TITLE OF REPORT: BUDGET MONITORING REPORT 2012/13
REPORT BY: CHIEF OFFICER: FINANCE & COMMERCIAL
1. Classification Open
2. Key Decision This is not a key decision
3. Wards Affected County-wide
4. Purpose To report the financial position for both Revenue and Capital budgets to 28 February 2013. The Treasury Management position is also included.
5. Recommendation(s) THAT:
(a) Cabinet note the report and the forecast position;
(b) Note the Treasury Management report at Appendix C.
6. Key Points Summary • As at 28 February 2013 the overall revenue budget position showed a projected overspend of £3.5m by the end of the financial year, as shown in Appendix A. This is approximately 2.5% of the council’s £143.4m revenue budget. This is an improvement of £398k since the projection in January 2013. Details of spending and actions taken by Directorates are included in Appendix A.
• The general fund reserve balance as at 31 March 2012 was £6.1m. Any overspend on the revenue account at the year-end would have to be met largely from this reserve.
• At 1 April 2012 the council held £13.5m of earmarked reserves, which are detailed in Appendix A. The specific nature of those reserves means that some are not available for Further information on the subject of this report is available from Heather Foster: Head of Corporate Finance on Tel: (01432) 260248 reclassification as general reserves, for example the balance held for schools. However, the requirement for other reserves will be further reviewed as part of the 2012/13 accounts closedown.
• Under the current medium term financial plan, any use of reserves would need to be “paid back” as part of the 2013/14 budget.
• In addition to the revenue overview the forecast outturn spend on capital schemes is £38.1m compared to the original budget of £44m. Further details are attached in Appendix B.
• The overall position is mitigated by projected savings on borrowing and investments (£776k net).
• This is the last report until the year end position is reported to Cabinet in June 2013.
7. Alternative Options 7.1 There are no Alternative Options as this report is for information purposes.
8. Reasons for Recommendations 8.1 To keep Cabinet informed about the projected revenue and capital out-turn position for 2012/13 including Treasury Management activities.
9. Introduction and Background 9.1 Cabinet receives regular budget monitoring reports. The last report was presented to Cabinet on 14 March 2013, which included the revenue and capital projected out-turn as at January 2013.
10. Key Considerations 10.1 The projected overspend is £3.5m by the end of the financial year 2012/13. This is approximately 2.5% of the council’s £143.4m revenue budget.
10.2The main movements from the January projected overspend of £3.9m are shown in the table below;
£000
Projected out-turn as at January (3,933)
Additional pressure on Winter maintenance cost (215)
Reduction in shortfall on Planning income 175
Savings from capitalisation of ICT spend 240
Reduction in Learning Disabilities respite care 250
Reduction in Mental Health (MH) packages (residential & nursing) 142
MH deferred packages 163 MH domiciliary packages 39
Older People (Incl. nursing / reduction residential) (17)
Increase in Physical Disabilities (dom. care and residential (39) packages)
Reduce estimate capitalisation in social care (100)
Redundancy costs (62)
Other commissioning savings 27
Provide for data protection fine (estimate) (100)
Increased agency / young offender placements (63)
Other children’s provider savings 21
Environmental health (Leominster leachate key item) (19)
Investment income (4)
Centrally held budgets (40)
Latest projected out-turn (3,535)
10.3The 2012/13 budget agreed by Council in February 2012 reflects the overall savings of £10.8m required to meet the reduced funding levels from central government and budget pressures, particularly on Adult Social Care budgets.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
End of Feb 2013 FINALAppendix A | 157 KB | Download |
PDF |
Feb 13 FINALAppendix B | 75 KB | Download |
PDF |
TM Report to 28 Feb 13 FINALAppendix C | 121 KB | Download |
PDF |
BUDGET MONITORING REPORTReport | 93 KB | DownloadRead as text |
Follow Cabinet at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | MINUTESThat the minutes of the meeting held on 24 September 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 24 Sep 2026 | MINUTESThat the minutes of the meeting held on 30 July 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 30 Jul 2026 | MINUTESThat the minutes of the meeting held on 25 June 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 25 Jun 2026 | MINUTESThat the minutes of the meeting held on 21 May 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 21 May 2026 | MINUTESThat the minutes of the meeting held on 30 April 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.