That (a) the final DSG settlement and the increase of 3.5% in the Individual Schools Budget be noted; (b) the schools Forum retains the 2009/10 DSG underspend of £128k to help meet the forecast overspends in out county placements and school business rates. (c) a report detailing Early Years expenditure be presented for discussion to the Budget Working Group with a report from the Group to the October Schools Forum meeting; (d) schools be requested to put forward suggestions to Schools Forum on how to achieve 0.9 per cent budget efficiency savings and 10 per cent procurement savings; and (e) Property Services and other appropriate officers be asked for their suggestions in relation to (d) above.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
Purpose To inform Schools Forum of the final Dedicated Schools Grant (DSG) for 2010/11 and the Outturn for 2009/10 .
Key Decision This is not a Key Decision.
Recommendation(s) THAT Schools Forum:
(a) to note the final DSG settlement and the increase of 3.5% in the Individual Schools Budget;
(b) to comment on the Section 251 Budget Statement as appropriate.
(c) to retain the 2009/10 DSG underspend of £128k to help meet the forecast overspends in out county placements and school business rates.
Key Points Summary • The Individual Schools Budget (ISB) is the amount distributed direct to schools and has increased overall by 3.5%. Primary budgets have increased by 3.2%, high school budgets by 3.6% and special school budgets by 5.8%.
• The total 2009/10 DSG underspend is : £727k comprising of
o Prior commitments of
§ £186k for rates rebates which Forum has already agreed to distribute to schools over the three years from April 2010
Further information on the subject of this report is available from Malcolm Green, Schools Finance Manager (01432) 260818
$voanv10l.doc 26Nov08 § £413k which is the balance of the 2008/09 underspend allocated to schools over three years and yet to be drawn down.
o An underspend of £128k in 2009/10 on central expenditure
Alternative Options 1 No alternative options or projects have been identified at this stage. Schools Forum can propose initiatives to be developed and considered alongside those identified in this report.
Reasons for Recommendations 2 The recommendations seek to ensure considered decisions for the use of the Dedicated Schools Grant underspend from 2009/2010.
Introduction and Background 3 The report provides a full breakdown of the DSG carry-forward balances from 2009/10. It also updates Schools Forum on the final amount of DSG for 2010/11 and provides some background information on the school budgets for 2011/12 and 2012/13.
4 The report is in two parts as follows;
A The Budget 2010/11
B The DSG Outturn for 2009/10
Key Considerations A. The Budget 2010/11
5 Three year budgets (final for 2010/11 and draft for 2011/12 and 2012/13) have been completed and issued to schools. The Section 251 Education Budget Statement has been completed for financial year 2010/2011 and submitted to the Department for Children, Schools and Families (DCSF) prior to the deadline of 30th April 2010. Full details of all the Section 251(previously section 52) tables will be published on the Council’s website. Table 1 setting out an overview of school and central expenditure is attached as Appendix 1. Of particular note is the deprivation annex which indicates an 82% achievement against the 100% target for passing deprivation funding through to schools. This is a significant increase on the 49% in 2007/08 and meets the Department for Education (DfE) target of 80% by 2010/11. Further work is in hand through the Budget Working Group to meet the requirement for 100% of deprivation funding to be passed through to schools by 2014/15.
6 The Schools Budget is based on pupil numbers of 22,561.6 and a Dedicated Schools Grant of £90.294m. Recoupment for the Hereford Academy is expected to be £2.987m including a deduction of £136k for LA services (but excluding bands 3 & 4 which are paid to the Academy by the Council from DSG). SEN banded funding costs for the Steiner Academy are expected to be £28k compared to a budget allocation of £32k within DSG.
7 School budgets have been calculated on the following pupil numbers (excluding nurseries and sixth forms but including Hereford Academy). Pupil 2010/11 2009/10 Difference % Numbers
Primary 12,001 12,119 -118 -1.0%
High 9,209 9,266 -57 -0.6%
Special 231 219 +12 +5.5%
Total 21,441 21,604 -163 -0.75%
8. Confirmation of the final grant allocation for DSG and final pupil numbers are still awaited from the DfE and is expected prior to the 9th July.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.