ENVIRONMENT SCRUTINY COMMITTEE 23RD JANUARY, 2004
HIGHWAY MAINTENANCE Report By: Director of Environment
Wards Affected County wide
Purpose To consider the performance of the Highway Maintenance Service since the completion of the Best Value Inspection Review in 2002.
Reasons In March 2002 a Best Value Inspection of Highway Maintenance concluded that the service was rated as Fair with uncertain prospects of improvement. A series of performance improvements have since been implemented to address the issues raised in the inspection. A review of performance was agreed as part of this Committee’s programme for 2003/04.
Considerations 1. In March 2002 the Audit Commission carried out a Best Value Inspection of the Council’s Highway Maintenance Service. A Best Value Review of the service had been completed in 2001 and an Improvement Plan produced to address the issues identified.
2. At the time of the inspection the condition of Herefordshire’s highways was poor, reflecting the historical under-investment in maintenance inherited from the predecessor authority. That investment pattern had continued until 2001/2002 when additional capital funding was allocated as part of the Government’s Local Transport Plan settlement. The settlement supported the Government’s national transport targets which included the achievement of halting the deterioration in local road condition by 2004 and eliminating the maintenance backlog by 2010.
3. The Council’s policies for Highway Maintenance are set out in the Highway Maintenance Plan. The Local Transport Plan 2001/02 – 2006/07 describes the strategy for managing the highway network and contains estimates of the maintenance funding requirements. When the LTP was published in July 2000, the backlog of highway maintenance was estimated to be £26 million, with an annual funding requirement of £14.1 million for a “standstill” position. To eliminate the backlog over 10 years would raise this to £16.7 million each year. These figures exclude bridge maintenance. In 2003/04, the highway maintenance budget is £11.3 million.
4. Among the recommendations of the Best Value Inspection were:
The development of an effective performance management and monitoring culture within the Service;
Links between the Highway Maintenance Plan and the Local Transport Plan;
Linking actions in the Improvement Plan to individual targets and monitoring of progress
Further information on the subject of this report is available from Stephen Oates, Head of Engineering and Transportation on (01432) 260780 EnvScrutinyCommitteeJan04HihgwayMaintenance0.doc ENVIRONMENT SCRUTINY COMMITTEE 23RD JANUARY, 2004
The use of consistent and recorded methods of prioritising work
Sharing good practice
Setting clear service standards and making these known to the public.
5. Substantial progress has been made since then in addressing these identified weaknesses, in particular:
A new Highway Maintenance Plan published in 2003, setting out service standards, linkages to other Council policies and containing details of forthcoming maintenance schemes. The Plan will be republished later this year with details of the annual programme for 2004/05;
The Best Value Improvement Plan was revised to incorporate the recommendations of the Best Vale Inspection and to include more details of targets;
The creation of the new Partnership for service delivery between the Council, Herefordshire Jarvis Services and Owen Williams. The Partnership agreements contain specific performance targets to drive continual improvement of the service. Performance is monitored through mechanisms set out in the agreements;
The Council has joined the Midlands Benchmarking Group (for highways and transportation) and the National Highway Maintenance Benchmarking Club;
Annual maintenance programmes targeted at defined improvements in highway condition, set out in the Local Public Service Agreement (LPSA);
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HIGHWAY MAINTENANCEReport | 69 KB | DownloadRead as text |
Follow Environment Scrutiny Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Feb 2011 | MINUTESThat subject to including the above additional wording the minutes of the meeting held 26 November 2010 were confirme... | Decided | Open |
| 28 Feb 2011 | Road over Rail BridgesThat a) the position set out in the report be noted ; and b) in view of the public safety, site security and visual u... | Noted | Open |
| 28 Feb 2011 | Introduction to Emergency Preparedness Planning for Flooding in HerefordshireThat the Committee supported the work undertaken in the development of the Herefordshire Multi-Agency Flood Plan (MAF... | Decided | Open |
| 28 Feb 2011 | Capital Budget MonitoringThat the position set out in the Capital Budget report be noted. | Noted | Open |
| 28 Feb 2011 | Revenue Budget MonitoringThat the position set out in the Revenue Budget report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.