P0400.14 - 65 LAMBS LANE SOUTH RAINHAM

Agreed Planning 1 paper

Planning Committee agreed this item on Thursday 26 June 2014. Below is the council's own wording, with the papers it was decided on.

Item20

Resolved

RESOLVED that the proposal was unacceptable as it stood but would be acceptable subject to the applicant entering into a Legal Agreement under Section 106 of the Town and Country Planning Act 1990 (as amended), to secure the following: A financial contribution of £12,000 towards the infrastructure costs arising from the development would be required to fulfil the requirements of the Planning Obligations SPD. All contribution sums shall include interest to the due date of expenditure and all contribution sums to be subject to indexation from the date of completion of the Section 106 agreement to the date of receipt by the Council. The Developer/Owner to pay the Council’s reasonable legal costs associated with the Legal Agreement prior to the completion of the agreement irrespective of whether the agreement is completed. · Payment of the appropriate planning obligations monitoring fee prior to the completion of the agreement. That staff be authorised to enter into a legal agreement to secure the above and upon completion of that agreement, grant planning permission subject to the conditions as set out in the report. The vote for the resolution to grant planning permission was carried by 6 votes to 2 with 3 abstentions. Councillors Misir, Best, Crowder, Kelly, White and Dodin voted for the resolution to grant planning permission. Councillors Hawthorn and Ower voted against the resolution to grant planning permission. Councillors Nunn, Martin and Williamson abstained from voting.
Word for word from the decision Havering published for this meeting. Source: democracy.havering.gov.uk

Follow this further

Built from Havering's papers

What the report saysPro

Report to Planning Committee

Recommendations

That the Committee notes that the development proposed is liable for the Mayor’s Community Infrastructure Levy (CIL) in accordance with London Plan Policy 8.3 . The application fee is based on a combined net increase in floor area of 218.1 square meters which equates to a Mayoral CIL payment of £4,362.00.

That the proposal is unacceptable as it stands but would be acceptable subject to the applicant entering into a Legal Agreement under Section 106 of the Town and Country Planning Act 1990 (as amended), to secure the following:

 A financial contribution of £12,000 towards the infrastructure costs arising from the development would be required to fulfil the requirements of the Planning Obligations SPD.

 All contribution sums shall include interest to the due date of expenditure and all contribution sums to be subject to indexation from the date of completion of the Section 106 agreement to the date of receipt by the Council.

 The Developer/Owner to pay the Council’s reasonable legal costs associated with the Legal Agreement prior to the completion of the agreement irrespective of whether the agreement is completed.

 Payment of the appropriate planning obligations monitoring fee prior to the completion of the agreement.

That Staff be authorised to enter into a legal agreement to secure the above and upon completion of that agreement, grant planning permission subject to the conditions set out below. It is recommended that planning permission be granted subject to the following conditions:

1. Time Limit: The development to which this permission relates must be commenced not later than three years from the date of this permission.

Reason: To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).

2. Accordance with plans: The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans as detailed on page one of the decision notice.

Reason: The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with the LDF Development Control Policies Development Plan Document Policy DC61.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
P0400.14: 65 LAMBS LANE SOUTH RAINHAMReport 225 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Havering

Search all
  1. P0400.14 - 65 LAMBS LANE SOUTH RAINHAMThis decision
  2. P1013.21 - harris academy rainham, lambs lane southDeferred

More from Havering Planning Committee

All decisions
MeetingDecisionOutcome
13 Mar 2025 Quarterly planning performance update - items for informationRESOLVED to note the contents of the report. Members were advised to contact officers directly if there are any enqui... Noted Open
6 Jul 2023 Land to the rear of 158-160 victoria roadRESOLVED that PLANNING PERMISSION BE GRANTED subject to conditions in the report. The vote for the resolution to gran... Decided Open
13 Apr 2023 P1991.22 - 73 brentwood road, romfordRESOLVED that PLANNING PERMISSION BE GRANTED with the revised conditions in the report. The vote for the resolution t... Decided Open
13 Apr 2023 P0229.22 - land to the rear of 88 harrow drive, hornchurchRESOLVED that PLANNING PERMISSION BE GRANTED with the revised condition of a wheel washing facility. The vote for the... Decided Open
13 Apr 2023 P0867.22 corbets tey road upminsterRESOLVED that PLANNING PERMISSION BE GRANTED . The vote for the resolution to grant planning permission was granted u... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies