London Borough of Havering
Cabinet, Wednesday 12 December 2018 at 7.30pm

Implementation of Phase 4 expansion programme -Royal Liberty Secondary school expansion - Virement

Agreed Executive 4 papers

Cabinet agreed this item on Wednesday 12 December 2018. Below is the council's own wording, with the papers it was decided on.

Item26

Resolved

Cabinet : Agreed to vire funding of £1.2m from the DfE Basic Need Capital Grant - Phase 4 School Expansions contingency budget to the Royal Liberty expansion. Agreed to release funding to the ESFA (Education and Skills Funding Agency) to proceed with expansion build works. Agreed to review the feasibility process to ensure more accurate forecasting of costs.
Word for word from the decision Havering published for this meeting. Source: democracy.havering.gov.uk

Follow this further

Built from Havering's papers

What the report saysPro

Report to Cabinet, 8 pages

Summary

Cabinet approved the Phase 4 School Expansion programme at their meeting on the 12 October 2016. The programme included an expansion of The Royal Liberty School from a 4 FE school to a 5 FE school from 1 September 2018.

The Local Authority undertook a non-statutory consultation for the expansion of Phase 4 secondary schools, all of which were academies, and following the consultation the Cabinet Member took the decision to approve these expansion proposals on the 29th August 2017. These were still subject to each of the schools making an application to the DfE with a business case, and the business case for the expansion of Royal Liberty was duly approved by the DfE in April 2018. Both the Cabinet report and the ED to implement had an estimate cost of £4m for The Royal Liberty expansion build works and funding of £4m was allocated to The Royal Liberty in the School Expansion Capital Programme, funded from the DfE Basic Need Grant. This was based on an estimate of costs through the feasibility carried out by the Education Asset Management team, in consultation with local Planners. The Council was aware that The Royal Liberty School is to be rebuilt as part of the Priority School Building Programme PSBP, and that the ESFA intended to enter into a Design and Build contract for carrying out design and construction work relating to the school. The Council used this opportunity to incorporate additional works to expand the school from its Published Admission Number (PAN) of 120, to a PAN of 150 (4FE to 5FE). The additional works to enable the additional pupils to be accommodated included a new 3 court sports hall and two new general teaching spaces.

The ESFA issued a section 151 letter in September 2017 requesting the Council to provide a capital contribution of £3,630,000 for the provision of the additional works associated with the expansion works. The Council acknowledges that this figure was an estimate only, and that the total cost of the additional works, and therefore the contribution, may be higher or lower than the estimate.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Royal Liberty: s151 letter: update re costsAppendix 1 2 pages Download
PDF
ED Implementation of Phase 4 expansion programmeAppendix 2 12 pages Download
PDF
EIA-Secondary ConsultationAppendix 3 11 pages Download
PDF
Implementation of Phase 4 expansion programme -Royal Liberty Secondary school expansion: VirementReport 8 pages DownloadRead as text

At this meeting

Whole meeting
24Corporate Performance Report - Quarter 2Noted 25Keeping Havering Moving - The Parking Strategy and Highways Resurfacing PolicyAgreed
26Implementation of Phase 4 expansion programme -Royal Liberty Secondary school expansion - VirementThis decision

More from Havering Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 AnnouncementsThe Chair outlined the procedures to be followed in the event of a fire alarm or any other emergency requiring the ev... Decided Open
16 Sep 2026 Apologies for absenceAll Cabinet members were in attendance. Decided Open
16 Sep 2026 Disclosures of InterestThere were no disclosures of interest. Decided Open
16 Sep 2026 MinutesThe minutes of the meetings held on 12 th August 2026 , were agreed as a correct record and the Chair signed them. Agreed Open
16 Sep 2026 Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary SchoolReport Title: Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary School ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies