Resolved
That the report of the meetings of the Hereford and Worcester Fire and Rescue Authority which were held on 15th December, 2005 and 15th February, 2006 be received.
COUNCIL 10TH MARCH, 2006
REPORT OF THE HEREFORD & WORCESTER FIRE AND RESCUE AUTHORITY TO THE CONSTITUENT AUTHORITIES Meetings Held on 15 December 2005 and 15 February 2006.
OPERATIONAL ACTIVITY
1. During the period 1 April 2005 to 31st January, 2006 the Service attended a total of 7851 incidents. (This includes all types of Fire, All False Alarms and Special Service Incidents). More statistics and details of notable incidents have been reported to the Authority and can be found on the Service’s website (www.hwfire.org.uk).
INTEGRATED RISK MANAGEMENT PLAN
2. The Constituent Authorities have previously been advised of the requirement under the Fire and Rescue National Framework that all Fire and Rescue Services must produce an Integrated Risk Management Plan (IRMP) and associated annual action plans. The purpose of the Plan is to provide a strategic overview of all aspects of service delivery and determine current and future policy. It is intended to make the service more responsive to locally identified needs and better able to deliver community safety. Plans must undergo a full public consultation process for twelve weeks before being adopted by the Authority.
3. In September 2005 the Authority approved a draft Plan for consultation covering the period 2006-09. A number of modifications were made to the Plan in response to replies made during the consultation process.
4. The main themes of the proposals in the Plan remain: • Strengthen capacity to improve community safety and reduce risk; • Ensure that operational resources are best aligned to areas of greatest risk and need; • Realign management resources in order to improve support to frontline services. • Update incident command structures and arrangements to assess operational performance; • Provide improved support to Fire Stations in rural areas and those Firefighters who work the retained duty system; • Prepare for anticipated changes to fire safety legislation and enforcement, principally the Regulatory Reform (Fire Safety) Order; and • Ensure that Fire Stations are appropriately located and have the necessary facilities to provide an efficient, effective and economic service in compliance with statutory duties. BUDGET 2006/07
5. The Authority has set a budget which enables the requirements of the Integrated Risk Management Plan to be met. The Authority’s Net Budget Requirement is £27.061 million. The effect on the precept is to give a Band D Tax rate of £61.95 representing a 4.9% increase on 2005/06. (This is an increase of £2.90 a year.)
CouncilreportFRAFebruary20060.doc 6. In setting this budget the Authority has noted the effects of the “damping” mechanism the Government has put in place to smooth the effects of the introduction of new formula grant arrangements. This has resulted in the Authority receiving £0.442 million (4.2%) less than it was entitled to on the basis of the formula grant calculation.
7. The Authority now receives the lowest government grant per citizen of any Fire and Rescue Authority and receives only 75% of the average for precepting Fire and Rescue Authorities.
REGIONAL FIRE CONTROL CENTRE
8. The Constituent Authorities have previously been advised of the replacement of the existing 46 local Fire Service control rooms across the Country with 9 regional control centres by the end of 2009. The Regional Fire Control for the West Midlands is to be located in Wolverhampton, the expectation being that the new Centre will be operational by 2009.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HEREFORD & WORCESTER FIRE AND RESCUE AUTHORITYReport | 52 KB | DownloadRead as text |
Follow Council at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Oct 2026 | MINUTESThat the minutes of the meeting held on 24 July be confirmed as a correct record and signed by the Chairman. | Decided | Open |
| 9 Oct 2026 | Constitutional updatesRESOLVED – a. That Council notes the requirements to change the terms of the Planning and Regulatory Committee in res... | Approved | Open |
| 9 Oct 2026 | Notices of motion under standing ordersRESOLVED – that: Statutory Council meetings to which the public have access are held during the normal working day. T... | Decided | Open |
| 24 Jul 2026 | MINUTESThat the minutes of the meeting held on 22 May 2026 be confirmed as a correct record and signed by the Chairman. | Decided | Open |
| 24 Jul 2026 | Notices of motion under standing ordersRESOLVED – that: Council notes that: 1. Herefordshire has demonstrated its solidarity with the people of Ukraine sinc... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.