Herefordshire Council
Cabinet, Thursday 13 September 2012 at 2.00pm

BORDERS BROADBAND CONTRACT AWARD AND PARTNERSHIP AGREEMENT

Noted Executive 4 papers

Cabinet noted this item on Thursday 13 September 2012. Below is the council's own wording, with the papers it was decided on.

Item26

Resolved

RESOLVED THAT: (a) Herefordshire Council’s capital contribution to the project be increased to £10,100,000 (from current allocation of £6m) to match fund BDUK’s contribution to the deployment of broadband to Herefordshire premises through the proposed contract with the Bidder and via a bursary scheme to the value of £350,000 as part of the match funding required by BDUK; (b) Cabinet note the ... view the full minutes text for item 26.
Word for word from the decision Herefordshire published for this meeting. Source: councillors.herefordshire.gov.uk

Follow this further

Built from Herefordshire's papers

What the report saysPro

Report to Cabinet

MEETING: CABINET DATE: 13TH SEPTEMBER 2012 TITLE OF REPORT: BORDERS BROADBAND CONTRACT AWARD AND PARTNERSHIP AGREEMENT PORTFOLIO AREA: EDUCATION AND INFRASTRUCTURE CLASSIFICATION: Open Wards Affected All except Aylestone, Belmont, Central, Hinton, Holmer, St Martins, St Nicholas and Tupsley with other wards only partially affected.

Purpose The purpose of this report is to seek agreement to conduct final negotiations for the delivery of improved Broadband infrastructure; and in so doing authorise Herefordshire Council’s financial contribution to the project and to progress the terms of a Partnership Agreement between Herefordshire Council and Gloucestershire County Council to oversee the delivery of the Borders Broadband project.

Key Decision This is a Key Decision because it is likely to have a significant effect on communities living and working in an area comprising one or more wards in the County.

Recommendations THAT:

(a) Herefordshire Council’s capital contribution to the project be increased to £10,100,000 (from current allocation of £6m) to match fund BDUK’s contribution to the deployment of broadband to Herefordshire premises through the proposed contract with the Bidder and via a bursary scheme to the value of £350,000 as part of the match funding required by BDUK;

(b) Cabinet note the terms of contract negotiated to date, the risks identified in this and the exempt report and the outstanding contractual issues;

(c) The Director for Places and Communities in consultation with the Cabinet Member for Education and Infrastructure and the statutory officers be authorised to conclude a contract with the remaining Bidder SUBJECT TO

(i) the agreement of Gloucestershire County Council certified in writing by its Chief Executive;

(ii) this being satisfied that the mitigation of the outstanding risks as identified in this report are the best that can reasonably be achieved;

(iii) the deal represents value for money, having particular regard to the payment mechanism controls and premises cap referred to in these reports;

Further information on the subject of this report is available from Natalia Silver, Project Director on (01432) 260732 (iv) the conclusion of a suitable partnership agreement with Gloucestershire County Council;

(d) The Director for Places and Communities be authorised to negotiate and conclude a partnership agreement with Gloucestershire County Council for the governance of the project, the terms of which are to be subject to the approval of the Statutory Officers;

(e) Cabinet note the content of the accompanying exempt report.

Key Points Summary • The successful Bidder will be obliged to improve the broadband network in areas of Herefordshire which would not otherwise receive investment commercially covering Universal Service Commitment (USC) of 2Mbps (megabits per second) or Next Generation Access (NGA) of 30Mbps and above.

• The procurement is in a single Bidder scenario and as such, members must be vigilant to ensure that the contract represents value for money and, in particular, that the NGA coverage eventually achieved will justify the outlay of public funds.

• It is therefore recommended that negotiations proceed with the remaining Bidder to ensure value for money is achieved and risks of coverage are mitigated.

• The legal powers that would enable the authority to enter into a contract with the remaining Bidder for the delivery of the project and also a Partnership Agreement with Gloucestershire are contained in section 2 of the Local Government Act 2000 and Section 1 of the Localism Act 2011.

Alternative Options 1 Options for contract award - to reject the offer made by the Bidder.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Equalities Impact and Needs AssessmentAppendix A 194 KB Download
PDF
BORDERS BROADBAND CONTRACT AWARD AND PARTNERSHIP AGREEMENTReport 137 KB DownloadRead as text
PDF
Calculating the Economic Impact of NGA Broadband in Herefordshire and GloucestershireReport 1.2 MB Download
PDF
Digital CountyReport 514 KB Download

At this meeting

Whole meeting

Who was there

7 of 20 attended
JJ
Councillor JG JarvisChairperson, present
AB
Councillor AJM BlackshawIn Attendance, in attendance
HB
Councillor H BramerMember, present
PM
Councillor PM MorganMember, present
RP
Councillor RJ PhillipsMember, apologies
PP
Councillor PD PriceMember, present
RH
Councillor RB HamiltonMember, present
JH
Councillor JA HydeIn Attendance, in attendance
AJ
Councillor AW JohnsonIn Attendance, in attendance
NN
Councillor NP NenadichIn Attendance, in attendance
PR
Councillor P RoneIn Attendance, in attendance
GP
Councillor GJ PowellMember, present

All 20 on the meeting page

More from Herefordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 MINUTESThat the minutes of the meeting held on 24 September 2026 be approved as a correct record and signed by the Chairperson. Approved Open
24 Sep 2026 MINUTESThat the minutes of the meeting held on 30 July 2026 be approved as a correct record and signed by the Chairperson. Approved Open
30 Jul 2026 MINUTESThat the minutes of the meeting held on 25 June 2026 be approved as a correct record and signed by the Chairperson. Approved Open
25 Jun 2026 MINUTESThat the minutes of the meeting held on 21 May 2026 be approved as a correct record and signed by the Chairperson. Approved Open
21 May 2026 MINUTESThat the minutes of the meeting held on 30 April 2026 be approved as a correct record and signed by the Chairperson. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies