Cabinet, Wednesday 9 April 2025 at 7.00pm

Building / Fire safety Works

Approved Executive 1 paper

Cabinet approved this item on Wednesday 9 April 2025. Below is the council's own wording, with the papers it was decided on.

Item75

Resolved

Cabinet: 1. Approved the procurement of a t wo- stage t ender process via Lot 1 of the Fusion 21 Refurbishment, Construction, New Build and Modular Buildings Framework for building safety remedial / improvement works to the Council’s high -r is k buildings , comprising Pre-Construction Services (Stage 1) and Works (Stage 2) , with a total indicative value of £ 1 3.4 million . 2. Approved a waiver of the Council’s default evaluation criteria of 70% Price: 30% Quality and instead award the contracts on the MEAT basis of a 60% Quality, 30% Price, and 10% Social Value weighting for the reasons set out in Section 4 of this report, Procurement Proposals. 3. Delegated the approval of the award of the Pre-Construction Services Agreement (Stage 1) and the works contract (Stage 2) to the Strategic Director of Place, acting in consultation with the Strategic Director of Resources and the Deputy Director of Legal & Governance . 4. Delegated the change of procurement route from a framework to a Dynamic Procurement system ( DPS ), if required , to the Strategic Director of Place.
Word for word from the decision Havering published for this meeting. Source: democracy.havering.gov.uk

Follow this further

Built from Havering's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Building / Fire safety WorksReport 316 KB Copy on its way

At this meeting

Whole meeting

On this subject at Havering

Search all
  1. Building / Fire safety WorksThis decision
  2. P0138.12 - 93-95 redden court road - demolition of fire damaged building and reconstruction of building incorporating 6 apartmentsDecided

More from Havering Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 AnnouncementsThe Chair outlined the procedures to be followed in the event of a fire alarm or any other emergency requiring the ev... Decided Open
16 Sep 2026 Apologies for absenceAll Cabinet members were in attendance. Decided Open
16 Sep 2026 Disclosures of InterestThere were no disclosures of interest. Decided Open
16 Sep 2026 MinutesThe minutes of the meetings held on 12 th August 2026 , were agreed as a correct record and the Chair signed them. Agreed Open
16 Sep 2026 Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary SchoolReport Title: Implementation of a School-Based Nursery and expansion of the SEND Unit at R J Mitchell Primary School ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies