Health & Wellbeing Board, Wednesday 12 February 2014 at 1.30pm

UPDATE ON BHRUT

Agreed Committee 1 paper

Health & Wellbeing Board agreed this item on Wednesday 12 February 2014. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

It was agreed that this would be a challenge however all parties were equally committed and acknowledged that it was essential that they work together. It was necessary for the Trust to demonstrate that it was addressing financial issues and that systems were moving in the right direction. The outcome of the review on senior leadership was imminent and that an Improvement Manager had been engaged. The Board were advised that the Chief Executive of the Council and the Chief Officer of BHRUT would be meeting with the Trust Development Agency.
Word for word from the decision Havering published for this meeting. Source: democracy.havering.gov.uk

Follow this further

Built from Havering's papers

What the report saysPro

Report to Health & Wellbeing Board

ITEM 6.3 To: Meeting of NHS Havering Clinical Commissioning Group Governing Body

From: Conor Burke, Chief Accountable Officer

Date: 28 January 2014

Subject: CQC and special measures at BHRUT

Executive summary The Care Quality Commission (CQC) identified Barking, Havering and Redbridge University Hospitals NHS Trust (BHRUT) as a top priority acute provider to be inspected in the first wave of the new CQC hospital inspection programme, as it had been shown to be at “high risk” on several indicators in the new Intelligent Monitoring tool. Over recent years the trust has faced significant quality challenges including:

 Poor results on the CQC inpatient survey and on the cancer patient experience survey  Achievement of the four-hour accident and emergency waiting time standard  Poor results on the national staff survey  High weekend mortality in some areas  Non-compliance with regulations recorded on several CQC inspections since it was registered especially in the A&E departments.

The CQC inspected the Trust from 14 - 17 October 2013 and held a Quality Summit on 17 December 2013 where the final reports were shared. It was also announced at the Quality Summit that the trust was being placed in “Special Measures” as it was recognised given the scope and scale of the challenges faced by the Trust additional support was required.

This report sets out the initial actions taken by the local and national organisations to address the key issues identified within the CQC report.

Recommendations The Governing Body is asked to:  Note the CQC report and the action being taken by the Trust Development Agency and BHRUT under the „Special Measures‟ framework  Review the action being taken to date by the CCG advising on any additional activities  Agree to receive a further report on the Trust Improvement plan at its next meeting 1.0 Purpose of the Report 1.1 To advise the Governing Body on the publication of the CQC inspection report of BHRUT and assure the members on action being taken to address key quality issues

2.0Background/Introduction

2.1The Care Quality Commission (CQC) identified Barking, Havering and Redbridge University Hospitals NHS Trust (BHRUT) as a top priority acute provider to be inspected in the first wave of the new CQC hospital inspection programme, as it had been shown to be at “high risk” on several indicators in the new Intelligent Monitoring tool. Over recent years the trust has faced significant quality challenges including:

o Poor results on the CQC inpatient survey and on the cancer patient experience survey o Achievement of the four-hour accident and emergency waiting time standard o Poor results on the national staff survey o High weekend mortality in some areas o Non-compliance with regulations recorded on several CQC inspections since it was registered especially in the A&E departments.

2.2The CQC inspected the trust from 14 -17 October 2013. It was also announced at the Quality Summit that the trust were being placed in “Special Measures” as it was recognised that given the scope and scale of the challenges faced by the Trust additional support was required.

3.0CQC report summary

3.1A full copy of the CQC inspection report is available at http://www.cqc.org.uk/public/news/our-latest-reports 3.2 The key findings from the report are as follows:  Many initiatives to improve quality and safety have only started very recently and it is too early to tell if they will deliver the required improvements quickly.

 The lack of support and engagement to drive improvements and address the Trust challenges from all senior clinical staff has meant progress has been slow

 Issues with record keeping were identified and need to be addressed

 The longstanding history of the problems and lack of progress indicates that the leadership is inadequate to address the scale of the challenges that the trust is facing and additional support is required

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
UPDATE ON BHRUTReport 139 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Havering

Search all
  1. UPDATE ON BHRUTThis decision
  2. Bhrut clinical strategyAgreed
  3. Barking, havering and redbridge university hospitals nhs trust (bhrut) clinical strategyAgreed
  4. Bhrut improvement updateAgreed
  5. Bhrut - breast care services - change of locationAgreed
  6. Bhrut - response to cqc reportAgreed

More from Havering Health & Wellbeing Board

All decisions
MeetingDecisionOutcome
7 May 2025 BCFAgreed to enter into a section 75 agreement with Havering Place-Based Partnership, on the terms and conditions outlin... Agreed Open
20 Dec 2023 Findings of #beewell surveyReport: Findings of #BeeWell Survey Due to lack of time the Board agreed that this item would be added to the next me... Agreed Open
20 Dec 2023 Government funding to stop smokingReport: Proposed spending plan with additional government funding for stop smoking services Presented by: Kate-Ezeoke... Noted Open
20 Dec 2023 Nel joint forward planReport: North East London Joint Forward Plan 2024-2025 Refresh Due to lack of time the Board agreed to the recommenda... Agreed Open
20 Dec 2023 Starting well jsnaReport: BHR JSNA 2023 – Demographics and Starting Well Chapters Presented by: [name removed] & [name removed] HWB not... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies