DMSW/100855/F - Land at or near Windmill Hill, Pencoyd Court & Trevase Farms, also Court Farm at Much Birch, Herefordshire, HR2
DecidedPlanning1 paper
Planning and Regulatory Committee decided this item on Wednesday 1 September 2010. Below is the council's own wording, with the papers it was decided on.
RESOLVED It be recorded that the Environmental Statement and associated documents including the Statement of Community Consultation have been taken into account in making this recommendation. That planning permission be granted subject to the following conditions: 1 No more than 20 hectares of Zone 1 shall be covered with polytunnels , or any part or parts thereof excepting the legs at any one time, for which purposes any uncovered hoops in a row shall be measured from the first to the last to be included in this coverage. Reason: In order to safeguard and maintain the the visual amenity of the area and to ensure that the development conforms with Policies DR1, LA2, LA5 and LA6 of the Herefordshire Unitary Development Plan. 2 No more than 25 hectares of Zone 2 shall be covered with polytunnels , or any part or parts thereof excepting the legs, at any one time, for which purposes any uncovered hoops in a row shall be measured from the first to the last to be included in this coverage. Reason: In order to safeguard and maintain the visual amenity of the area and to ensure the development conforms with Policies DR1, LA2, LA5 and LA6 of the Herefordshire Unitary Development Plan 2007. 3 No more than 10 hectares of Zone 3 shall be covered with polytunnels , or ... view the full minutes text for item 36.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
1.1By way of an introduction to this application, Members will be aware that the Council operated a voluntary code of practice for soft fruit growers in relation to polytunnel developments between 2003 and 2006. Once the law in respect of polytunnels was clarified, following the Tuesley Farm case, and the operation of that code ceased, negotiations were sought with all of the major growers with a view to planning applications being submitted.
1.2The planning application seeks to regularise the erection of polytunnels (polytunnels have been rotated within the application site since 1995) and has been the subject of a formal screening opinion under the Environmental Impact Assessment Regulations. It was determined that an Environmental Impact Assessment was required in this instance. The scope of the Environmental Statement (which incorporates the Statement of Community Consultation) covers the following topic areas:-
(a) traffic and transport (including impacts upon Public Rights of Way); (b) residential amenity; (c) ecology and nature conservation (an Ecological Survey accompanies the application); (d) archaeology and cultural heritage; (e) landscape impact (a Landscape and Visual Impact Assessment accompanies the application); (f) flood risk and water resources (a Flood Risk Assessment and Water Resources Evaluation accompanies the application) and (g) socio-economic impacts
Further information on the subject of this report is available from [name removed] on 01432 261932 PF2 Site Description and Proposal
1.3The application site lies to the south of Hereford and comprises three separate zones which together comprise a total area of 158 hectares within which it is proposed to erect a maximum of 55 hectares of polytunnels. The three zones are all to the west of the A49 road on land which generally slopes down in a westerly direction. The A49 constitutes the eastern edge of the Wye Valley Area of Outstanding Natural Beauty (AONB). There are no listed buildings within the application site itself but there are a number that lie adjacent to it. Harewood End Wood is designated as Ancient Woodland and is located some 550 metres from the application site and on the northern side of the A49.
1.4Zone 1 (Court Farm, Much Birch) is the northern most area for production and amounts to 52.3 hectares gross within which a maximum of 20 hectares of polytunnels would be erected. Access is taken off the A49 close to the village hall at Much Birch and GP surgery. The adopted road continues south westwards as a public footpath. The area identified for the erection of polytunnels is to the east and west of this track. The track then kinks south eastwards before joining the B4348 road. The Gamber brook is on the opposite side of the B4348 road. The land at Court Farm is leased and also is the site of a range of poultry units mid-way between the B4348 and the A49. There is a ridge along the western side of Zone 1 which screens the site in views from the west (i.e from Tump Lane and Wormelow).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.