Resolved
The minutes of the meeting held on 7 th February 2024 , were agreed as a correct record and the Chair signed them. : The minutes of the meeting held on 7 th February 2024 , were agreed as a correct record and the Chair signed them.
Cabinet agreed this item on Wednesday 13 March 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
The minutes of the meeting held on 7 th February 2024 , were agreed as a correct record and the Chair signed them. : The minutes of the meeting held on 7 th February 2024 , were agreed as a correct record and the Chair signed them.
Public Document Pack
MINUTES OF A CABINET MEETING Council Chamber - Town Hall Wednesday, 7 February 2024 (7.30 - 9.00 pm)
Present: Councillor Ray Morgon (Leader of the Council), Chairman
Cabinet Member responsibility: Councillor Keith Darvill Lead Member for Climate Change & Housing Need Councillor Gillian Ford Lead Member for Adults & Wellbeing Councillor Oscar Ford Lead Member for Children and Young People Councillor Paul McGeary Lead Member for Housing & Property Councillor Paul Middleton Lead Member for Digital, Transformation & Customer Services Councillor Barry Mugglestone Lead Member for Environment Councillor Christopher Wilkins Lead Member for Finance Councillor Graham Williamson Lead Member for Regeneration
In attendance: Councillor David Taylor – Conservatives & Councillor Martin Goode (Group Leader – EHRG)
Also, in the chamber Cllr Jane Keane (Labour).
152 ANNOUNCEMENTS
Members were advised of the Fire Safety procedures in the Council Chamber.
153 APOLOGIES FOR ABSENCE
No apologies for absence received.
154 DISCLOSURES OF INTEREST
There were no disclosures of interest. Cabinet, 7 February 2024
155 MINUTES
The minutes of the meeting held on 10th January 2024, were agreed as a correct record and the Chair signed them.
156 BRIDGE CLOSE REGENERATION LLP 2024/25 BUSINESS PLAN REFRESH
Report: Bridge Close Regeneration LLP Business Plan Refresh 2024-2025
Presented by: Councillor Graham Williamson - Cabinet Member for Development and Regeneration
1.1The Council established a joint venture development vehicle, Bridge Close Regeneration LLP (‘BCR LLP’, ‘Joint Venture’ or ‘JV’) to bring forward the proposed regeneration of the site known as Bridge Close (see plan with red line at Appendix A). BCR LLP was until October 2020 jointly owned between the Council and a private sector partner. On 16th September 2020, Cabinet approved the proposed acquisition by the Council of the private sector interest in BCR LLP and on 29th October 2020, the Council entered into a purchase agreement to acquire the interest in BCR LLP that it did not already own from the private sector partner.
1.2In light of the Council acquiring full control of Bridge Close Regeneration LLP, on 16th December 2020, Cabinet considered a number of recommendations relating to the future funding and delivery of the scheme. Approval was granted for the Council to deliver the regeneration of Bridge Close directly, funding the development entirely through Council resources, predominantly using the Housing Revenue Account. Cabinet approved a budget with referral to and subsequent agreement by Full Council on 3rd March 2021. Subsequently, the Bridge Close Regeneration LLP Business Plan 2022/2023 was approved by Cabinet on 16th February 2022 and thereafter adopted by the Bridge Close Regeneration LLP.
1.3The Business Plan forms part of a comprehensive suite of project documents, including the Members’ Agreement, the Land Agreement, the Land Acquisition Strategy, the Security Agreement and the Loan Note Instruments, which amongst others, set out the strategy and the terms and conditions for provision of funding by the Council as principal Member of the Joint Venture (noting that a wholly owned company of the Council acts as second member of the JV). The Business Plan is a suite of strategy and policy documents, including a budget and financial model with detailed forecasts, which provides a management framework for delivering the vision and objectives for the regeneration of Bridge Close.
1.4In accordance with the Members’ Agreement, the Board of Bridge Close Regeneration LLP must prepare, issue and agree a draft Business Plan to the Council as Member. Once agreed, the draft Business Plan would replace the then current Business Plan as the formal Business Plan adopted by the Bridge Close Regeneration LLP. Cabinet, 7 February 2024
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MinutesMinutes | 10 pages | DownloadRead as text |
Follow Cabinet at Havering and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | AnnouncementsThe Chair outlined the procedures to be followed in the event of a fire alarm or any other emergency requiring the ev... | Decided | Open |
| 16 Sep 2026 | Apologies for absenceAll Cabinet members were in attendance. | Decided | Open |
| 16 Sep 2026 | Disclosures of InterestThere were no disclosures of interest. | Decided | Open |
| 16 Sep 2026 | MinutesThe minutes of the meetings held on 12 th August 2026 , were agreed as a correct record and the Chair signed them. | Agreed | Open |
| 16 Sep 2026 | Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary SchoolReport Title: Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary School ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.