Resolved
RESOLVED That the report be noted.
Planning and Regulatory Committee noted this item on Wednesday 20 February 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the report be noted.
MEETING: PLANNING COMMITTEE
DATE: 20 FEBRUARY 2013
TITLE OF REPORT: ENFORCEMENT REPORT
CLASSIFICATION: Open
Wards Affected Countywide
Purpose To update the Committee in respect of Planning Enforcement Performance for the period 1 April 2012 – 30 September 2012
Key Decision This is not a key decision.
Recommendation That the report be noted ENFORCEMENT PERFORMANCE – 6-MONTHLY REPORT - 1 April 2012 – 30 September 2012 There are no national Performance Indicators for planning enforcement. The Planning Enforcement Policy includes a requirement for reporting on Enforcement activity to this Committee. The tables below set out the results for the period 1 April 2012 – 30 September 2012, the fourth such report.
Cases opened 1 April 2012 – 30 September 2012
Type Total D01 Breach of Planning Condition 45 D03 Development contrary to approved plans 16 D04 Unauthorised operational development 116 D05 Unauthorised material change of use 85 D06 Unauthorised works to Listed Building 15 D07 Unauthorised works to TPO 1 D08 Unauthorised works to trees in a Conservation Area 1 D09 Unauthorised Advertisement 17 D10 Unauthorised demolition in a Conservation Area 1 D11 Untidy land 7 D26 Unauthorised Works to a Hedgerow 2
Total 306
Further information on the subject of this report is available from Mark Tansley, Development Manager (Monitoring and Compliance) - 01432 261815 Closed Cases 1 April 2012 – 30 September 2012
Type Total D01 Breach of Planning Condition 63 D03 Development contrary to approved plans 12 D04 Unauthorised operational development 121 D05 Unauthorised material change of use 83 D06 Unauthorised works to Listed Building 14 D07 Unauthorised works to TPO 1 D08 Unauthorised works to trees in a Conservation Area 1 D09 Unauthorised Advertisement 14 D10 Unauthorised demolition in a Conservation Area 1 D11 Untidy land 11 D15 Unauthorised Building 29 D19 Unauthorised Mobile Home 1 D26 Unauthorised Works to a Hedgerow 2 Grand Total 353
Enforcement Outcomes 1 April 2012 – 30 September 2012
Code Total C01 No apparent breach (not development) 68 C02 No apparent breach (permitted development) 57 C03 Immune from action (4/10 yr rule) 10 C04 Not expedient to take action 62 C05 Resolved through negotiation or compliance 86 C06 Resolved by planning permission being approved 50 C07 Enforcement action taken - compliance secured 7 C08 Passed onto other service area 8 Grand Total 348
Notices Served 1 April 2012 – 30 September 2012
Count of type Type Total P01 Planning Contravention Notice 10 P02 Breach of Condition Notice 2 P03 Enforcement Notice 2 P05 Section 215 Notice 2 P09 Section 330 Requisition 4 Total 20
Members requested a comparison of cases dealt with since reporting began. The table below sets out performance following re-organisation of the team:
1/4/10 -30/9/10 1/10/10 – 31/3/11 1/4/11 – 30/9/11 1/10/11 – 31/3/12 Cases Opened 389 357 392 337 Cases Closed 362 400 434 385
Further information on the subject of this report is available from Mark Tansley, Development Manager (Monitoring and Compliance) - 01432 261815 In addition approximately 524 notifications of commencement from Building Control have been checked. This involves checking that planning permission has been received, where required, and whether or not any pre-commencement condition requirements have been met. It can result in requests for planning applications or in letters seeking submission of details of conditions.
Applications to vary a premises licence under the Licensing Act 2003 are also checked along with Festival and Show Events. These can also result in requests for planning applications or in letters seeking submission of details of conditions.
Enforcement performance is now reported monthly on the Planning Enforcement web page,
Further information on the subject of this report is available from Mark Tansley, Development Manager (Monitoring and Compliance) - 01432 261815
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ENFORCEMENT REPORTReport | 82 KB | DownloadRead as text |
Follow Planning and Regulatory Committee at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Oct 2026 | 260943 - land southeast of woonton farm, woonton, almeley, herefordApplication approved in accordance with the case officer’s recommendation and a change to the conditions. | Approved | Open |
| 14 Oct 2026 | 253316/253317 - 123 the homend, ledbury, herefordshire, hr8 1bpApplication approved, contrary to the case officer’s recommendation. | Approved | Open |
| 9 Sep 2026 | 251908/251909 - land at town well station road, credenhill, herefordshire, hr4 7dwApplication approved in accordance with the case officer’s recommendation. | Approved | Open |
| 9 Sep 2026 | 261671 - town well, station road, credenhill, hereford, herefordshire, hr4 7dwApplication approved in accordance with the case officer’s recommendation. | Approved | Open |
| 9 Sep 2026 | 260149 - land south east of greyhound close, longtown, hereford, herefordshireApplication approved in accordance with the case officer’s recommendation. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.