UPDATE ON THE COUNCIL'S STATEMENT ON INTERNAL CONTROL

Noted Finance 1 paper

Audit and Corporate Governance Committee noted this item on Friday 22 September 2006. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

That the Report be noted and the actions endorsed.
Word for word from the decision Herefordshire published for this meeting. Source: councillors.herefordshire.gov.uk

Follow this further

Built from Herefordshire's papers

What the report saysPro

Report to Audit and Corporate Governance Committee

AUDIT AND CORPORATE GOVERNANCE COMMITTEE 22ND SEPTEMBER, 2006

UPDATE ON THE COUNCIL’S STATEMENT ON INTERNAL CONTROL Report By: Principal Audit Manager

Wards affected County-wide

Purpose To note the outcome of the Audit Commission’s review of the Council’s 2005/6 Statement on Internal Control.

Financial Implications None

Recommendation THAT the report be noted and the actions endorsed.

Reasons 1. The CPA Use of Resources highlights the criteria for judgement in relation to the Statement of Internal Control as follows:

• An appropriate member group has responsibility for review and approval of the Statement of Internal Control (SIC) and considers it separately from the accounts. (Level 2)

• The Council has conducted an annual review of the effectiveness of the system of internal control and reported on this in the Statement of Internal Control. (Level 2)

• The sources of assurance to support the Statement of Internal Control have been identified and are reviewed by senior officers and members. (Level 2)

• There are action plans in place to address any significant internal control issues reported in the Statement of Internal Control. (Level 2)

• The Council has put in place an assurance framework that maps the council’s strategic objectives to risks, controls and assurances. (Level 3)

• The assurance framework provides members with information to support the Statement of Internal Control. (Level 3)

• The assurance framework is fully embedded in the Council’s business process. (Level 4)

Further information on the subject of this report is available from Tony Ford (Principal Audit Manager) on 01432 260425 SICupdatereport0.doc AUDIT AND CORPORATE GOVERNANCE COMMITTEE 22ND SEPTEMBER, 2006

• The Council can demonstrate corporate involvement in/ownership of the process for preparing the Statement of Internal Control. (Level 4)

Considerations 2. The Corporate Management Board at their meeting on 19th June 2006 reviewed and commented on the evidence used to support the Council’s Statement on Internal Control. The Board endorsed the Statement on Internal Control and recommended its signing off by the Leader of the Council, the Chief Executive and the Director of Resources and its presentation to the Audit Committee.

3. The Council’s Statement on Internal Control was presented to and approved by the Audit Committee on 30th June 2006.

4. Following the Corporate Management Board’s review of the Council’s Statement on Internal Control there were four areas identified for improvement:

• The Council does not have a code of Corporate Governance in line with best practice;

The draft Code of Corporate Governance has been submitted to the Audit and Corporate Governance Committee for consideration.

• There is now a need to embed risk management at Key Manager level to ensure consistency across the Council;

A staff survey has been completed and the results are being used to develop the required level of training. A revised Policy has been submitted to the Audit and Corporate Governance Committee for comments and submission to Cabinet for approval.

• ‘Staying Safe’ improvements within the Children and Young People Directorate raised as part of the Joint Area Review; and

JAR progress improvement board in place and ongoing. Additional senior resource now in place. Improvement Board overseeing the next stage of improvements, focusing on performance management and project management disciplines.

• ensuring the Council’s Performance Management Framework is robustly and consistently followed across the Council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
UPDATE ON THE COUNCIL'S STATEMENT ON INTERNAL CONTROLReport 37 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 9 attended
MW
Councillor Mike Wilsonex-officio, present
PA
Councillor Polly AndrewsMember, apologies
HB
Councillor Harry BramerMember, present
AC
Councillor ACR ChappellChairperson, present
TJ
Councillor Terry JamesMember, present
JJ
Councillor JG JarvisMember, present
BM
Cllr Bob MatthewsMember, apologies
SR
Councillor SJ RobertsonMember, present
TT
Terry Tobinex-officio, present

On this subject at Herefordshire

Search all
  1. UPDATE ON THE COUNCIL'S STATEMENT ON INTERNAL CONTROLThis decision
  2. Update on statement of accounts 2006/07 and statement on internal control 2006/07Noted
  3. Statement of internal control 2006/07Approved
  4. Progress on the council's 2006/07 statement of internal controlNoted
  5. Approval of the council's statement of internal control 2005-06Approved
  6. Statement of internal control assurance framework protocolsApproved

More from Herefordshire Audit and Corporate Governance Committee

All decisions
MeetingDecisionOutcome
28 Sep 2009 MINUTESThat the Minutes of the meeting held on the 19 June 2009 be approved as a correct record and signed by the Chairman s... Approved Open
28 Sep 2009 International financial reporting standardsThat the Committee note the report. Noted Open
28 Sep 2009 Major projects statementThat the report be noted. Noted Open
28 Sep 2009 Internal audit joint working protocolThat the report be noted. Noted Open
28 Sep 2009 Data quality updateThat (i) the progress being made on the areas of the data quality action plan where the Committee had particular conc... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies