RESOLVED that the proposal was unacceptable as it stood but would be acceptable subject to the applicant entering into a Section 106 Legal Agreement under the Town and Country Planning Act 1990 (as amended), to secure the following: · A financial contribution of £30,000 to be used towards infrastructure costs. · All contribution sums shall include interest to the due date of expenditure and all contribution sums to be subject to indexation from the date of completion of the Section 106 agreement to the date of receipt by the Council. · To pay the Council’s reasonable legal costs in association with the preparation of a legal agreement, prior to completion of the agreement, irrespective of whether the legal agreement is completed. · Payment of the appropriate planning obligation/s monitoring fee prior to completion of the agreement. That staff be authorised to enter into a legal agreement to secure the above and upon completion of that agreement that the Committee delegate authority to the Head of Development and Building Control to grant planning permission subject to the conditions as set out in the report.
Word for word from the decision Havering published for this meeting.Source: democracy.havering.gov.uk
This application relates to a Council owned garage court. The application proposes the demolition of 15 garages and the erection of 5 x No. two storey dwellings. The application is submitted in outline form with all matters such as access, appearance, layout and scale to be submitted at a later stage as a reserved matter submission. Staff consider the outline proposal to be acceptable.
The application is recommended for approval subject to conditions and the applicant entering into a Section 106 Legal Agreement.
Recommendations
The proposed development is liable for the Mayor‟s Community Infrastructure Levy (CIL) in accordance with London Plan Policy 8.3. The exact amount liable for would be calculated at reserved matters stage.
That the proposal is unacceptable as it stands but would be acceptable subject to the applicant entering into a Section 106 Legal Agreement under the Town and Country Planning Act 1990 (as amended), to secure the following:
A financial contribution of £30,000 to be used towards infrastructure costs.
All contribution sums shall include interest to the due date of expenditure and all contribution sums to be subject to indexation from the date of completion of the Section 106 agreement to the date of receipt by the Council.
To pay the Council‟s reasonable legal costs in association with the preparation of a legal agreement, prior to completion of the agreement, irrespective of whether the legal agreement is completed.
Payment of the appropriate planning obligation/s monitoring fee prior to completion of the agreement.
That staff be authorised to enter into a legal agreement to secure the above and upon completion of that agreement that the Committee delegate authority to the Head of Development and Building Control to grant planning permission subject to the conditions set out below:
1. Approval of Details: The development hereby permitted may only be carried out in accordance with detailed plans and particulars which shall previously have been submitted to and approved by the Local Planning Authority, showing the layout, scale and appearance of the buildings, the means of access thereto, and landscaping, including all matters defined as "landscaping" in the Town and Country Planning (Development Management Procedure) (England) Order 2010 (herein after called "the reserved matters").
Reason: The particulars submitted are insufficient for consideration of the details mentioned and the application is expressed to be for outline permission only. 2. Time Limit for Details: Application/s for approval of the reserved matters shall be submitted to the Local Planning Authority within three years from the date of this permission.
Reason: To comply with Section 92 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
3. Time Limit for Commencement: The development to which this permission relates must be begun not later than the expiration of two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last reserved matter to be approved.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
P1991.22 - 73 brentwood road, romfordRESOLVED that PLANNING PERMISSION BE GRANTED with the revised conditions in the report. The vote for the resolution t...
P0867.22 corbets tey road upminsterRESOLVED that PLANNING PERMISSION BE GRANTED . The vote for the resolution to grant planning permission was granted u...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.