Resolved
RESOLVED That approval be given for the purchase and installation of a temporary Bailey bridge, if this is considered the most appropriate means to carry the B4218 over the existing sub-standard bridge in Colwall.
Cabinet approved this item on Thursday 13 December 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That approval be given for the purchase and installation of a temporary Bailey bridge, if this is considered the most appropriate means to carry the B4218 over the existing sub-standard bridge in Colwall.
COLWALL RAILWAY BRIDGE PORTFOLIO RESPONSIBILITY: HIGHWAYS AND TRANSPORTATION CABINET 13 DECEMBER 2007
Wards Affected Hope End Ward.
Purpose To approve expenditure to provide a temporary bailey bridge over the sub-standard bridge in Colwall carrying the B4218 if the results of an assessment report show, on deliberation, that such a solution is the most appropriate means of opening the bridge to normal highway traffic.
Key Decision This is a Key Decision because it is likely to be significant in terms of its effect on communities living or working in Herefordshire in an area comprising one or more wards.
It was not included in the Forward Plan however inclusion in the agenda gives the required notice in accordance with Section 15 of the Local Authorities (Executive Arrangements) (Access to Information) Regulations 2000.
Recommendation THAT approval be given for the purchase and installation of a temporary bailey bridge, if this is considered the most appropriate means to carry the B4218 over the existing sub-standard bridge in Colwall.
Reasons To allow access into the village for all normal highway vehicles including those serving businesses.
Considerations 1. Herefordshire Council closed the bridge to traffic following an inspection by Owen Williams, the council’s engineering consultants, undertaken on Saturday / Sunday 11/12 August. The decision was made on the grounds of public safety.
2. At the inspection the bridge was observed to have deteriorated significantly since the previous inspection in 2004 and significantly greater than expected. Because of this the inspector had serious concerns as to the capacity of the bridge.
3. The bridge was closed to traffic on Wednesday 15 August based on recommendation of the inspection.
Further information on the subject of this report is available from Andrew Culley, Programme & Contracts Manager on (01432) 261955 4. Owen Williams was asked to consider their recommendation again, in effect to check again that they had made the correct decision, on the safety of the bridge, based on the evidence available. They confirmed their recommendation to close the bridge.
5. The bridge was inspected again over the nights of 14/15, 15/16, and 16/17 October for the purpose of gaining more data to assess, with increased certainty and detail, the capacity of the bridge.
6. The results of the assessment using the later inspection data will be complete before Christmas. It will accurately assess all aspects of the bridge’s strength taking into account the different elements and varying degrees of deterioration.
7. The work towards a resolution of to the bridge is based on a planned collection and assessment of complete and reliable data related to a number of possible scenarios for the bridge re-opening. This ensures that all possibilities are thoroughly reviewed and challenged and that the best outcome for all is achieved.
8. This assessment is crucial to successfully identifying the best solution to the bridge closure.
9. It is not appropriate to commit to any solution before the full evaluation, approval and challenge to the range of options available is completed. The range of alternatives is expected towards the end of the year.
10. One alternative that has been considered, with a design prepared, is the provision of a temporary “Bailey Bridge”.
11. The proposed temporary bridge will be capable of carrying 40 tonne vehicles, though it will be under traffic signal control (as was the case before the closure in August). The bridge is termed “temporary” as it is currently envisaged that a full replacement of the existing structure will be required in the longer term.
12. If ordered the expected delivery period from the fabricator of a temporary bridge is 12 weeks.
13. This assessment is crucial to successfully identifying the best solution to the bridge closure.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
COLWALL RAILWAY BRIDGEReport | 74 KB | DownloadRead as text |
PDF |
CapProgNov07 v2Report | 128 KB | Download |
Follow Cabinet at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | MINUTESThat the minutes of the meeting held on 24 September 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 24 Sep 2026 | MINUTESThat the minutes of the meeting held on 30 July 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 30 Jul 2026 | MINUTESThat the minutes of the meeting held on 25 June 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 25 Jun 2026 | MINUTESThat the minutes of the meeting held on 21 May 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 21 May 2026 | MINUTESThat the minutes of the meeting held on 30 April 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.