Resolved
That the minutes for the meeting held on 13th June 2005, be approved as a correct record and signed by the Chairman.
Community Services Scrutiny Committee approved this item on Wednesday 5 October 2005. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes for the meeting held on 13th June 2005, be approved as a correct record and signed by the Chairman.
COUNTY OF HEREFORDSHIRE DISTRICT COUNCIL MINUTES of the meeting of Community Services Scrutiny Committee held at Committee Room No. 1 Shirehall, Hereford on Monday, 13th June, 2005 at 6.00 p.m.
Present: Councillor A.C.R. Chappell (Chairman) Councillor H. Bramer (Vice Chairman)
Councillors R.B.A. Burke, M.R. Cunningham, [name removed].P.A. Daniels, J.G.S. Guthrie, B. Hunt, D.C. Taylor, P.G. Turpin and A.L. Williams
Co-opted Members G. Jones (Tourism Sector) and [name removed] (Herefordshire Association of Local Council's)
In attendance: Councillors [name removed].A. Andrews, [name removed].D. Lloyd-Hayes, J. Stone and R.M. Wilson
1. APOLOGIES FOR ABSENCE
Apologies were received from [name removed] and [name removed].
2. NAMED SUBSTITUTES
There were no named substitutes.
3. DECLARATIONS OF INTEREST
Name Item Interest Councillor Mrs. P.A. Andrews 6 – Castle Green Regeneration Personal Project Councillor Mrs. M.D. Lloyd- 8 – Youth Service Personal Hayes
4. MINUTES
RESOLVED: That the minutes for the meeting of the former Social and Economic Development Scrutiny Committee held on 22nd March 2005, be approved as a correct record and signed by the Chairman.
5. SUGGESTIONS FROM MEMBERS OF THE PUBLIC ON ISSUES FOR FUTURE SCRUTINY
The Chairman invited the members of the public present to suggest items for the Committee to scrutinise in the future.
Following a suggestion that the Committee scrutinise the County’s Museums the Committee agreed to note the suggestion and consider adding it to its work programme. COMMUNITY SERVICES SCRUTINY COMMITTEE MONDAY, 13TH JUNE, 2005
6. CASTLE GREEN REGENERATION PROJECT
Members were advised on the current position in respect of the Hereford Castle Green Regeneration Project.
The Parks and Countryside Manager informed the Committee of a number of initiatives to regenerate the Castle Green area in light of the decision not to proceed with a Heritage Lottery Fund (HLF) bid for park restoration. These initiatives amounted to over £1m and included cleansing the Castle Pool, renovation of the Victoria footbridge, refurbishment of the public toilets and other smaller scale funding bids.
The HLF bid had been withdrawn for a number of reasons, which included:
• High cost of preparing a bid. • A less than 50% chance of a successful outcome. • Other corporate priorities. • A possibly compromising situation with HLF. Both the Cathedral Close project and Friar Street Heritage Resource and Learning Centre are set to make bids to HLF.
The Parks and Countryside Manager reported that £30,000, which was going to be used to fund feasibility work for the HLF bid, had now been redirected towards minor improvements on the Castle Green including the refurbishment of Nelson’s Column in time for the bicentenary celebrations of the Battle of Trafalgar.
With regard to the cleansing work due to be undertaken at the Castle Pool, the Parks and Countryside Manager highlighted the number of outside agencies consulted and extensive preparation work that had delayed the cleansing project. After much behind the scenes work he now anticipated the work taking place over a two-week period in autumn 2005.
The Committee was informed that the toilet block refurbishment at the Castle Green was the responsibility of the Highways and Transportation Department. The block was scheduled to be refurbished during 2006/07.
The Chairman welcomed invitees from Friends of Castle Green, Castle Street and District Residents Association and St. James and Bartonsham Community Association. He thanked them for accepting his invitation to attend the meeting and gave them the opportunity to present their comments on the Castle Green Regeneration Project to the Committee.
The following are the principal points from the ensuing discussion:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MINUTESMinutes | 75 KB | DownloadRead as text |
Follow Community Services Scrutiny Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Mar 2011 | MINUTESThat the minutes for the meeting held on 11 February 2011, be approved as a correct record and signed by the Chairman. | Approved | Open |
| 7 Mar 2011 | Budget Monitoring 2010/11That the report be noted. | Noted | Open |
| 7 Mar 2011 | Performance out-turn to end of december 2010THAT: (a) the report be noted; and ; (b) areas of concern continue to be monitored. | Noted | Open |
| 7 Mar 2011 | Committee Work ProgrammeThat the work programme be approved and reported to the Overview and Scrutiny Committee. | Approved | Open |
| 11 Feb 2011 | MINUTESThat the minutes for the meeting held on 13 January 2011 be approved as a correct record and signed by the Chairman. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.