0867.22 corbets tey road upminsterRESOLVED that PLANNING PERMISSION BE GRANTED . The vote for the resolution to grant planning permission was granted u... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies