Resolved
That the Schools Forum notes the work that has been carried out and the proposed timeline, with involvement from the head teacher touchstone group and that the SLA charging proposals be submitted to the Forum in September 2009.
Herefordshire Schools Forum decided this item on Monday 15 December 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Schools Forum notes the work that has been carried out and the proposed timeline, with involvement from the head teacher touchstone group and that the SLA charging proposals be submitted to the Forum in September 2009.
SERVICE LEVEL AGREEMENTS REPORT BY HEAD OF PLANNING, PERFORMANCE AND DEVELOPMENT
SCHOOLS FORUM 12 DECEMBER 2008
Schools Affected All schools
Purpose 1. To set out the next steps in establishing revised service level agreements, including financial considerations and to provide feedback from the working group set up to inform Schools Forum.
Financial Implications 2. Approximately £2m is allocated in the Schools Budget for Service Level Agreement (SLA) spend with additional spend on ICT SLAs. The method of calculation has been in existence since 2000. Schools and the Local Authority are interested in achieving highly effective and valued services. This is within the overall context of fewer pupils and therefore less money available over the coming years.
Report 3. Following Schools Forum of 13 October 2008 a group of head teachers (the head teacher touchstone group) and officers met to consider a range of draft SLAs, as well as the template used to generate the SLAs, the overview sheet and the pro- forma that will enable schools to set out which services they are wanting to choose. The group also considered the overall processes to renew our use of SLAs and the associated financial implications.
4. The group felt that more work was required to achieve a consistent standard across the current service areas and that this would then enable schools to assess key questions around value for money. This should therefore be the focus of activity over the next month.
5. Finances are critical to some SLAs and the group discussed a range of issues including the fact that the existing charging arrangements are dependent upon a formula developed at least six years ago. The group discussed the use of some services as an insurance scheme and how this might affect the charging for services. The relationship between Council funding and school budgets funding, and the lack of clarity in the overall charging policy as a result was also considered in broad terms. The group recognised that a lot of work had to be carried out so that an actual choice and charging process could be put in place. The aim is for this to be operational for the financial year 2010/11. The existing financial arrangements would continue therefore for 2009/10, with a 2.1% increase in line with the Minimum Funding Guarantee.
Further information on the subject of this report is available from Chris Baird, Head of Planning, Performance & Development on 01432 260264
E:\MODERNGOV\data\published\Intranet\C00000444\M00002790\AI00015520\ServiceLevelAgreements0.doc 6. The following timescales are therefore proposed to establish SLAs not only for 2009/10 but also for 2010/11. The Head of Improvement and Inclusion is keen for some aspects of school improvement and learning support services to be delivered through a SLA approach. However this needs to be developed in line with the locality arrangements that the Children and Young People’s Directorate are aiming to put in place over the coming year.
Proposed Timeline for Development of SLAs
Services finalise their SLAs to a consistent standard 12 December 2008
Share with Head teacher working group By 19 December 2008
Meeting of Head teacher working group to cross check By 21 January 2008 consistency and clarity
SLA pack out to schools By 31 January 2009
Schools return SLA pro-forma to Council By 28 February 2009
SLA officer working group meet to address charging Feb to May 2009
Head teacher working group meet to address charging
Charging proposals to schools forum September 2009
Improvement and Inclusion officers work on developing Feb to Aug 2009 SLAs for aspects of School Improvement and Learning Support, to be in place for 2010/11
Revised SLA pack to schools By 1 November 2009
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
SERVICE LEVEL AGREEMENTSReport | 73 KB | DownloadRead as text |
Follow Herefordshire Schools Forum at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Oct 2026 | Election of Chairpersonthat Paul Jennings be elected Chairperson of the Forum for the ensuing year. | Decided | Open |
| 23 Oct 2026 | Election of Vice-Chairpersonthat Richard Foster be elected vice-chairperson of the Forum for the ensuing year. | Decided | Open |
| 23 Oct 2026 | Schools National Funding Formula 2027/28 UpdateResolved that the draft 2027/28 budget to be prepared in line with the approach taken in 2026/27. | Decided | Open |
| 23 Oct 2026 | Request to the Secretary of State to Disapply the School Finance RegulationsResolved that the forum approve the disapplication request in respect of Eastnor Primary School. | Approved | Open |
| 23 Oct 2026 | De-Delegations and Education Management Function Proposal 2027/28Resolved that the De-Delegated Services as listed in the report be used to form the draft 2027/28 budget. (Voting on ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.