RESOLVED that Cabinet: (a) note progress made on the Shared Service Project since March 2010, and; (b) Note the current challenges and risks, principally: i. Review of the Business Case; ii. Partnership agreement for establishing the JVCo ; iii. Fundamental requirement for cultural and process change across the whole of HPS to deliver savings; iv. Implementation of the Agresso system in April 2011; (c) Note the key role of all stakeholders in leading the organisational and cultural changes required to deliver transformed support services and savings; (d) Note that a further report seeking formal decision to agree terms of the partners’ participation in the JVCo will be presented to the Board and Cabinet in September 2010.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
PORTFOLIO AREA: CORPORATE & CUSTOMER SERVICES AND HUMAN RESOURCES CLASSIFICATION: Open
Wards Affected County-wide
Purpose On 18 March 2010 the Cabinet agreed that the Council’s preferred option for the delivery and commissioning of shared services would be a Joint Venture Company (representing a public public partnership) involving Herefordshire Council (HC), NHS Herefordshire (NHSH) and Hereford Hospitals NHS Trust (HHT). The Cabinet authorised the Deputy Chief Executive (DCE) to progress and take all necessary steps to establish a JVCo in consultation with the Leader and Deputy Leader of the Council and Trust Boards.
A further report seeking a formal decision to agree terms of the Council’s participation in the JVCo is to be presented in September 2010. The purpose of this report is to update the Cabinet on the progress to date and next steps on the Shared Services Programme.
A similar update report is scheduled for the NHSH Board on 21 July 2010.
Key Decision This is not a key decision.
Recommendation THAT Cabinet
(a) Note progress made on the Shared Services Project since March 2010 and (b) Note the current challenges and risks, principally: i. Review of the Business Case; ii. Partnership agreement for establishing the JVCo;
Further information on the subject of this report is available from Dean Taylor, Deputy Chief Executive on Tel: (01432) 260037
$aod3r0kr.doc iii. Fundamental requirement for cultural and process change across the whole of HPS to deliver savings; iv. Implementation of the Agresso system in April 2011; (c) Note the key role of all stakeholders in leading the organisational and cultural changes required to deliver transformed support services and savings; (d) Note that a further report seeking formal decision to agree terms of the partners’ participation in the JVCo will be presented to the Board and Cabinet in September.
Key Points Summary This report outlines progress made on Shared Services.
• The current scope of services included are:
Finance Procurement
ICT Services Human Resources
Payroll and Expenses Estates
Transport Internal Audit
Legal Printing and Distribution
Communications and PR Emergency Planning
• The Cabinet and the PCT Board endorsed the decision of a public/public joint venture company (“JVCo”) as the preferred option for Shared Services in March 2010;
• The Business Transformation Board (BTB) have recommend a two stage process; (1) the establishment of JVCo to deliver short to medium term (1/2 years) benefits and (2) the further consideration of the strategic private sector partner option for the longer term (after 2/3 years);
• The Cabinet and the PCT board authorised the Deputy Chief Executive (DCE) to progress and take all necessary steps to establish a JVCo in consultation with the Leader and Deputy Leader of the Council and Trust Boards;
• Key areas of work since March have included:
o Engaging support services in scope and users of those services in the design of the future functions and what this means for changes to processes and how we work, including increasing self service
o Updating the investment appraisal in the Business Case, to reflect changes to structures since August 2009 and the decision to use a JVCo as the delivery vehicle
o Appointment of legal advisers and an interim CEO for the JVCo Reasons for Recommendations 1. To ensure that the Cabinet is briefed and is able to give guidance as appropriate on the work on Shared Services, to enable the projected benefits and costs savings to be delivered.
Introduction and Background 2. The scope of this work is the implementation of a shared services strategy for the Council, NHS Herefordshire (the PCT) and Hereford Hospital Trust (HHT) which collectively form the Herefordshire Shared Services Partnership (HSSP).
Key Considerations 3. A number of key public service drivers underpin the Shared Services work, these include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.