Resolved
The application was approved contrary to the case officer’s recommendation.
Planning and Regulatory Committee approved this item on Wednesday 18 July 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
The application was approved contrary to the case officer’s recommendation.
MEETING: PLANNING COMMITTEE
DATE: 18 JULY 2012 TITLE OF S120539/CD - AN EXTENSION, PART SINGLE STOREY AND REPORT: PART DOUBLE STOREY TO EXISTING SCHOOL BUILDING, WITH ASSOCIATED LANDSCAPING AND INCORPORATING AMENDMENTS TO LAYOUT AND APPEARANCE OF EXISTING SCHOOL AT BLACKMARSTON DAY SCHOOL, HONDDU CLOSE, HEREFORD, HR2 7NX
For: Property Services, Herefordshire Council per Amey Consulting, Explorer 2, Fleming Way, Crawley, W Sussex, RH10 9GT
WEBSITE http://www.herefordshire.gov.uk/housing/planning/58286.aspx?ID=120539&NoSearch= True LINK:
Date Received: 17 February 2012 Ward: St Martins and Hinton Grid Ref: 350248,238313 Expiry Date: 18 May 2012 Local Members: Councillors ACR Chappell, R Preece and P Rone
Update to Report
At the last committee, members were advised that a petition of 1251 signatures (from nearby neighbours and residents around the county) had been received in support of this application. This stated:
Blackmarston is Herefordshire’s ONLY Primary Special School for children with severe and complex learning difficulties and disabilities. The current school was originally built to accommodate 40 pupils, our population is increasing and we now have over 70 children on roll. As a result some of our children have to be accommodated in unsuitable portacabins and we all manage in a limited space with our essential specialist facilities being based in converted cupboards and shower rooms. These are Herefordshire’s most vulnerable children and yet, a present, the proposal is to reject our planning application which would allow us to extend the school to provide the learning space and facilities out children of the future so desperately need and richly deserve.
Following the last committee meeting the applicant has been considering the issues raised and has provided an update statement as follows:
Herefordshire Council recognises the importance of identifying and assessing all options, when considering a capital investment. This is particularly so for major schemes such as the one proposed for Blackmarston Special School.
The Council has adopted a robust governance and scrutiny process which ensures that options are fully assessed and challenged to ensure they offer the best solution. Cabinet and Cabinet Member
Further information on the subject of this report is available from [name removed] on 01432 261781 PF2 authorisation to commit capital funds requires officers to report on the assessment of alternative options.
Consequently, alternative options are always assessed prior to funding approval being awarded for any major capital scheme.
With regard to Blackmarston Special School, the overriding limitation for the viability of any alternative site option is insufficient capital resource to deliver what would need to be a completely new school. With a budget of £4.6m, a new school on a new site is not affordable. Capital receipts from the disposal of the existing school site would be inadequate. This would also be the case if the Council were minded at all to build a new all age special school to replace existing provision at Blackmarston and Barrs Court schools.
Consideration of specific sites referred to at Planning Committee on 27 June 2012.:
Aylestone Business & Enterprise College
This site was assessed when considering options for future accommodation for Barrs Court Special School. The option appraisal concluded that there was insufficient land available, given that Aylestone Business & Enterprise College is identified for expansion to accommodate additional pupils from new housing when the Local Development Framework is adopted. Since that appraisal was done, the school has applied to become an Academy. If the application is successful, the current land and buildings will be transferred to the new Academy Trust on a 125 year lease, in line with statute.
Former Whitecross High School site
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
S120539/CD: BLACKMARSTON DAY SCHOOL, HONDDU CLOSE, HEREFORD, HR2 7NXReport | 240 KB | DownloadRead as text |
Follow Planning and Regulatory Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Oct 2026 | 260943 - land southeast of woonton farm, woonton, almeley, herefordApplication approved in accordance with the case officer’s recommendation and a change to the conditions. | Approved | Open |
| 14 Oct 2026 | 253316/253317 - 123 the homend, ledbury, herefordshire, hr8 1bpApplication approved, contrary to the case officer’s recommendation. | Approved | Open |
| 9 Sep 2026 | 251908/251909 - land at town well station road, credenhill, herefordshire, hr4 7dwApplication approved in accordance with the case officer’s recommendation. | Approved | Open |
| 9 Sep 2026 | 261671 - town well, station road, credenhill, hereford, herefordshire, hr4 7dwApplication approved in accordance with the case officer’s recommendation. | Approved | Open |
| 9 Sep 2026 | 260149 - land south east of greyhound close, longtown, hereford, herefordshireApplication approved in accordance with the case officer’s recommendation. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.