Planning and Regulatory Committee approved this item on Friday 29 February 2008. Below is the council's own wording, with the papers it was decided on.
RESOLVED THAT: the Planning Application Requirements (Local) document be adopted for use subject to any minor drafting chances to be agreed with the Chairman, and be brought into operation on a date also to be agreed with the Chairman but in any event, no later than the implementation date for the standard planning application form 1-APP and the final adoption of the Supplementary Planning Document on Planning Obligations.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
CONSULTATION ON PLANNING APPLICATION REQUIREMENTS Report By: Head of Planning Services
Wards Affected County-wide
Purpose 1. To inform members about new planning application procedures, to confirm the outcome of consultation on the document “Planning Application Requirements (Local) and to approve it for use on a date to be determined by the meeting.
Financial Implications 2. None.
Background 2.1 At the meeting in September 2007 this Committee received a report on the new planning application procedures and agreed to a programme of consultation. The key elements of that report were as follows.
2.2The Government has decided to introduce a National Standard Planning Application form which will be mandatory from April 2008. It is known by the project title “1-APP”. In association with 1-APP the Government has set out minimum standards for planning application submissions which must be met by applicants to form a valid planning application. There will be national minimum standards, to be known as Planning Application Requirements (National). The government has also provided for local planning authorities to set their own local requirements, known as Planning Application Requirements (Local). In order for these local requirements to be enforceable they must be publicised and consulted on before being brought into use. The programme for consultation was agreed by Planning Committee at its meeting on 28th September 2007.
2.3There will be benefits in having a suitably prepared set of Planning Application Requirements (Local). At present, legally, applicants only have to submit fairly basic details with a planning application in order to make it valid. Additional items such wildlife surveys, tree surveys and a wide range of other essential information can be requested before a decision is made – but can not always be demanded at the start of the process. This frequently leads to delays. The basic concept is to raise the standard of planning application submissions at first submission.
2.4In theory, at least, this will benefit the local planning authority because the “rules” for what constitutes a valid application will be made more clear and it gives local planning authorities the ability to demand high standards of planning application submissions.
Further information about this report is available from Peter Yates, Development Control Manager on 1782 PLANNING COMMITTEE 29 FEBRUARY 2008
2.5It is, however, important to stress that the creation of a set of Planning Application Requirements (Local) will not prejudice the decision of the local planning authority on a planning application once submitted.
3 The Consultation Process
3.1The consultation process was delayed because the government failed to publish the anticipated guidance until December 2007. Since then the Consultation Draft has been prepared and a copy has been copied to all Members of this Committee prior to this meeting.
3.2The consultation process included: • Presentation of the draft PAR(L) to an Agents’ Forum in January 2008 • Written consultation with City, Town and Parish Councils in January and February 2008 • Written consultation with normal statutory consultees on planning applications at the same time • Written consultation with a selection of non-statutory consultees taken from the list in the Council’s Statement of Community Involvement, i.e. including those with County-wide interests and who comment most frequently on planning applications – also in January and February 2008
3.3The six week consultation period specified by the government advice has now expired.
3.4At the time of drafting this report seven responses had been received, with one in support and the others suggesting minor drafting changes. None of the responses conflict with the basic principles of the document and the points raised can be incorporated into the document with minor drafting changes where appropriate.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.