Resolved
That (a) that the report be noted; and (b) briefing notes be provided on the control exercised over consultants ... view the full minutes text for item 33.
Overview and Scrutiny Committee noted this item on Monday 18 October 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
That (a) that the report be noted; and (b) briefing notes be provided on the control exercised over consultants ... view the full minutes text for item 33.
MEETING: OVERVIEW & SCRUTINY COMMITTEE
DATE: 18 OCTOBER 2010
TITLE OF REPORT: PROJECT DESIGN AND DEVELOPMENT/FINANCIAL CONTROL OF CAPITAL SCHEMES
REPORT BY: DIRECTOR OF RESOURCES CLASSIFICATION: Open
Wards Affected County-wide
Purpose To advise Members on the project management and financial controls in place for Capital Schemes.
Recommendation THAT: the Overview & Scrutiny Committee notes the controls in place.
Key Points Summary • A wide range of project types and sizes exist.
• Prince 2 Project Management methodology in place.
• JCT (Joint Contract Tribunal) or NEC (New Engineering Contract)
• Procedures for budget costing are in place
• Final account controls are in place
Alternative Options 1 There are no alternative options as this is a report for noting only
Introduction and Background 2 In June the Children’s Services Scrutiny Committee requested that a full report on how major school building projects had been administered e.g. Riverside Primary School be considered by the Overview and Scrutiny Committee to ensure that learning and good practice was being
Further information on the subject of this report is available from Colin Birks, Property Operations Manager on (01432) 261980 $erd1z523.doc 22/02/10 incorporated into future projects.
Key Considerations 3 Asset Management & Property Services (AMPS) is responsible for a wide range of project types and sizes ranging from a minor improvement/maintenance scheme costing a few thousand pounds to a £22 million High School.
4 AMPS carries out work for Directorates within the council, external organisations such as Voluntary Aided Schools and projects commissioned by Schools.
5 In revenue terms AMPS spends about £3.5 million revenue and £10 to £12 million capital per annum.
6 In addition to professionally qualified surveyors, engineers and architects, specific staff are also trained in Prince 2 project management methodology. These trained staff support the projects undertaken.
7 Where Prince 2 is used on the larger schemes this involves forming a project team and a project board. The project manager is appointed and he/she leads the project team and reports to the project board. For construction type projects a qualified professional e.g. RICS (Royal Institute of Chartered Surveyors) or RIBA (Royal Institute of British Architects) is generally recognised as the most suitable to act as the project manager.
8 The projects are developed upon the RIBA (Royal Institute of British Architects) Outline Plan of work 2007 which is the industry’s recognised method of developing construction projects from approval through to completion.
9 AMPS subscribes to a number of organisations in order to obtain up to date cost information. The common one used on building projects is the BCIS (Building Cost Information Service). It provides budget and elemental cost information details for many of the common building functions.
10 In addition to the services AMPS also purchases industry recognised costing books including Spons and Griffiths pricing books.
11 In addition to the standard costing databases there is also a construction and engineering cost index which can be used to inform costs on an annual basis.
12 The method used to prepare cost information will vary throughout the project. At the initial preparation and design stages the cost plan is normally based upon a square meter basis. This is then checked against typical similar projects held on the BCIS database. As an example a 630 place Primary School would have an approximate floor area of 3400m² based upon the recommendations of the School Premises Regulations. (The approximate cost of constructing a School in the West Midlands area is in the region of £1950 per m²). Additional costs are then added for professional services, furniture and IT. Costs are also added for the utilities e.g. gas, water, electricity and drainage using actual budget costs, where possible, for approximate costs based on experience.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PROJECT DESIGN AND DEVELOPMENT/FINANCIAL CONTROL OF CAPITAL SCHEMESReport | 93 KB | DownloadRead as text |
Follow Overview and Scrutiny Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 12 Oct 2012 | MINUTESthat, as the Minutes of the meeting held on 4 October 2012 were received the previous day, they shoul be approved at ... | Approved | Open |
| 12 Oct 2012 | Hereford FuturesThat a) the contents of the report be noted; and; b) A working party comprised of Councillors EPJ Harvey, MAF Hubbard... | Noted | Open |
| 12 Oct 2012 | Locality working - first year of implementationThat a) the report be noted; b) the Committee recommend that greater engagement should be undertaken with the Town Co... | Noted | Open |
| 12 Oct 2012 | Corporate PlanThat a) The Committee endorsed the approach taken by Cabinet in formulating the ; and; b) The Committee recommended t... | Decided | Open |
| 12 Oct 2012 | Overview and scrutiny work programmeThat the work programme be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.