RESOLVED That planning permission be granted subject to the following conditions: 1 A02 (Time limit for submission of reserved matters (outline permission)) Reason: Required to be imposed by Section 92 of the Town and Country Planning Act 1990. 2 A03 (Time limit for commencement (outline permission)) Reason: Required to be imposed by Section 92 of the Town and Country Planning Act 1990. 3 A04 (Approval of reserved matters) Reason: To enable the local planning authority to exercise proper control over these aspects of the development. 4 A05 (Plans and particulars of reserved matters) Reason: Required to be imposed by Section 92 of the Town and Country Planning Act 1990. 5 F48 (Details of slab levels) Reason: In order to define the permission and ensure that the development is of a scale and height appropriate to the site. 6 G01 (Details of boundary treatments) Reason: In the interests of visual amenity and to ensure dwellings have satisfactory privacy. 7 F32 (Details of floodlighting/external lighting) Reason: To safeguard local amenities. 8 Prior to the commencement of the development an Outline Travel Plan, (which contains an overview of the transport implications of the proposed development, a commitment to promote alternative sustainable means of transport for staff and visitors and supporting strategies, with respect to the development hereby permitted), shall be submitted to and be approved in writing by the local planning authority. Reason: To satisfy the aims of PPG13 in reducing reliance on the use of private motor vehicles in order to promote sustainable transport choices to and from the site. To ensure the A449 trunk road continues to be an effective part of ... view the full minutes text for item 30.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
SOUTHERN AREA PLANNING SUB-COMMITTEE 20TH JUNE, 2007
7 DCSE2007/0181/O - ERECTION OF OFFICES (B1) 1858 SQ METRES (NET LETTABLE), 2137 SQ METRES GROSS WITH 86 CAR PARKING SPACES AT BP NORTHBOUND, ROSS SPUR, ROSS-ON-WYE, HEREFORDSHIRE, HR9 7QQ.
For: RL (UK) Ltd, per Blencowe Associates, Old Parish Barn, Sandford St. Martin, Oxfordshire, OX7 7AG.
Date Received: 22nd January, 2007 Wards: Ross-on-Wye East Grid Ref: 61062, 25736 Expiry Date: 23rd April, 2007 Old Gore Local Members: Councillors T.M.R. McLean, A.E. Gray, and P.G.H. Cutter
The Sub-Committee decided not to determine this application on 29th May, 2007 in order to visit the site. The site visit took place on 7th June, 2007.
1. Site Description and Proposal
1.1The site to which this application relates is to the east of Ross Labels car park (the former BP petrol filling station) and is bounded to the north by a tree-lined stream and to the south by the A449(T) dual carriageway. It is roughly triangular in shape, widest at the western end and tapering to the east.
1.2It is proposed to erect a 2-storey 'L' shaped office block. Details of the building are reserved for later approval but a sketch scheme shows a flat roofed building with a strong horizontal emphasis. This contrasts with the original submission which was partly 3-storied with hipped roofs. As submitted the floor plans show two rectangular buildings linked by the central core building with entrance, staircase, lifts and services. In relation to the dual carriageway, the 'L' would be upside down, presenting the narrowest elevation (about 16m wide). The office block would extend about 51m to the north, with the return elevation a total of about 31m long. The external materials are to be agreed later.
1.3In total this would provide 1858 net office space. 86 car parking spaces would be provided to the east of the office building, a reduction of 20 in response to concerns expressed from the Traffic Manager. Access (ingress) would be off the A449(T) but all vehicles leaving the site would travel via the service road to the north of Ross Labels, Netherton Road and the A40/A449 roundabout. The extreme eastern tip of the site would be extensively planted with trees, the existing trees and hedgerow along the stream would be planted more densely and new planting areas would be provided within the car parking area and the roadside planting retained.
1.4This proposed development is a revised scheme from that submitted as part of application DCSE2006/3633/F. The office block was withdrawn from that proposal however before being reported to Committee and was not therefore part of the refused scheme. An alternative proposal to the retail warehouses (a B8 storage unit DCSE2007/0534/F) is the subject of a separate report to the Committee but is not shown on the layout plan and no reference is made to a linkage between the schemes.
Further information on the subject of this report is available from [name removed] on 01432 260479 SOUTHERN AREA PLANNING SUB-COMMITTEE 20TH JUNE, 2007
2. Policies
2.1Herefordshire Unitary Development Plan 2007
Policy S1 - Sustainable Development Policy S4 - Employment Policy S6 - Transport Policy E3 - Confirmed Local Plan Employment Land Allocations Policy E8 - Development of Redundant Rural Buildings Policy LA1 - Areas of Outstanding Natural Beauty Policy LA3 - Setting of Settlements Policy DR1 - Design Policy DR3 - Movement Policy DR4 - Environment Policy T6 - Walking Policy T7 - Cycling Policy T8 - Road Hierarchy Policy T11 - Parking Provision
3. Planning History
3.1DCSE2006/2631/F Erection of office (B1), retail warehousing and - Withdrawn replacement roadside restaurant (A3/A5) 9.11.06 DCSE2006/3633/F Erection of retail warehousing and a replacement - Refused roadside restaurant (A3/A5). 24.1.07
4. Consultation Summary
Statutory Consultations
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Southern Area Planning Sub-Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.