CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Herefordshire Council
Cabinet, Thursday 13 December 2012 at 2.00pm

TO CONSIDER FUTURE OPTIONS FOR WASTE CONTRACT

Approved Executive 5 papers

Cabinet approved this item on Thursday 13 December 2012. Below is the council's own wording, with the papers it was decided on.

Item53

Resolved

RESOLVED THAT: Subject to Worcestershire County Council giving approvals substantially in the same form as those contained in the recommendations of this report (a) Notes, pursuant to the Cabinet Report of 16 February 2012 relating to a variation to the existing waste contract to provide for an Energy from Waste plant at Hartlebury Trading Estate (the EfW Plant), the on-going discussions with Mercia Waste Management Limited (Mercia) in relation to their proposals and the current status of satisfaction of the Parameters identified in that report ; (b) Cabinet authorised the Director for Places and Communities in consultation with the Cabinet Member for Major Contracts, the Chief Officer Finance and Commercial and Worcestershire County Council and through the joint governance arrangements between the two authorities to pursue terms for alternative methods of finance for the EfW plant; (c) (i) authorised the Director for Places and Communities in consultation with the Cabinet Member for Major Contracts and Worcestershire County Council and through the joint governance arrangements between the two authorities, to consider how the commissioning and operation of the EfW Plant could be integrated into the existing arrangements with Mercia, and (ii) if the Director for Places and Communities considered there was no satisfactory resolution in respect of point ( i ) above then ... view the full minutes text for item 53.
Word for word from the decision Herefordshire published for this meeting. Source: councillors.herefordshire.gov.uk

Follow this further

Built from Herefordshire's papers

What the report saysPro

Report to Cabinet

MEETING: CABINET DATE: 13 DECEMBER 2012 TITLE OF REPORT: TO CONSIDER FUTURE OPTIONS FOR WASTE CONTRACT REPORT BY: HEAD OF SPECIAL PROJECTS 1. Classification Open

2. Key Decision This is a Key Decision because it is likely to result in the Council incurring expenditure which is, or the making of savings which are, significant having regard to the Council’s budget for the service or function to which the decision relates:

Notice has been served in accordance with Part 3, Section 9 (Publicity in connection with key decisions) of The Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012

3. Wards Affected County-wide

4. Purpose To consider the proposals being made by Mercia Waste Management for the treatment of residual waste.

5. Recommendation(s) THAT: Subject to Worcestershire County Council giving approvals substantially in the same form as those contained in the recommendations of this report th (a) Notes, pursuant to the Cabinet Report of 16 February 2012 relating to a variation to the existing waste contract to provide for an Energy from Waste plant at Hartlebury Trading Estate (the EfW Plant), the ongoing discussions with Mercia Waste Management Limited (Mercia) in relation to their proposals and the current status of satisfaction of the Parameters identified in that report;

Further information on the subject of this report is available from Andrew Tector, Head of Special Projects on Tel: (01432) 261989

Cabinet Member Report DRAFT 18 Sept 12 (b) Cabinet authorises the Director for Places and Communities in consultation with the Cabinet Member for Major Contracts, the Chief Officer Finance and Commercial and Worcestershire County Council and through the joint governance arrangements between the two authorities to pursue terms for alternative methods of finance for the EfW plant;

(c)

(i) authorises the Director for Places and Communities in consultation with the Cabinet Member for Major Contracts and Worcestershire County Council and through the joint governance arrangements between the two authorities, to consider how the commissioning and operation of the EfW Plant could be integrated into the existing arrangements with Mercia, and

(ii) if the Director for Places and Communities considers there is no satisfactory resolution in respect of point (i) above then (subject to f) below) he is authorised if he considers it necessary (in consultation with the Cabinet Member for Major Contracts and Worcestershire County Council and through the joint governance arrangements between the two authorities) to launch a tendering exercise to commence the direct procurement by the 2 Councils of the EfW Plant in accordance with paragraph 9.9 below;

(d) Notes that Worcestershire County Council are authorised to procure and commence enabling works up to a maximum capital cost of £1.8m at Hartlebury in order to maintain the programme for the EfW Plant;

(e) Require the Director of Places and Communities to report back during the summer of 2013 with proposals for financing and procuring the EfW plant (by variation of the existing PFI contract or fresh procurement) to enable Cabinet to take a final decision; and

(f) Notes that Worcestershire County Council is expected to approve similar recommendations and that c ii) is subject to satisfactory negotiation and agreement with Worcestershire County Council of necessary amendments to the current Joint Working Agreement in place between the Councils; and

(g) Requires the Director for Places and Communities to report back to the Cabinet in the report referred to in (e) on the decisions taken by Worcestershire County Council on waste contract management and any implications for Herefordshire Council, .

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Parameters 211112 v2Appendix 1 29 KB Download
PDF
Options Appraisal WCC_Briefing Report_21112012Appendix 2 336 KB Download
PDF
Landfill Tax TrajectoryAppendix 3 104 KB Download
PDF
HW EFW Procurement Technical Review Final Report 12385i1Appendix 4 2.2 MB Download
PDF
TO CONSIDER FUTURE OPTIONS FOR WASTE CONTRACTReport 108 KB DownloadRead as text

At this meeting

Whole meeting
51MINUTESApproved 52BUDGET UPDATE 2013/14On the agenda
53TO CONSIDER FUTURE OPTIONS FOR WASTE CONTRACTThis decision

Who was there

8 of 21 attended
JJ
Councillor JG JarvisChairperson, present
HB
Councillor H BramerMember, present
RH
Councillor RB HamiltonMember, present
AJ
Councillor AW JohnsonMember, present
PM
Councillor PM MorganMember, present
RP
Councillor RJ PhillipsMember, present
GP
Councillor GJ PowellMember, present
PP
Councillor PD PriceMember, present
AA
Councillor AM AtkinsonIn Attendance, in attendance
JH
Councillor JA HydeIn Attendance, absent
NN
Councillor NP NenadichIn Attendance, in attendance
PR
Councillor P RoneIn Attendance, in attendance

All 21 on the meeting page

More from Herefordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 MINUTESThat the minutes of the meeting held on 24 September 2026 be approved as a correct record and signed by the Chairperson. Approved Open
24 Sep 2026 MINUTESThat the minutes of the meeting held on 30 July 2026 be approved as a correct record and signed by the Chairperson. Approved Open
30 Jul 2026 MINUTESThat the minutes of the meeting held on 25 June 2026 be approved as a correct record and signed by the Chairperson. Approved Open
25 Jun 2026 MINUTESThat the minutes of the meeting held on 21 May 2026 be approved as a correct record and signed by the Chairperson. Approved Open
21 May 2026 MINUTESThat the minutes of the meeting held on 30 April 2026 be approved as a correct record and signed by the Chairperson. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies