CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Herefordshire Council
Audit and Corporate Governance Committee, Friday 21 December 2007 at 10.00am

PROGRESS REPORT NO.3 - DIRECTOR OF RESOURCES SPECIAL REPORT

Noted Finance 3 papers

Audit and Corporate Governance Committee noted this item on Friday 21 December 2007. Below is the council's own wording, with the papers it was decided on.

Item57

Resolved

That the progress made to date and the proposed way forward in respect of the action plan, more particularly referred to in the report, be noted.
Word for word from the decision Herefordshire published for this meeting. Source: councillors.herefordshire.gov.uk

Follow this further

Built from Herefordshire's papers

What the report saysPro

Report to Audit and Corporate Governance Committee

ACTION PLAN FOR TRAVEL & SUBSISTENCE ARRANGEMENTS APPENDIX 1 Agreed action Responsible Agreed Progress Revised officer(s) target target date date th 1 Review the Code of Conduct Head of HR Sept 2007 Work in progress reported to Corporate Management Board on 20 March for Employees to ensure the November in line with previous update on progress with this action 2008. th Council’s expectations on the plan to the Audit & Corporate Governance Committee on 16 required standard of conduct on November 2007. This work shall be integrated with the work needed giving hospitality are clear. in relation to the Crookall recommendations as outlined in the body of the report. th 2 Review the Code of Conduct Head of HR Sept 2007 Work in progress reported to Corporate Management Board on 20 March for Employees to ensure the November in line with previous update on progress with this action 2008. th Council’s expectations on the plan to the Audit & Corporate Governance Committee on 16 required standard of behaviour November 2007. This work shall be integrated with the work needed in relation to consumption of in relation to the Crookall recommendations as outlined in the body of alcohol during office hours and the report. whilst representing the Council after office hours is clear. th 3 Review the Code of Conduct Head of HR Sept 2007 Work in progress reported to Corporate Management Board on 20 March for Employees to ensure the November in line with previous update on progress with this action 2008. th Council’s expectations on the plan to the Audit & Corporate Governance Committee on 16 standard of behaviour November 2007. This work shall be integrated with the work needed regarding working under the in relation to the Crookall recommendations as outlined in the body of influence of alcohol is clear. the report. th 4 Revise guidance on travelling Head of HR Sept 2007 Work in progress reported to Corporate Management Board on 20 March claims to require separate November in line with previous update on progress with this action 2008. th confirmation by attaching a plan to the Audit & Corporate Governance Committee on 16 signed memorandum that the November 2007. This work shall be integrated with the work needed line manager certifies overnight in relation to the Crookall recommendations as outlined in the body of stays within the Council’s area. the report.

Payroll to reject all claims for overnight stays in the Council’s areas that are not accompanied by separate written authorisation by Head of Service and Director. 5 Payroll to reject all claims that Payroll Immediate The Payroll Manager issued an e-mail to all staff as a reminder on the Complete. do not have the correct Manager need to ensure all travel and subsistence claims are supported by supporting documentation. VAT receipts, that they need to be submitted in a timely fashion and that exceptional items need to be approved by the Head of Service and the Director. th 6 Revise guidance on travelling Head of HR Sept 2007 Work in progress reported to Corporate Management Board on 20 March claims to require monthly November in line with previous update on progress with this action 2008. th submission of travel and plan to the Audit & Corporate Governance Committee on 16 expenses claims within a November 2007. This work shall be integrated with the work needed month of the period they relate in relation to the Crookall recommendations as outlined in the body of to. the report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
A&CG Progress Special Report 3 Apps 211207Report 51 KB DownloadRead as text
PDF
CG_Burton Hotel, Kington_1.1500_D_PReport 598 KB Download
PDF
PROGRESS REPORT NO.3: DIRECTOR OF RESOURCES SPECIAL REPORTReport 27 KB Download

At this meeting

Whole meeting

Who was there

7 of 11 attended
AC
Councillor ACR ChappellChairperson, present
PC
Councillor PGH CutterMember, present
GD
Councillor GFM DaweIn Attendance, in attendance
PE
Councillor PJ EdwardsIn Attendance, in attendance
MF
Councillor MJ FishleyMember, present
JG
Councillor JHR GoodwinMember, present
RM
Councillor R MillsMember, present
AO
Councillor Aubrey OliverIn Attendance, in attendance
PR
Paul RogersSecretary, present
RS
Councillor RH SmithMember, apologies
AT
Councillor AM ToonMember, present

On this subject at Herefordshire

Search all
  1. PROGRESS REPORT NO.3 - DIRECTOR OF RESOURCES SPECIAL REPORTThis decision
  2. Progress report no.2 - director of resources' special reportNoted
  3. Progress report on the joint review action plan - july 2003 and the directorate service plan 2003-04Noted

More from Herefordshire Audit and Corporate Governance Committee

All decisions
MeetingDecisionOutcome
28 Sep 2009 MINUTESThat the Minutes of the meeting held on the 19 June 2009 be approved as a correct record and signed by the Chairman s... Approved Open
28 Sep 2009 International financial reporting standardsThat the Committee note the report. Noted Open
28 Sep 2009 Major projects statementThat the report be noted. Noted Open
28 Sep 2009 Internal audit joint working protocolThat the report be noted. Noted Open
28 Sep 2009 Data quality updateThat (i) the progress being made on the areas of the data quality action plan where the Committee had particular conc... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies