DCCE2005/3706/RM - Former SAS Camp, Land Off Bullingham Lane, Hereford, HR2 7EW [AGENDA ITEM 11]
AgreedPlanning1 paper
Central Area Planning Sub-Committee agreed this item on Wednesday 8 February 2006. Below is the council's own wording, with the papers it was decided on.
Subject to no further objections raising additional material planning considerations by the end of the consultation period, Officers named in the Scheme of Delegation to Officers be authorised to issue planning permission subject to the following conditions/notes and any additional conditions/notes considered necessary by Officers. 1. E17 (No windows in side elevation of extension) (southern elevation of plots 12, 13, 18 and 21). Reason: In order to protect the residential amenity of adjacent properties. Informatives: 1. N15 - Reason(s) for the Grant of PP/LBC/CAC. 2. The applicant's attention is drawn to the Conditions attached to Outline Planning Permission reference CE2001/2757/O which require further details to be submitted and agreed prior to commencement of the development. 3. N02 - Section 106 Obligation. 4. The applicant is advised ... view the full minutes text for item 141.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
CENTRAL AREA PLANNING SUB-COMMITTEE 8TH FEBRUARY, 2006
11 DCCE2005/3706/RM - PROPOSED 2, 3 AND 5 BEDROOM MIXED RESIDENTIAL DEVELOPMENT FOR 21 DWELLINGS WITH ASSOCIATED ACCESSES AND GARAGING AT FORMER SAS CAMP, LAND OFF BULLINGHAM LANE, HEREFORD, HR2 7EW
For: George Wimpey South West, Copse Walk, Cardiff Gate Business Park, Pontprennah, Cardiff
Date Received: 15th November, 2005 Ward: St. Martins & Grid Ref: 50749, 38081 Hinton Expiry Date: 10th January, 2006 BVPI Expiry Date: 14th February, 2006 Local Members: Councillors [name removed].U. Attfield, A.C.R. Chappell and R. Preece
1. Site Description and Proposal
1.1The site is located on the southern side of Bullingham Lane (unclassified road 82300) and forms part of the land formerly associated with the SAS Camp known as Bradbury Lines. Immediately south of the site are existing semi-detached properties which front on to Redhill Avenue and Bullingham Lane and land to the north has now been developed for new housing forming part of Phase 1 of the overall development. The southern boundary of the site bordering existing residential properties is largely enclosed by a combination of fencing and mature hedging. Levels within the site are generally flat with the exception of the eastern corner which is raised slightly above the adjoining road level.
1.2Outline planning permission for a mixed use development to provide housing, open space, community and local retail facilities was issued on 10th February 2005 following Committee approval in December 2003. The master plan associated with the outline proposed that the site as a whole would be developed in three phases, two permissions totalling 160 dwellings were approved in June 2004 comprising Phase 1 and a further two permissions were approved last summer for 135 and 129 dwellings comprising Phases 2A and 2B. This application is identified within the outline master plan as being under Phase 2 and therefore comprises Phase 2C, the last Phase under Phase 2.
1.3The application is for the construction of 21 dwellings and apartments. It includes details of the siting, design and external appearance of the properties along with the landscaping, internal infrastructure and associated vehicle parking areas. The housing mix is as follows:
Further information on the subject of this report is available from [name removed] on 01432 261957 CENTRAL AREA PLANNING SUB-COMMITTEE 8TH FEBRUARY, 2006
ENV 14 – Design ENV 16 – Landscaping H3 – Design of new residential developments H4 – Residential roads H6 – Amenity, open space and smaller schemes H8 – Affordable housing H12 – Established residential areas, character and amenity H14 – Established residential areas, site factors T11 – Pedestrian provision T12 – Cyclist provision T13 – Pedestrian and cycle routes
Herefordshire Unitary Development Plan (Revised Deposit Draft)
S1 – Sustainable development S2 – Development requirements S3 – Housing S6 – Transport DR1 – Design DR2 – Land use and activity DR3 – Movement H1 – Hereford and the market towns, settlement boundaries and established residential areas H2 – Hereford and the market towns, housing land allocations H9 – Affordable housing H13 – Sustainable residential design H15 – Density H16 – Car parking H19 – Open space requirements T6 – Walking T7 – Cycling T11 – Parking provision
3. Planning History
CE2001/2757/O - Site for mixed use development to provide housing, open space, community and local retail uses at land at Bradbury Lines, Bullingham Lane. Outline planning approved 10th February, 2005.
4. Consultation Summary
Statutory Consultations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Central Area Planning Sub-Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.