PLANNING PERFORMANCE AGREEMENTS Report By: HEAD OF PLANNING SERVICES
1. Wards Affected County-wide
2. Purpose 2.1 To update Committee on this important national initiative and to agree a local protocol.
3. Financial Implications 3.1 Likely to be cost neutral at this stage. Future reports will address the issue of charging for pre-application advice.
4. Background 4.1 Planning Performance Agreements are a key element of the Planning Reform agenda. Planning Performance Agreements are essentially a collaborative project management process primarily aimed at complex development proposals. Although PPAs can be used for all development projects that fit the Communities and Local Government definition of a major application, it is recommended that they are most appropriate for unique, complex schemes as PPAs require considerable effort. The aim is to move away from development control to a system of development management which takes account the broader concept of spatial planning. PPAs are about improving the quality of the decision making process, not the speed or decision making, and they may not be appropriate for all types of development proposal. Collaboration is key to the process and one party cannot insist on the use of a PPA if there is no collective agreement.
4.2A PPA can be used for all major applications. Local authorities are required to notify Communities and Local Government about their use of a PPA via the amended general Development Control Return Forms PS1/2. The local planning authority (LPA) and applicant are free to agree on the necessary componements of a PPA which will depend upon the individual project. However, LPAs will be monitored against that agreed PPA timescale (PPA programme).
4.3There are a number of core componements recommended as a minimum by Communities and Local Government for following the PPA process and producing a PPA. In developing the individual agreement parties must acknowledge the key written content of the PPA, which should include:
- project vision and development objectives and the planning proposal; - project issues and tasks plan; - project team and decision making framework; and - project programme.
Further information on the subject of this report is available from Andrew Ashcroft, Head of Planning Services, on (01432) 383098
PLANNINGPERFORMANCEAGREEMENTSreport0.doc PLANNING COMMITTEE 23 MAY 2008
4.4A PPA can only be considered via agreement between the local authority and the applicant.
Potential criteria for assessing the complexity of a scheme can include:
- proposals that meet a local authority’s identified strategic objectives as set out in the Local Development Framework (LDF); - proposals requiring an Environmental Impact Assessment; - larger sites that include a variety of land uses; - proposals that have an impact on strategic areas of environmental sensitivity, i.e. a Special Protection Area or sites where there are many constraints to be resolved before the development can be delivered; - proposals involving significant non-standard planning obligations; - proposals which require referral to a central or regional government body; - proposals which would have significant impact on existing communities and therefore require consultations or involvement from many different stakeholders, interest groups, statutory agents, etc; and/or - proposals that are unique to a local authority’s experience.
4.5Experience from the pilot exercise identified a wide variety of factors that can impact on any particular development proposal and that establishing a single model agreement was neither realistic nor helpful. It also identified that the actual process of establishing an agreement is significantly beneficial in developing a common understanding of project issues and objectives and building positive relationships.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.