That consideration of the application be deferred pending a site inspection on the following grounds. (a) the character or appearance of the development itself is a fundamental planning consideration; (b) a judgement is required on visual impact; and (c) the setting and surroundings are fundamental to the determination or to the conditions being considered. In accordance with the criteria for public speaking, [name removed] an objector and [name removed] the applicant’s agent deferred their right to speak until the next meeting.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
Date Received: Ward: Ledbury Grid Ref: 70730, 38828 Expiry Date: Local Member: Councillor P Harling and Councillor D Rule
1. Site Description and Proposal
1.1The application site lies on the western side of the Bromyard Road (B4214), on the northern side of Ledbury. It has an area of approximately one hectare. The land slopes downwards from the road in a westward direction. The site is currently cleared and vacant. Immediately to the north of the application site is a large fruit storage and packing facility building operated by Wye Fruit Ltd. To the south of the application site is a research facility. On the opposite site of the road (east) are four residential properties. One of these dwellings, 'Orchard Cottage', is operated as a guesthouse. These properties are set back a considerable distance from the road at a higher ground level.
1.2The proposal involves the following elements: -
The erection of three tanks for the transfer of fuel oils. These tanks would be sited in excess of 60 metres from the road in a central position upon the site such that a gap of 15 metres would be maintained with the northern boundary and a gap of 21 metres would be maintained with the southern boundary. These tanks would be aligned along a north-south axis. Two of the tanks would have a diameter of 10 metres and one would have a diameter of 8 metres. These seven metre high tanks would be set below existing ground level within an impervious bund such that their height above existing ground level would not exceed 6 metres. The fuel proposed to be stored is: -
a) Domestic burning oil (kerosene) 540 m3 b) DERV (Diesel-engined road vehicle oil) 350m3 c) Gas oil ("agricultural" or "red" diesel) 540m3
1.3The potential maximum volumes of oil held temporarily in the tanks will be adequate for approximately three days supply. In this respect it is short-term oil storage rather than a long-term storage facility.
1.4The tank walls will be manufactured of steel and painted in an appropriate colour.
Further information on the subject of this report is available from [name removed] on 01432 261803 NORTHERN AREA PLANNING SUB-COMMITTEE 14TH JUNE 2006
1.5The erection of a flat-roofed site office measuring 20.05 metres in width and 14.64 metres in depth. The height of this building would be 3.74 metres. It would be sited some 32 metres south of the highway and set in some 6 - 9 metres from the southern boundary.
1.6The provision of a new vehicular access onto the Bromyard Road. This would be set in 10.4 metres from the southern boundary of the site. There would be a barrier set into the site allowing vehicles to manoeuvre - off the public highway prior to entering the operational site. Twenty five on-site car parking spaces would be provided. In addition, provision would be made for the parking of sixteen rigid tankers. A one-way traffic system would be operational within the site for safety and operational reasons.
1.7A covered cycle shed store would be provided
1.8The plan shows large areas available for landscaping, especially on the eastern and western ends of the site where appropriately graded landscaped bunds would be provided.
2. Policies
2.1Malvern Hills District Local Plan 1998
Environment Policy 1 – Location of Development Environment Policy 3 – Environmental Assessment Environment Policy 6 – External Lighting Details Environment Policy 9 – Flood Defence Environment Policy 10 – Protection of Groundwater Supplies Environment Policy 11 – Water Pollution Prevention Environment Policy 12 – Disposal of Foul Sewage, Trade Effluent and Surface Water Employment Policy 2 – The Retention of Existing Industrial Land Transport Policy 3 – Provision for Pedestrians and Cyclists Transport Policy 8 – Car Parking and Servicing Requirements
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Northern Area Planning Sub-Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.