Resolved
That the Minutes of the meeting held on 31 July 2014 be approved as a correct record and signed by the Chairman.
Cabinet approved this item on Thursday 11 September 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Minutes of the meeting held on 31 July 2014 be approved as a correct record and signed by the Chairman.
HEREFORDSHIRE COUNCIL MINUTES of the meeting of Cabinet held at The Council Chamber, Brockington, 35 Hafod Road, Hereford on Thursday 31 July 2014 at 2.00 pm
Present: Councillor AW Johnson (Chairman)
Councillors: JW Millar, GJ Powell, PD Price, P Rone, and H Bramer
In attendance: Councillors , WLS Bowen, AJW Powers, TM James, F Norman, R Matthews, J Stone, M Lloyd-Hayes, J Bartlett, and CNH Attwood
Officers: Richard Ball, Helen Coombes, Jo Davidson, Steve Hodges, Geoff Hughes, Bill Norman and Peter Robinson [name removed] (Chair Herefordshire Safeguarding Children Board) [name removed], West Mercia Youth Offending Service
14. APOLOGIES FOR ABSENCE
Councillors: JA Hyde, J Jarvis, PM Morgan, R Phillips.
Alistair Neill
15. DECLARATIONS OF INTEREST
There were no declarations of interest.
16. MINUTES
RESOLVED: That the minutes of the meeting held on 3 July 2014 be approved as a correct record and signed by the chairman, subject to the addition of Cllr R Matthews as being present.
17. BUDGET MONITORING REPORT
Cabinet received a report setting out the forecast outturn position based on information as at the end of May 2014, and proposals for a number of budget virements to support centralisation of corporate budgets. It was noted that delivery of a balanced budget was projected.
The Chief Financial Officer, Peter Robinson, drew attention to two significant budget pressures which had arisen since the budget period being reported: £400,000 to support additional in year grass cuttings to be funded from the revenue contingency; and £2m to address the need for temporary accommodation at Colwall Church of England Primary School pending the outcome of works to investigate damp issues at the school to be funded from within existing repair and maintenance and capital and revenue contingencies. [name removed] confirmed that he remained confident in the budget forecast for a balanced budget, even should there be winter pressures. All sources of funding were being pursued.
Following issues raised by members in attendance: Assurance was sought that other schools premises were not likely to require additional emergency significant expenditure. The Chief Financial Officer acknowledged that the damp issues had been known for some time but had significantly worsened following the exceptional spring rains resulting in the need for some urgent response. The Cabinet Member Young People and Children’s Wellbeing advised that existing conditions surveys for schools were in the process of being updated in line with the activity planned in the Corporate Plan. The Cabinet Member Health & Wellbeing clarified the mitigations put in place to address adult social care savings risks. The Director Economy, Communities and Corporate provided clarification regarding the Yazor Brook flood relief scheme costs and confirmed that some of the additional planning income (a positive indicator of economic improvement) would be reinvested in the service. The Leader provided assurance that the Colwall community was, and would continue to be engaged in discussions about the future of the school. Assurance was provided that provision had been made for legal costs; the Assistant Director Governance confirmed that any judicial reviews were managed to minimise costs.
RESOLVED THAT: (a) Cabinet notes the council is projected to spend within its budget for this financial year; (b) Cabinet notes the capital and treasury projected outturns; and (c) Cabinet agrees the virement of 14/15 budgets, including £7m of budgets from services to centralised area to improve budgetary control and improve value for money
18. QUARTERLY PERFORMANCE REPORT
Cabinet considered performance for the first quarter of 2014/15 following the first quarterly performance review held on 15th July 2014.
The Cabinet Member Health & Wellbeing provided an update to the report that 43,000 premises had access to fibre broadband and Vodaphone /O2 had now identified 19 sites across the city identified for 4g masts.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MINUTESMinutes | 81 KB | DownloadRead as text |
Follow Cabinet at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | MINUTESThat the minutes of the meeting held on 24 September 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 24 Sep 2026 | MINUTESThat the minutes of the meeting held on 30 July 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 30 Jul 2026 | MINUTESThat the minutes of the meeting held on 25 June 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 25 Jun 2026 | MINUTESThat the minutes of the meeting held on 21 May 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 21 May 2026 | MINUTESThat the minutes of the meeting held on 30 April 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.