RESOLVED that Cabinet approve: (a) the final outturn for 2007/08 ; (b) t he Joint Management Team’s recommendations for carry forward of unspent budget into 2008/09 (page 165, paras 55 and 56); and the movement to new reserves as outlined in the report (page 166, para 59) ; and (c) the movements to new reserves outlined in the report.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
FINAL REVENUE AND CAPITAL OUTTURN 2007/08 PORTFOLIO RESPONSIBILITY: RESOURCES CABINET 29 MAY 2008
Wards Affected Countywide.
Purpose The purpose of this report is for Cabinet to consider and approve:
a. The final outturn position for 2007/08.
b. Joint Management Team’s proposals for carry forward of unspent budget into 2007/08.
c. The creation of new reserves and provisions in the 2007/08 accounts.
Key Decision This is not a Key decision.
Recommendations That Cabinet approve:
(a) the final outturn for 2007/08;
(b) the Joint Management Team’s recommendations for carry forward of unspent budget into 2008/09; and
(c) the movements to new reserves outlined in the report.
Reasons 1 Whilst work continues on the range of tasks necessary to prepare the Council’s statutory Statement of Accounts for 2007/08, it is sufficiently advanced for Cabinet to consider the final outturn for the revenue account.
2 On 20 June 2008 the full Statement of Accounts for 2007/08 will be presented to the Audit and Corporate Governance Committee for formal approval. This will ensure the Council meets the statutory deadline for the approval of the accounts.
Further information on the subject of this report is available from David Powell, Head of Financial Services on (01432) 383173 Considerations DIRECTORATE BUDGET OUTTURNS FOR 2007/08
3 An overall summary of the outturn position for directorate budgets is as follows:
£000 Directorate outturns 2007/08 Adult & Community Services – an over spend 22 Children & Young People’s Services 0 Corporate & Customer Services – an over spend 1,176 Environment – an over spend 60 Human Resources – an under spend -15 Resources – an under spend -585 Corporate budgets – an under spend -118 Bellwin threshold related to Environment – an over spend 360 Net directorate over spend 900
4 The above table shows that the final outturn position for 2007/08 was an over spend of £900k on directorate budgets after adjustments for use of revenue contingencies. The explanation of significant variances is included in the summary covering each directorate.
5 It is important to distinguish between the financial performance of directorates and the final overall revenue outturn of the Council. The following table gives the overall position after allowing for transactions not under the control of directorates:
£000 Net directorate outturn 2007/08 – an over spend 900 Additional income from Financing Transactions -804 Additional dividend income from West Mercia Supplies -44 Unbudgeted income from the Local Authority Business Growth Incentive -581 scheme Former local authority debt -31 Unused Invest to Save allocation -31 Net revenue under spend -591
6 The overall position is an under spend of £591k on the Council’s 2007/08 revenue account. This compares to a forecast outturn for the year in the final Integrated Performance Report (IPR) of an over spend of £578k.
7 The Council has now established a consistent approach to managing budgets where cash is treated as a corporate resource by all levels of the Council. Service managers have been encouraged and supported by staff in the Resources
Page 2 of 17 Directorate to concentrate their energies on delivering improved services at or below the available budget in line with corporate priorities rather than on protecting resources for their own particular service area.
8 The outturn position provides some additional flexibility for matching cash resources to corporate priorities into the future. The above tables demonstrate that the under spend is overwhelmingly accounted for by corporate activity. This overall directorate over spend is largely accounted for by the cost of the Community Network upgrade. If this is set to one side it is clear the overall position is a balanced budget for directorates. This has been significantly assisted by the allocation of £3.5m to help service improvement in 2007/08 and the £1.3m central contingency for social care.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.