Cabinet, Wednesday 22 January 2025 at 7.00pm

Approval to extend windows and doors contract

Agreed Executive 1 paper

Cabinet agreed this item on Wednesday 22 January 2025. Below is the council's own wording, with the papers it was decided on.

Item43

Resolved

Cabinet : Agreed to extend the contract with Equans Regeneration Limited to deliver windows and doors including fire doors to HRA properties for a period of one year at a maximum value of £7 million.
Word for word from the decision Havering published for this meeting. Source: democracy.havering.gov.uk

Follow this further

Built from Havering's papers

What the report saysPro

Report to Cabinet

Summary

As part of the Council’s responsibility as a landlord, the Council has a duty to undertake repairs and maintenance works to its HRA housing stock. The Council entered into contract with Equans Regeneration Limited to replace windows and doors. The original contract was for 3 years with 2 one-year optional extensions subject to performance. The Council has been satisfied with the performance and would like to activate an additional one-year extension to the original contract at a value of £7m. Monies have been identified within the HRA 30-year business plan and contract spend will be aligned with business priorities and approved budgets.

Recommendations

For the reasons set out in the report, Cabinet is recommended to;

a) Agree to extend the contract with Equans Regeneration Limited to deliver windows and doors including fire doors to HRA properties for a period of one year at a maximum value of £7 million.

Background

1.1Through the Asset Management System, Housing Services identified a Borough-wide need for window and door refurbishments. Following a competitive procurement process, the Council awarded a contract to Equans Regeneration Limited commencing on 14th June 2022 to carry out these works.

1.2The contract was originally awarded by the council for a three-year period, with an option for two additional one-year extensions. Its primary aim was to replace windows and doors across council-owned properties to meet the Decent Homes Standard, ensuring compliance with safety regulations and improving the security and aesthetics of these buildings.

1.3In addition to meeting the Decent Homes Standard, the contract was designed to support the council's long-term asset management strategy by improving the durability and energy efficiency of council-owned properties. The window and door replacements aimed to reduce maintenance costs over time and enhance energy conservation, contributing to the council’s sustainability goals and reducing utility costs for residents.

1.4In response to the Council's urgent needs, the contract also encompassed essential fire safety works, including the replacement of fire entrance doors to individual flats and communal fire doors in residential blocks. The value of the works under the contract was estimated to be up to £20 million. Cabinet, 22nd January 2025

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval to extend windows and doors contractReport 166 KB DownloadRead as text

More from Havering Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 AnnouncementsThe Chair outlined the procedures to be followed in the event of a fire alarm or any other emergency requiring the ev... Decided Open
16 Sep 2026 Apologies for absenceAll Cabinet members were in attendance. Decided Open
16 Sep 2026 Disclosures of InterestThere were no disclosures of interest. Decided Open
16 Sep 2026 MinutesThe minutes of the meetings held on 12 th August 2026 , were agreed as a correct record and the Chair signed them. Agreed Open
16 Sep 2026 Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary SchoolReport Title: Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary School ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies