That the Assistant Director People, Policy & Partnership be granted delegated authority, in consultation with the Cabinet Member Highways and Transportation, Chief Financial Officer and Solicitor to the Council, to make the decision on the Wide Area Network re-procurement for Herefordshire Council.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
MEETING: CABINET – HIGHWAYS & TRANSPORTATION MEETING DATE: 25 JULY 2013 TITLE OF REPORT: HEREFORDSHIRE COUNTY NETWORK RENEWAL (PSN) REPORT BY: ASSISTANT DIRECTOR PEOPLE, POLICY & PARTNERSHIPS
1. Classification Open 2. Key Decision This is a Key Decision because it is likely to result in the Council incurring expenditure which is, or the making of savings which are, significant having regard to the Council’s budget for the service or function to which the decision relates. NOTICE has been served in accordance with Part 3, Section 9 (Publicity in connection with key decisions) of The Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012 3. Wards Affected County-wide
4. Purpose The Wide Area Network service contract for Herefordshire Council and partners is due for renewal in March 2014. The contract is currently managed by Updata Infrastructure UK Ltd, which costs the Council approximately £435,000 per annum. Herefordshire Council are working with Hoople to ensure that the replacement contract delivers value for money. One of the collaborative options available to the Council will require full commitment to contractually engage by August 8th 2013. Full details of the proposal will not be available for Cabinet.
Cabinet is asked to agree the approach and delegate decision making about the preferred option to the Assistant Director People, Policy & Partnerships in order that the timeline for this work can be achieved. This decision will be made after consideration by the IM&T Board (29th July 2013), and in consultation with the Cabinet Member Highways and Transport, Chief Financial Officer and Solicitor to the Council (31st July 2013). This decision can only be made when in full knowledge of the proposed contract details which will not be available at time of cabinet report, and needs to be made by the 8th August to comply with one of the option requirements.
The appendix to this report provides an update on the progress made towards re-
Further information on the subject of this Report is available from Dominic Latham, Service Manager ICT Strategy and Commissioning on Tel (01432) 383186 procuring a Network Connectivity contract for Herefordshire Council in time for the current contract end date of March 2014. 5. Recommendation(s) THAT:
(a) the Assistant Director People, Policy & Partnership is granted delegated authority, in consultation with the Cabinet Member Highways and Transportation, Chief Financial Officer and Solicitor to the Council, to make the decision on the Wide Area Network re-procurement for Herefordshire Council;
6. Alternative Options The Wide Area Network provision, maintenance and support requires renewal for March 2014. It is essential that the Council’s Wide Area Network (and that of schools and NHS) is supported and under contract to ensure the smooth running of important data circuits and telephony services. The alternative options as outlined in the document are:
6.1To procure network provision independently for the council and its local partners only.
6.2To procure WAN provision through Staffordshire County Council’s Framework Agreement.
6.3To procure network provision collaboratively through the West Midlands collaborative PSN.
7. Reasons for Recommendations 7.1 There are a number of timescale constraints. Cabinet is therefore asked to agree the approach being taken and to delegate authority to Assistant Director, People Policy and Partnerships for the consideration of the options and final decision on the way forward.
8. Key Considerations 8.1 The objective is to ensure that due consideration is given to the renewal of WAN provision in Herefordshire for the next 3 years;
8.2To ensure that provision is provided with maximum value for money; with a provider that will work with the partners to reduce costs year on year;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.