BRADBURY LINES DEVELOPMENT UPDATE Report By: Head of Planning Services
1.0Introduction
1.1This report has been prepared in order to clarify the evolution of the housing site at Bradbury Lines and furthermore to establish clearly the current planning position and what is expected so far as the completion of the remaining phase of development is concerned.
1.2A number of Members, residents and also Lower Bullingham Parish Council have expressed some concern in respect of the apparent escalation of housing numbers and as such it seems appropriate to set this in the context of the planning history of the site as well as the changes made through the relevant policies of the emerging Herefordshire Unitary Development Plan (Revised Deposit Draft).
2.0Planning History
2.1It should be noted that this planning history relates specifically to the applications relating to the construction of dwellings. There have been a number of reserved matters submissions dealing with the details of road and drainage infrastructure. As well as the construction of roundabouts and the provision of the central play area.
CE2001/2756/O – Site for mixed use development to provide housing, open space, community and local retail uses (Phase 1). Approved 19th January, 2004.
CE2001/2757/O – Site for mixed use development to provide housing, open space, community and local retail uses (Phases 1, 2 and 3). Approved subject to Section 106 Agreement 10th February, 2005.
CE2004/0095/RM – Residential development of 2, 3, 4 and 5 bed houses, flats, bungalows (90 dwellings in total) Phase 1A. Approved 2nd June, 2004.
DCCE2006/0836/RM – Proposed erection of 70 mixed dwellings (Phase 1B). Approved 2nd June, 2004.
DCCE2005/1130/RM – Proposed residential development of 2, 3, 4 and 5 bed houses, flats and car parking (134 dwellings in total) Phase 2A. Approved 9th August, 2005.
DCCE2005/1230/RM – Construction of 129 dwellings, provision of public open space and associated works. Phase 2B. Approved 18th October, 2005.
DCCE2005/3706/RM – Proposed 2, 3 and 5 bedroom residential development for 21 dwellings. Phase 2C. Approved 8th February, 2006. CENTRAL AREA PLANNING SUB-COMMITTEE 15TH NOVEMBER, 2006
DCCE2006/1928/RM – Proposed 2, 3 and 4 bedroom residential development. Amendment to permission DCCE2005/1130/RM to enable construction of additional 14 dwellings. Approved 15th September, 2006.
3.0Policy Context
3.1The history of planning permissions is set against a changing policy context. In the early stages of the Herefordshire Unitary Development Plan (specifically the Deposit Draft stage published in September 2002), the estimated capacity of the Bradbury Lines Estate was 400 dwellings. The Revised Deposit Draft version of the Unitary Development Plan (published in May 2004) increased the estimated capacity to 500 dwellings and latterly the Inspector’s Report published in June 2006 following a Public Inquiry which closed in June 2005 it set an overall target of 600 dwellings with a proportionate increase in the associated number of affordable dwellings. This increased capacity of 600 dwellings is not being challenged by Herefordshire Council and as such it is capable of being a material consideration in the determination of any further applications relating to the remaining phase(s) of development of the site as a whole.
4.0Officers Commentary
4.1The key starting point in the planning history of this site is the outline permission (CE2001/2757/O) for the development of the whole site. This was accompanied by a Master Plan, which envisaged the delivery of around 500 dwellings, which at the time of determination was generally consistent with the estimated capacity identified in the Unitary Development Plan.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Bradbury Lines Development, Lower Bullingham: Sub-Committee UpdateReport | 24 KB | DownloadRead as text |
Follow Central Area Planning Sub-Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Dec 2009 | MinutesThat the minutes of the meeting held on 11 November be approved as a correct record and signed by the Chairman. | Approved | Open |
| 9 Dec 2009 | DCCE/092424/F - Woodcroft, Haywood, Callow, Hereford, HR2 8BX [Agenda Item 6]That officers named in the Scheme of Delegation to Officers be authorised to issue planning permission subject to the... | Decided | Open |
| 9 Dec 2009 | DCCE0009/1813/F - 10 Chilton Square, Tupsley, Hereford, Herefordshire, HR1 1PS [Agenda Item 8]RESOLVED : That (i) The Central Area Planning Sub-Committee is minded to refuse the application subject to the reason... | Refused | Open |
| 9 Dec 2009 | DMCW/092179/F - Levante, Belle Bank Avenue, Holmer, Herefordshire, HR4 9RL [Agenda Item 9]RESOLVED : That (i) The Central Area Planning Sub-Committee is minded to refuse the application subject to the reason... | Refused | Open |
| 11 Nov 2009 | MinutesThat the minutes of the meeting held on 14 October 2009 be approved as a correct record and signed by the Chairman. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.