Resolved
That the report be noted.
Environment Scrutiny Committee noted this item on Monday 12 March 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
ENVIRONMENT SCRUTINY COMMITTEE 12TH MARCH 2007
ENVIRONMENT REVENUE BUDGET MONITORING Report By: DIRECTOR OF ENVIRONMENT
Purpose 1. To advise members of the financial position for the Environment Directorate budgets for the period to 31st January 2007. The report lists the variations against budget at this stage in the year.
Financial Implications 2. It is expected that all Environment directorate budget variances will be contained within the overall 2006/07 Revenue Budget for Environment.
Considerations 3. The detailed report on Budget Monitoring is attached at Appendix 1 for Members’ consideration.
4. The total Environment Budget for 2006/07 is the amount reported to the last meeting of the Committee which was £26,714,460.
5. The summary position is set out in the table below.
2006/07 Budget Projected Variance Outturn
Service Area £000 £000 £000
Environmental Health & Trading Standards 13,361 12,786 (575)
Highways & Transportation 10,345 10,354 9
Planning 3,008 2,808 (200)
Environment Total 26,714 25,948 (766)
6. In overall terms the year end position for the Environment Budgets is a projected under spend of £766,000. This is mainly due to projected under spending on the Waste Disposal PFI and also grant income received in advance in Planning. The under spend on the Waste Disposal PFI will be transferred to reserves and an application to carry forward unspent grant income into 2007/08 will be made at the end of the financial year.
Environmental Health and Trading Standards 7. Although there are minor pressures within this service, the projected outturn reflects a net under spend of £575,000. This mainly relates to the under spend of £600,000
Further information on the subject of this report is available from Graham Dunhill on 01432 260041 ENVIRONMENT SCRUTINY COMMITTEE 12TH MARCH 2007
on the Waste Disposal PFI contract and is as a result of expected contract variations; the under spend will be transferred to reserves at year end.
8. The budget pressures on Landfill and Contaminated Land of £11,000 relates to additional costs incurred on fencing and security of the Agricote site. Increased energy costs also puts pressure of £14,000 on the Crematoria budget for the year. Underspending in other areas within Environment will mitigate these pressures.
Highways and Transportation 9. The Highways & Transportation budgets continue to be under considerable pressure and every effort will be made to contain spending within the service budget through the re-allocation of resources. Current projected outturn reflects a net over spend of £9,000 which will be used to mitigated by under spends from other areas within the Directorate.
10. Pressure will be put on the Winter Maintenance budget due to the recent adverse weather conditions. It is estimated that the outturn will be £35,000 above budget.
11. Uptake of the Concessionary Fare scheme has been strong and out-turn is currently predicted to be in the region of £1,004,000, being £172,000 over spend against budget.
12. The budget for Car Parking is also under pressure due to a small fall in income in comparison to previous years and additional rental charges in relation to 2005/06 payable within the current year. The projected net outturn is estimated to be £150,000 overspend. Income on Decriminalised Parking is also expected to fall below target by £65,000. This is due to the reduction in Wardens during the year, absent from work due to ill health.
13. Street Lighting budgets continue to be underspent due to recruitment problems and Owen Williams have now been brought in to carry out commissioning of schemes. The estimated under spend of £350,000 will be re-allocated to meet other budget pressures within the service.
14. There is additional projected under spend for the year in relation to Public Convenience costs (£25,000) and additional income received on Section 38 Agreements (£38,000). These will be use to mitigate pressures within the service.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Environment Revenue Budget MonitoringReport | 33 KB | DownloadRead as text |
PDF |
Revenue Appendis 1Report | 73 KB | Download |
Follow Environment Scrutiny Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Feb 2011 | MINUTESThat subject to including the above additional wording the minutes of the meeting held 26 November 2010 were confirme... | Decided | Open |
| 28 Feb 2011 | Road over Rail BridgesThat a) the position set out in the report be noted ; and b) in view of the public safety, site security and visual u... | Noted | Open |
| 28 Feb 2011 | Introduction to Emergency Preparedness Planning for Flooding in HerefordshireThat the Committee supported the work undertaken in the development of the Herefordshire Multi-Agency Flood Plan (MAF... | Decided | Open |
| 28 Feb 2011 | Capital Budget MonitoringThat the position set out in the Capital Budget report be noted. | Noted | Open |
| 28 Feb 2011 | Revenue Budget MonitoringThat the position set out in the Revenue Budget report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.