Resolved
That the report be noted.
Environment Scrutiny Committee noted this item on Monday 27 March 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
ENVIRONMENT SCRUTINY COMMITTEE 27 MARCH 2006
BEST VALUE REVIEWS – IMPLEMENTATION OF IMPROVEMENT PLANS Report By: Environment Support Manager
Wards Affected County-wide
Purpose 1 To report the remaining actions and the exceptions to the programmed progress in the improvement plans resulting from the reviews of Commercial Enforcement Development Control and Public Conveniences.
Financial Implications 2 There has been no variation to the financial implications identified in the individual Improvement Plans.
Background 3 In response to comments from Members and Officers, the reporting arrangements have been developed by consolidating the reports and only reporting on exceptions to the programmed actions. That is, where actions have been completed earlier than programmed or where the timetable has not been met.
4 Appendix 1 of this report covers the following improvement plans:
• Public Conveniences
• Development Control
• Commercial Enforcement
Appendix 1 also includes progress updates on the Development Control Action Plan and the Peer Assessment of Trading Standards.
RECOMMENDATION THAT Members note and comment on, where appropriate, the implementation of the improvement and action plans.
BACKGROUND PAPERS • None identified.
Further information on the subject of this report is available from Peter Cross, Environment Support Manager on 01432 260099
BVImprovementPlanReportMarch2006RF0.doc ENVIRONMENT SCRUTINY COMMITTEE 27 MARCH 2006
Further information on the subject of this report is available from Peter Cross, Environment Support Manager on 01432 260099
BVImprovementPlanReportMarch2006RF0.doc APPENDIX 1 PROGRESS ON IMPROVEMENT PLANS
PUBLIC CONVENIENCES BEST VALUE REVIEW Priority Outcome Action Milestones Officer(s) By When Progress to the Indicator for end of Jan Improvement High Improved provision of Refurbishment programme in Tenbury Road, HOS To be Tenbury Road Public Priority – facilities progress Bromyard scheduled for completed completed. perception Property 2003/5 Summer 2005. 2004/5 Programme 06/07 indicator under review. Accelerated closure programme to be agreed.
DEVELOPMENT CONTROL BEST VALUE REVIEW Priority Outcome Action Milestones Officer(s) By When Progress to the Indicator for end of Jan Improvement High Improved quality and Review and update current Adopt Manual for Team December 2003 Draft consultation accessibility of highways Highway Design Guide Streets when published Leader period completed. design advice by DfT in November Transportat 2005 ion Date revised to Meeting with BV109 – Improved speed of July 2005 Forward Planning Determine applications processing th 8 March 2006 to applications and responsiveness of determine next within 8/13 service steps in relation to weeks SPD - Revised publication date subject to SPD requirements
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BEST VALUE REVIEWS: IMPLEMENTATION OF IMPROVEMENT PLANSPlan | 75 KB | DownloadRead as text |
Follow Environment Scrutiny Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Feb 2011 | MINUTESThat subject to including the above additional wording the minutes of the meeting held 26 November 2010 were confirme... | Decided | Open |
| 28 Feb 2011 | Road over Rail BridgesThat a) the position set out in the report be noted ; and b) in view of the public safety, site security and visual u... | Noted | Open |
| 28 Feb 2011 | Introduction to Emergency Preparedness Planning for Flooding in HerefordshireThat the Committee supported the work undertaken in the development of the Herefordshire Multi-Agency Flood Plan (MAF... | Decided | Open |
| 28 Feb 2011 | Capital Budget MonitoringThat the position set out in the Capital Budget report be noted. | Noted | Open |
| 28 Feb 2011 | Revenue Budget MonitoringThat the position set out in the Revenue Budget report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.