THAT (a)the results of the Herefordshire Housing Land Study 2004 and Employment Land Study 2003-2004 be noted; (b) the Herefordshire Housing Land Study 2004 and Employment Land Study 2003-2004 be published as a record of the housing and employment land position in the County.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
HEREFORDSHIRE HOUSING LAND STUDY 2004 AND EMPLOYMENT LAND STUDY 2004 Report By: Forward Planning Manager
Wards Affected County-wide
Purpose 1. To present to members the results of the Herefordshire Housing Land and Herefordshire Employment Land Studies 2004.
Financial Implications 2. None.
Background 3. As part of the changes to the planning system brought about by the Planning and Compulsory Purchase Act 2004 there is a requirement for the Council to prepare an annual monitoring report to Government on progress in preparing the documents set out in the Local Development Scheme (LDS), and on how far planning policies are being achieved. The content of the Annual Monitoring Report (AMR) will be developed over time to meet the requirements of the new system and will involve consideration of the report by Cabinet via the Planning Committee.
4. An important part of the AMR will be the presentation of evidence regarding the extent to which policies within Local Development Documents are being achieved and in particular it will be necessary that the AMR will report on the number of dwellings built in Herefordshire during the period.
5. A considerable amount of monitoring is already undertaken within the Council and this is provided to the Regional Planning Body to present in its annual monitoring report. In addition a report outlining the results of the annual Housing Land Study has been presented for information purposes to the Planning Committee each year since 1999.
6. This year the Housing Land Study has again been prepared and as a precursor for future AMR’s an Employment Land Study for Herefordshire has also been prepared for publication. In addition to presenting an indication of land available in the County these documents can help to assess the success of the Council’s planning policies in respect of housing and the provision of employment land and will prove valuable as background information for the forthcoming Public Inquiry into objections to the Unitary Development Plan. Full copies of both documents are attached to this report.
Housing Land Study 7. The study involved a survey of all planning permissions for new housing in the County. The numbers of dwellings built, under construction and not started on each permission
Further information on the subject of this report is available from [name removed] on 01432 260137
It13HerefordshireHousingLandStudy2004ANDEmploymentLandStudy200340.doc PLANNING COMMITTEE 26TH NOVEMBER 2004
have been recorded. The study also examines other features of housing supply and its characteristics.
8. Some 661 dwellings have been built in the County during the 12 months from April 2003 to the end of March 2004. This is an increase from 622 completions recorded in last years study although it is below the average rate experienced in the past 12 years.
9. The number of housing commitments in the County have continued to hold up with 1817 units having planning permission or being identified in adopted local plans.
10. During the first eight years of the UDP period 6,758 houses have been built in the County with just over half (53%) taking place in urban areas. In terms of the proposed UDP strategy these completions have been distributed as follows:
Location Actual Completions Anticipated % completions 1996-2004 1996-2011 Hereford City 1571 (23.2%) 27% Market Towns Total 2041 (30.2%) 29% Main Villages 1933 (28.6%) 26% Smaller Settlements 479 (7.1%) 7% Other rural areas 734 (10.9%) 11%
Development on previously-developed land
11. Over the 8-year period the percentage of housing built on previously-developed land has averaged at 43%. This year the study shows that in terms of completions 69% of all new dwellings in the County were on previously-developed (brownfield) land. Looking to the future, 77% of all dwellings given planning permission on new sites between April 1st 2003 and March 31st 2004 were on previously-developed land.
Conversions
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.