That the Cabinet Member for Young People and Children’s Wellbeing be recommended to approve that; (i) The options set out in paragraph 12 are implemented where possible to deliver savings as estimated (ii) The necessary additional financial contributions to the PFI contract be shared equally between the council and schools (through Dedicated Schools Grant) as follows; Year Council Share £’000 DSG Funding £’000 Cumulative £’000 2015/16 - 16 12.5 12.5 25 2016/17 25 25 75 2017/18 25 25 125 (iii) this position be reviewed if inflation increases take place above those anticipated; (iv) Schools Forum receive a progress report in January 2015 so that the forecasts can be updated. (Following consideration of this item [name removed] commented that the School ... view the full minutes text for item 184.
Word for word from the decision Herefordshire published for this meeting.Source: councillors.herefordshire.gov.uk
Purpose To report on the Whitecross Private Finance Initiative (PFI) scheme and to consider the need for potential additional funding.
Recommendation(s)
THAT: the Cabinet Member for Young People and Children’s Wellbeing be recommended to approve that;
(i) The options set out in paragraph 12 are implemented where possible to deliver savings as estimated
(ii) The necessary additional financial contributions to the PFI contract be shared equally between the council and schools (through Dedicated Schools Grant) as follows; Year Council Share DSG Funding Cumulative
Further information on the subject of this report is available from Malcolm Green on Tel (01432) 260818 (iii) This position to be reviewed if inflation increases take place above those anticipated (iv) Schools Forum will receive a progress report in January 2015 so that the forecasts can be updated.
Alternative Options 1 The options available are limited and have been discussed with the PFI project’s original financial advisors at a meeting on 10th March 2014. Their advice is set out in paragraph 12 below.
Reasons for Recommendations 2 The Whitecross PFI scheme is required to meet its costs over the life of the 25 year contract so that an impossible financial burden is not passed onto future ratepayers.
Key Considerations 3 Cabinet approved the outline business case for the replacement of Whitecross High School under a PFI scheme on 18th July 2001. The approval assumed PFI credits from the Department for Education (DfE) of £19.5m and annual contributions from the authority between £603k and £731k. In November 2003 bids were received from two consortia. Both bids were within the parameters set by the outline business case. Following careful evaluation of the technical, legal and financial aspects of both bids using criteria described in a formal evaluation framework, Cabinet approved a preferred bidder in March 2004 and the scheme moved to financial close on 17th January 2005.
4 Following the tender clarification process, both bids were outside the parameters of the approved outline business case and the DfE imposed new rules on the education revenue budget, making it more difficult to fund the annual payment from the centrally held education budget. Therefore, a three point strategy for managing the cost of the annual revenue payments was approved by Cabinet as follows:
(i) The DfE was asked for an uplift in the PFI credit by making the contract operational after 1st April 2006. This would reduce the average annual payment by around £50k per year
(This happened as the new school opened on 5th June 2006)
(ii) The preferred bidder was offered £1m from the capital receipt of the existing site, thereby reducing the capital cost of the new building to the consortium and in so doing, reducing the council’s average annual L.E.A. payment by £75k
(This has not happened as the old Whitecross site has not yet been sold. Given the passage of time since that decision a further Cabinet member decision would be required to ensure such action continued to offer best value)
(iii) Manage the PFI credit across the 25 year period in such a way as to ensure that the build up of annual PFI payments is commensurate with the reduction from 2008, of the cost of the Local Government Re-organisation Further information on the subject of this report is available from Malcolm Green on Tel (01432) 260818 (LGR) loan commitment, and consistent with the council’s medium term plan. Such an approach should make it possible for the council to meet the government’s guarantees to schools within the education revenue budget, whilst also remaining within the defined limits on central LEA spending.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.