Herefordshire Council
Cabinet, Thursday 11 September 2008 at 2.00pm

Minster College Building Schools for the Future One School Pathfinder – Award of Contract

Decided Executive 4 papers

Cabinet decided this item on Thursday 11 September 2008. Below is the council's own wording, with the papers it was decided on.

Item43

Resolved

RESOLVED that: Cabinet endorse the recommendation of the report that the Building Schools for the Future (BSF) Project Board award the design and build contract, for the Minster College Building Schools for the Future One School Pathfinder scheme, to Stepnell Limited.
Word for word from the decision Herefordshire published for this meeting. Source: councillors.herefordshire.gov.uk

Follow this further

Built from Herefordshire's papers

What the report saysPro

Report to Cabinet

MINSTER COLLEGE BUILDING SCHOOLS FOR THE FUTURE ONE SCHOOL PATHFINDER – AWARD OF CONTRACT PORTFOLIO RESPONSIBILITY: CHILDREN’S SERVICES

CABINET 11 SEPTEMBER 2008

Wards Affected Leominster South Leominster North Golden Cross with Weobley Hampton Court Upton

Purpose To receive and approve the recommendation of the Building Schools for the Future Project Board to award the design and build contract for the above scheme to Stepnell Limited.

Key Decision This is a Key Decision because it is likely to be significant in terms of its effect on communities living or working in Herefordshire in an area comprising of one or more wards.

It was included in the Forward Plan

Recommendation THAT the recommendation of the Building Schools for the Future (BSF) Project Board, to award the design and build contract, for the Minster College Building Schools for the Future One School Pathfinder scheme, to Stepnell Limited, is approved.

Reasons The award of the contract will allow the authority to deliver The Minster BSF One School Pathfinder design and build project.

Considerations Tender Evaluation:

1. To deliver this Building Schools for the Future, One School Pathfinder project, the local authority opted to procure the new building through a two stage selective tendering process. The authority adopted the National Joint Consultative Committee for Building (NJCC) Code of Procedure for Design and Build Contracts and the NJCC code of Procedure for Two Stage Selective Tendering.

2. Tenders were submitted by three contractors on 18th April 2008. They were Stepnell Ltd., Morgan Ashurst plc and Mansell Construction Services Ltd. Morgan Ashurst plc

Further information on the subject of this report is available from Rob Reid, Schools Planning & Access Manager on Tel: (01432) 260920

MinsterCollege0.doc returned a compliant and a non-compliant bid.

3. All of the Bids were disseminated to stakeholders for comment, evaluation and information including the Project Board, the Evaluation Team, the Project Team, Minster College students and staff. Membership of these groups is listed at the end of this paper.

4. A Presentation Day was held on the 6th May 2008 to give all three contractors an opportunity to present their submissions to the School Governors and the Local Authority. All three contractors took advantage to this opportunity.

5. On 8th May 2008 the Evaluation Team met to discuss and evaluate the submissions and to agree on the recommendation for the Preferred Bidder for the Minster College BSF OSP. The evaluation criteria are shown at Appendix 1. The evaluation reports are shown at Appendix 2.

6. Using notes and comments received from a wide range of sources, particularly those who had attended the Presentation Day, the Evaluation Team were aware that no one Submission contained the definitive solution to the required new school.

7. Through the Two Stage Design and Build process the second stage design period was used to correct and perfect the most advantageous submission to provide the right development for the Minster College.

8. Of the three bids, the Morgan Ashurst bids, both compliant and non-compliant were rejected, firstly because of cost and secondly due to insufficient educational design in terms of room associations, circulation suitability and lack of suitable landscape proposals.

9. Of the other two bids, Stepnell was within budget, but scored lower on their educational suitability whilst Mansell’s bid was over budget but scored higher on their educational suitability.

10. The Evaluation Team put forward a proposal to the Project Board that Stepnell Limited be appointed as the preferred contractor. This was because the Stepnell bid had outscored Mansell on the Evaluation Matrix and because the second design stage offered the opportunity to improve the design of the Stepnell submission.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 45 KB Download
PDF
Appendix 2Appendix 2 45 KB Download
PDF
Appendix 3Appendix 3 85 KB Download
PDF
Minster College Building Schools for the Future One School Pathfinder: Award of ContractReport 69 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 23 attended
RP
Councillor Roger PhillipsChairperson, present
LB
Councillor LO BarnettMember, present
AB
Councillor AJM BlackshawMember, present
HB
Councillor Harry BramerMember, present
JF
Councillor JP FrenchMember, present
JH
Councillor JA Hyde sadly passed away on Monday 11 February 2019.Member, present
JJ
Councillor JG JarvisMember, present
PP
Councillor Philip PriceMember, present
DW
Councillor DB WilcoxMember, present
SC
Sian ClarkSecretary, present
SC
Sally ColeSecretary, present
AM
Alan McLaughlinOfficer, present

All 23 on the meeting page

On this subject at Herefordshire

Search all
  1. Minster College Building Schools for the Future One School Pathfinder – Award of ContractThis decision
  2. Dcnc2008/1934/cd - proposed redevelopment of the minster college. minster college, south street, leominster, herefordshire, hr6 8jjApproved

More from Herefordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 MINUTESThat the minutes of the meeting held on 24 September 2026 be approved as a correct record and signed by the Chairperson. Approved Open
24 Sep 2026 MINUTESThat the minutes of the meeting held on 30 July 2026 be approved as a correct record and signed by the Chairperson. Approved Open
30 Jul 2026 MINUTESThat the minutes of the meeting held on 25 June 2026 be approved as a correct record and signed by the Chairperson. Approved Open
25 Jun 2026 MINUTESThat the minutes of the meeting held on 21 May 2026 be approved as a correct record and signed by the Chairperson. Approved Open
21 May 2026 MINUTESThat the minutes of the meeting held on 30 April 2026 be approved as a correct record and signed by the Chairperson. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies