L0010.13 - PARKLANDS BRIDGE, PARKLANDS PARK, CORBETS TEY ROAD, UPMINSTER - LISTED BUILDING CONSENT FOR THE REPAIR AND RESTORATION OF THE GRADE II LISTED BRIDGE
ApprovedPlanning1 paper
Planning Committee approved this item on Thursday 6 March 2014. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the application and all relevant documentation be forwarded to the Secretary of State for determination in accordance with Section 12 of the Listed Building Act 1990 and regulation 13 of the Planning (Listed Building and Conservation Areas) Regulations 1990 and that should the Secretary of State be minded to grant Listed Building Consent that the conditions and Reason for Approval contained within the report be considered in respect of such consent: As mentioned previously in these minutes Councillor Linda Hawthorn declared a prejudicial interest in item L0010.13. Councillor Hawthorn advised that she was the Secretary of the Friends of Parklands Park and had previously expressed a view on the proposed development. Councillor Hawthorn left the room during the discussion of the item and took no part in the voting.
Word for word from the decision Havering published for this meeting.Source: democracy.havering.gov.uk
This proposal relates to Parklands Bridge, a Council owned, Grade II listed bridge in Parklands Park on the western side of Corbets Tey Road. Listed building consent is sought for the repair and restoration of the bridge. In all respects, the proposal is considered to accord with the relevant policies contained in the LDF Core Strategy and Development Control Policies Development Plan Document and The London Plan. Approval of the application is therefore recommended, subject to conditions.
Recommendations
It is recommended that the application and all relevant documentation be forwarded to the Secretary of State for determination in accordance with Section 12 of the Listed Building Act 1990 and regulation 13 of the Planning (Listed Building and Conservation Areas) Regulations 1990 and that should the Secretary of State be minded to grant Listed Building Consent that the conditions and Reason for Approval below be considered in respect of such consent:
1. Time Limit - The development to which this consent relates must be commenced not later than three years from the date of this consent.
Reason: To comply with the requirements of Section 18 of the Planning (Listed Building and Conservation Areas) Act 1990.
2. Accordance with plans - The development hereby permitted shall not be carried out otherwise than in complete accordance with the plans as listed on page 1 of this decision notice approved by the Local Planning Authority.
Reason: The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with the LDF Development Control Policies Development Plan Document Policy DC61.
3. Methodology for bridge restoration - The repair and restoration works shall be carried out to match the original work in exact accordance with Drawing No. MW-156-01, MW156-02; MW156-03; MW156-04 and the document titled “Parklands Bridge Restoration, MW 156 - Specification for materials and workmanship at Parklands Bridge”, dated 26th November 2013.
Reason: To preserve the character and appearance of the Listed Building and its setting and comply with Policies DC61 and DC67 of the Development Control Policies Development Plan Document.
4. Materials - The repair and restoration works to the bridge shall be undertaken, as far as is reasonably possible, using matching materials. Details/samples of additional materials, including the rendered brickwork, and supplementary matt finish steel handrails, to be used in the restoration of the bridge shall be submitted to and approved by the Local Planning Authority prior to the commencement of building. The bridge shall be repaired/restored in strict accordance with the agreed details.
Reason: To preserve the character and appearance of the Listed Building and its setting and comply with Policies DC61 and DC67 of the Development Control Policies Development Plan Document.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
L0010.13: PARKLANDS BRIDGE, PARKLANDS PARK, CORBETS TEY ROAD, UPMINSTER: LISTED BUILDING CONSENT FOR THE REPAIR AND RESTORATION OF THE GRADE II LISTED BRIDGEReport
236L0010.13 - PARKLANDS BRIDGE, PARKLANDS PARK, CORBETS TEY ROAD, UPMINSTER - LISTED BUILDING CONSENT FOR THE REPAIR AND RESTORATION OF THE GRADE II LISTED BRIDGEThis decision
P1991.22 - 73 brentwood road, romfordRESOLVED that PLANNING PERMISSION BE GRANTED with the revised conditions in the report. The vote for the resolution t...
P0867.22 corbets tey road upminsterRESOLVED that PLANNING PERMISSION BE GRANTED . The vote for the resolution to grant planning permission was granted u...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.