Resolved
RESOLVED THAT: (a) the revised joint Risk Management and Assurance Policy be approved; and (b) the joint Risk Management Assurance Guidance be approved.
Cabinet approved this item on Thursday 26 November 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT: (a) the revised joint Risk Management and Assurance Policy be approved; and (b) the joint Risk Management Assurance Guidance be approved.
MEETING: CABINET
DATE: 26 NOVEMBER 2009
TITLE OF REPORT: RISK MANAGEMENT AND ASSURANCE
PORTFOLIO AREA: CORPORATE AND CUSTOMER SERVICES AND HUMAN RESOURCES CLASSIFICATION: Open Wards Affected County-wide
Purpose To approve the revised joint Risk Management and Assurance Policy and Guidance documents.
Key Decision This is not a Key Decision.
Recommendation(s) THAT:
(a) the revised joint Risk Management and Assurance Policy be approved;
(b) the joint Risk Management Assurance Guidance be approved;
Key Points Summary • If strategic priorities are to be met and if positive assurances are to be given in response to external drivers then a robust risk management process must be embedded within the authority.
Alternative Options 1 There are no Alternative Options.
Reasons for Recommendations 2 As stated within the current Risk Management Policy a review of the risk management documents should be undertaken at regular intervals to ensure that they are still fit for purpose.
Further information on the subject of this report is available from Andrew Rewell Corporate Risk Manager on (01432) 260295 3 The new Comprehensive Area Assessment (CAA) process calls for a more robust management of risk across the organisation. Within the Use of Resources assessment one of the three themes, ‘Governing the Business’ highlights the need to have clear and robust processes in place for managing risks, particularly those relating to partnerships and fraud and corruption.
Introduction and Background 4 Since February 2007 the Council and NHS Herefordshire have had an integrated risk management team. A shared Risk Management Strategy, Policy and Toolkit, were approved by Cabinet in May 2008.
5 In April 2009 a review of the existing tool kit was undertaken with a view to developing a single risk assessment process for both risk management and health and safety across the partnership. An internal audit of risk management practices within the Council was also w undertaken in 2009. The key recommendations highlighted the need to refocus on the responsibilities for risk management, risk management training, use of the corporate risk management process and to further align business plans with the risk management policy.
6 The introduction of the revised quarterly performance reporting process has provided an opportunity to review the Council’s corporate risks. This has resulted in a more focused look at risks that could have a strategic impact on the achievement of corporate objectives as identified within the corporate plan. The revised documents will enable us to develop this process further.
Key Considerations 7 The need for a clear policy and procedure in order to embed the management of risk is essential if corporate priorities are to be met, and to provide positive assurance that risks are being identified and managed.
8 The main changes to the policy reflect the need to develop a positive culture in which the management of risk is seen as a day to day activity and not considered as a separate and bureaucratic task.
9 The revised policy promotes the positive aspects of managing risk so as to add value: achieving the balance between under-managing risks i.e. unaware and therefore no control, (which could damage performance and use limited resources unnecessarily), and over management i.e. an obsessive level of involvement in the fine details, which could become overwhelming and stifle innovation and creativity.
10 The revised guidance document is intended to be used at all levels of the organisation and guides the user through the 5 steps of managing risks:
1) Identify Hazards and Threat events
2) Evaluate the level of risk based on adequacy of existing controls
3) Determine additional controls required – this emphasises the need for a risk owner and describes in more detail than previously the 4 T’s of risk control – Terminate, Tolerate, Transfer, Treat. 4) Implement control measures and an action plan.
5) Monitor controls, record and review.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
RISK MANAGEMENT AND ASSURANCEReport | 86 KB | DownloadRead as text |
PDF |
Risk Management and Assurance Guidance August 2009Report | 395 KB | Download |
PDF |
Risk Management and Assurance Policy October 2009Report | 293 KB | Download |
Follow Cabinet at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | MINUTESThat the minutes of the meeting held on 24 September 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 24 Sep 2026 | MINUTESThat the minutes of the meeting held on 30 July 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 30 Jul 2026 | MINUTESThat the minutes of the meeting held on 25 June 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 25 Jun 2026 | MINUTESThat the minutes of the meeting held on 21 May 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 21 May 2026 | MINUTESThat the minutes of the meeting held on 30 April 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.