Resolved
That the Minutes of the meeting held on 1st April 2003 be approved as a correct record and signed by the Chairman.
Strategic Monitoring Committee approved this item on Monday 7 July 2003. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Minutes of the meeting held on 1st April 2003 be approved as a correct record and signed by the Chairman.
COUNTY OF HEREFORDSHIRE DISTRICT COUNCIL
MINUTES of the meeting of the Strategic Monitoring Committee held at Brockington, 35 Hafod Road, Hereford on 1 April 2003 at 2.00 pm. Present: Councillor R.J. Phillips (Chairman) Councillor Mrs. J.P. French (Vice-Chairman)
Councillors: B.F. Ashton, [name removed].O. Barnett, [name removed], R.V. Stockton, J. Stone, J.P. Thomas
In attendance: Councillors CE Grover – Cabinet Member (Environment), TM James – Leader of the Council.
88. APOLOGIES FOR ABSENCE
There were no apologies for absence.
89. DECLARATIONS OF INTEREST
There were no declarations of interest made.
90. MINUTES
RESOLVED: That the Minutes of the meeting held on 10th February, 2003 be approved as a correct record and signed by the Chairman.
91. BEST VALUE REVIEW OF HUMAN RESOURCES – STAGE 4 REPORT
Further to its consideration of the Stage 3 report in October 2002 the Committee was asked to consider the Improvement Plan resulting from the Best Value Review of Human Resources.
The Interim Head of Human Resources presented the Improvement Plan. He outlined the consultation undertaken within the Council and the contribution made by Bulmers as the external experts. The improvement plan identified six improvement areas and set out actions to achieve the targets set out for each area.
In the course of discussion the following principal points were made:
• It was suggested that, as drafted, it was difficult to see how progress towards achieving the targets set out in the Plan could be monitored. In reply the Interim Head of Human Resources commented that the targets in the Improvement Plan did not readily lend themselves to measurement. A number of statistical measures were included in other documents in particular the Human Resources Strategy.
• The proposals for regular briefings for Members were welcomed. It was suggested that consideration still needed to be given to enhancing Member involvement in and oversight of human resources issues.
• That there was an absence of any costings. In response it was acknowledged that whilst there were Service Level Agreements with Directorates the issue of costs would be addressed as part of the Plan. STRATEGIC MONITORING COMMITTEE 1ST APRIL, 2003
• That the question of outsourcing would be a matter for future consideration. The focus at this stage had been on reshaping the service so that it would be able to respond to the challenges presented by any future review along those lines.
• In relation to the recommendation that the Head of Human Resources should be located at Brockington the Chief Executive confirmed that this would be a matter he would wish to discuss with the Head of Human Resources when appointed.
RESOLVED: That the Improvement Plan be noted.
92. TRANSPORT CROSS-SERVICE REVIEW IMPLEMENTATION TARGETS AND MILESTONES
Further to its request in February the Committee was informed of the key targets and milestones to be achieved in implementing the recommendations of the transport cross-service review.
The Director of Environment reported on progress and reiterated why for practical reasons a revised policy towards discretionary transport, if approved, could not be implemented before September 2005.
RESOLVED: That the targets and milestones for the implementation of the transport cross-service review be endorsed.
93. WORK PROGRAMMES
The Committee considered the work programmes adopted by the individual Scrutiny Committees.
It was reported that a number of additions had been made to its programme by the Education Scrutiny Committee at its meeting on 26th March. It was noted that the work programmes would provide a suggested basis for scrutiny work over the rest of the year. Account would need to be taken in due course of any amendments to the Council’s Constitution, for example, any change to the role of programme panels.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MINUTESMinutes | 83 KB | DownloadRead as text |
Follow Strategic Monitoring Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Dec 2009 | MINUTESThat the Minutes of the meeting held on 2 December 2009 be confirmed as a correct record and signed by the Chairman. | Decided | Open |
| 2 Dec 2009 | Accommodation strategyThat: the development of the Joint Accommodation Strategy be endorsed, whilst highlighting the importance of close wo... | Decided | Open |
| 2 Dec 2009 | Integrated corporate performance reportThat (a) the report and points raised by the Committee be noted; and (b) performance against a range of education att... | Noted | Open |
| 2 Dec 2009 | Budget monitoring report 2009It was agreed that a briefing note would be provided. · The number of debts written off was questioned. The Director ... | Agreed | Open |
| 2 Dec 2009 | Scrutiny of external communicationThat (a) the scoping statement for the review as appended to the report be approved as the basis for the review, subj... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.