DCCW2004/1308/RM - VACANT FIELD, ADJACENT TO THREE ELMS ROAD, NORTH OF BONINGTON DRIVE, WHITECROSS, HEREFORD (AGENDA ITEM NO. 6)
ApprovedPlanning1 paper
Central Area Planning Sub-Committee approved this item on Wednesday 30 June 2004. Below is the council's own wording, with the papers it was decided on.
Subject to the receipt of further information and any required additional amended plans, Officers named in the Scheme of Delegation to Officers, in consultation with the Local Ward Members, be authorised to approve this reserved matters application following any necessary reconsultation with conditions as considered necessary by Officers.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
CENTRAL AREA PLANNING SUB-COMMITTEE 30TH JUNE, 2004
DCCW2004/1308/RM - A NEW SECONDARY SCHOOL (1 SINGLE AND TWO 2-STOREY TEACHING BLOCKS) WITH ASSOCIATED SPORTS FIELDS, HARD COURTS, CAR PARKING AND ASSOCIATED LANDSCAPING AT VACANT FIELD, ADJACENT TO THREE ELMS ROAD, NORTH OF BONINGTON DRIVE, WHITECROSS, HEREFORD
Date Received: 28th April 2004 Ward: Three Elms Grid Ref: 48841, 41417 Expiry Date: 23rd June 2004 Local Members: Councillors [name removed].A. Andrews, [name removed].P.A. Daniels and [name removed].M. Toon
1. Site Description and Proposal
1.1The application site consists of 6.75 hectares of open agricultural land on the western side of Three Elms Road, Hereford. To the east and north the site is bounded by areas of protected open countryside and the Yazor Brook. To the south of the site the established residential areas on Bonington Drive and Pentland Gardens. The site also adjoins the former Bulmers playing field beyond Pentland Gardens.
1.2This application seeks reserved matters approval following the granting of outline planning permission under reference CW2003/2113/O on the 5th January 2004. All matters which include external appearance, means of access, siting, design and landscaping are considered as part of this application given that they were all previously reserved for consideration at the outline stage. The outline planning application was accompanied by an Environmental Statement in accordance with the Environmental Impact Assessment Regulations (1999) and included a Flood Risk Assessment, Transport Assessment and Planning Statement.
1.3The detailed scheme submitted shows a full site layout with the main school buildings being sited towards the central and northern parts of the application site. Vehicular access is provided off Three Elms Road at only one point and would include a drop-off facility for school buses. Eighty seven car parking spaces are indicated which would be sited on land immediately to the north of Bonington Drive. An all weather football/hockey pitch is also proposed close to the site entrance point adjoining Three Elms Road. The main school complex is split between two linear blocks which are sited approximately 120 metres off the Three Elms Road. This setback position allows for the significant level of services, and potential flood storage area in the northeastern part of the site which adjoins Three Elms Road. The proposed school building are in the main two storeys in height and have been designed and laid out to maximise energy efficiency and sustainability from the development. The proposed buildings will be finished with a mixture of Cedar boarding and through coloured render systems to the walls and will include a Sedum roof (green roof to mitigate the loss of green open
Further information on the subject of this report is available from [name removed].J. MacPherson on 01432 261946 CENTRAL AREA PLANNING SUB-COMMITTEE 30TH JUNE, 2004
space from the site) and also recycled aluminium standing seam roofing which will contain high insultation values as part of the sustainability agenda.
1.4The main pedestrian and cycle route to the school is located immediately to the north of the all weather football and hockey pitch and is some 140 metres away from the main vehicular access to the site.
1.5The layout of the site enables a significant amount of sport and playing field facilities to provide a buffer between the established residential areas to the south of the site and the main school complex.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Central Area Planning Sub-Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.