Resolved
That the report be noted.
Audit and Governance Committee noted this item on Friday 17 September 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
MEETING: AUDIT AND GOVERNANCE COMMITTEE
DATE: 17 SEPTEMBER 2010
TITLE OF REPORT: MAJOR PROJECTS STATEMENT
PORTFOLIO AREA: RESOURCES CLASSIFICATION: Open.
Wards Affected None
Purpose To provide a position statement on major projects being undertaken by the authority.
Key Decision This is not a Key Decision.
Recommendation(s) THAT the contents of the report be noted.
Key Points Summary • The overall capital programme for 2010/2011 totals £77.7m.
• Funding for major projects includes a significant level of capital grants from central government.
Alternative Options 1 This is an information report and therefore no alternative options are outlined.
Reasons for Recommendations 2 The recommendation is proposed so that the committee acknowledges the supplied information.
Introduction and Background 3 Audit and Governance Committee has requested a regular position statement on major projects. The background to the request is that the committee has commented
Further information on the subject of this report is available from Malcolm MacAskill, Head of Asset Management & Property Services on (01432) 260227 on major projects at previous meetings.
Key Considerations 4 The report provides information on major projects being delivered by the council. In line with previous issues raised at committee the report has taken as a definition all projects with a forecast expenditure in excess of £500k and included in the capital programme. This is a definition consistent with that used to help provide capital programme budget monitoring information.
5 The committee will be aware that the council has faced a reduction in capital resources and will continue to see a further reduction in the foreseeable future. This will inevitably affect our ability to bring forward new capital projects. As a result the Council will need to give serious consideration to more innovative methods of funding future capital projects.
6 The current 20010/11 programme forecast is £77.7m. This is a net decrease of £0.2m over the original capital programme. The principal reasons for the decrease represent funding cuts by central government counteracted by the allocation of new funds and slippage from the previous year’s programme. Slippage occurs for a variety of reasons including revised timing of programme delivery that may result from policy review. In some cases slippage results from factors outside of the control of the council.
7 The original forecast can also increase as a result of the allocation of new funds. The council in common with other authorities will bid for funding from central government for specific schemes. If successful the notification can fall outside of the timescale of capital programme setting and the additional funding is then added to the overall programme total.
8 The major projects all have links to corporate themes. In addition the detailed capital programmes are reported to relevant scrutiny committees.
9 The funding picture for capital projects has been affected by central government’s approach to borrowing. Until April 2004 funding arrangements were based on credit approvals that were used to authorise expenditure financed by borrowing. Revenue support was generally provided by government for such borrowing.
10 The legislative framework for local authority borrowing changed on 1st April 2004. The key feature of the new system is that local authorities are free to raise finance for capital expenditure without government approval. The key test is whether they can afford to service the debt without government support. The new system places a duty on local authorities to determine and keep under review the amount they can afford to borrow.
11 The other significant source of funding is capital grants and contributions. In Herefordshire £40.5m of the £77.7m forecast programme is grant funded. The majority of the grant funding is for projects in the Children’s and Young People’s Directorate (£30m).
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
STATEMENT ON MAJOR PROJECTSReport | 97 KB | DownloadRead as text |
Follow Audit and Governance Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Nov 2026 | MinutesThat the minutes of the meeting held on 29 September 2026 be confirmed as a correct record and signed by the chairman. | Decided | Open |
| 3 Nov 2026 | Work programmeThat, subject to the updates made by the committee, the work programme be noted. | Noted | Open |
| 29 Sep 2026 | MinutesThat the minutes of the meeting held on 21 July 2026 be confirmed as a correct record and signed by the chairperson. | Decided | Open |
| 29 Sep 2026 | External Audit Findings ReportThat the report of the external auditor having been considered agreed that no issues raised in the report be added to... | Agreed | Open |
| 29 Sep 2026 | Final Annual Governance StatementThat the Annual Governance Statement for 2025/26 properly reflects the council’s internal control environment and the... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.