Resolved
That a) The report be noted; b) That the Communications Plan be organised through the Engagement Gateway in order to involve communication leads;and; c) An updated report be bought to the Board in six months’ time.
Health and Wellbeing Board noted this item on Tuesday 21 July 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
That a) The report be noted; b) That the Communications Plan be organised through the Engagement Gateway in order to involve communication leads;and; c) An updated report be bought to the Board in six months’ time.
Mental Health Integrated Pathway
Joint Mental Health Project Summary
13/07/2015 1
Joint Procurement of Mental Health Services
This presentation summarises a new joint project of NHS Herefordshire CCG and Herefordshire Council to develop a joint, all ages, integrated pathway for mental health services and sets out a timeline based upon a commencement date of 1st April 2017 for the new services.
The project recognises the central importance of mental health in the Health and Wellbeing strategy and builds on the engagement undertaken to complete the mental health needs assessment, all ages mental health strategy and Children’s and Young People’s Plan.
The core aim of the project is to integrate services across care, health and public health to deliver much better outcomes for Herefordshire service users and to increase prevention of mental illness.
Workshops with commissioners are now taking place to develop the joint objectives of the project, the scope of the project and the outcomes required for services users.
The objectives and outcomes are very much based on the perspective of service users and their needs and will be tested with a reference group of stakeholders.
The scope of the project will likely involve a core procurement with programmes of phased work “wrapped around” that core. Some services or opportunities may not be included in the procurement process, but may be developed alongside the procurement process with key timelines relating to the procurement process.
1 Joint Procurement of Mental Health Services
Draft Strategic Aims:
The project should deliver a joint pathway for contracts for mental health and emotional wellbeing services in Herefordshire such that within available resources they demonstrably:
• Support service users to have the best possible mental and physical health.
• Meet service users’ needs such that they • are able to function in their daily lives; • can get assessment and support where and when they need it; • experience seamless transitions and teams that work together to meet their needs; • are supported to recover and remain well; and • are supported at the end of life if it such support is needed.
• Involve service users in decisions about their care such that they are • listened to and their views are taken into account; and • treated as a person not a diagnosis or collection of conditions.
• Enable service users to be open about their condition if they want to be.
• Support carers in in their caring role.
• Build capability and capacity in other partners / providers
Joint Procurement of Mental Health Services
Draft Strategic Aims for Integration:
Combining the commissioning strength of the two organisations to procure new integrated mental health services should:
• Design services around the joint mental health needs assessment;
• Target services to give the greatest impact on outcomes;
• Avoid duplication of services;
• Ensure value for money, efficiency and effectiveness;
• Develop co‐ordinated services;
• Remove barriers between health and social care services;
• Share best practice;
• Share expertise; and
• Share intelligence about needs
2 Project Proposed Timeline‐ Outline
The Broad Phases of a project are:
• April 2015 to October 2015‐ Initiation, Design and Development Phase
• November 2015 to September 2016 Procurement Phase
• October 2016 to March 2017 Mobilisation and Transition Phase
• 1st April 2017 New Contract Commences
A contract model that is outcomes‐based and supports integration with other services is likely to benefit from a procurement route that includes some form of dialogue / negotiation with prospective providers.
This initial illustrative timeline is based upon a procurement route involving dialogue. All permissible procurement routes will be explored as part of the preparation phase of the project before a final recommendation is made.
This timeline requires an extension of current contracts with 2gether NHS FT of 12 months.
Project Proposed Timeline‐ Summary Workstreams
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Mental Health Services Integrated PathwayFrontsheet | 144 KB | Download |
PDF |
Presentation to HOSC and H&WB July 2015Report | 180 KB | DownloadRead as text |
Follow Health and Wellbeing Board at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Jul 2026 | MinutesThat the minutes of the meeting held on 18 May 2026 be confirmed as a correct record and be signed by the Chairperson... | Decided | Open |
| 13 Jul 2026 | Best Start in Life - Good Level of Development (GLD) in children aged 5 yearsThat ... view the full minutes text for item 8. Media | Decided | Open |
| 13 Jul 2026 | Gambling and Related HarmsThat the contents of the briefing paper be noted. Action: Partner organisations to consider what contribution could b... | Noted | Open |
| 13 Jul 2026 | The Better Care Fund (BCF) year-end report 2025/26That a) The Better Care Fund 2025/26 end-of-year report, as submitted to NHS England, has been reviewed and approved ... | Approved | Open |
| 13 Jul 2026 | Herefordshire's Better Care Plan 2026/27That a) The Herefordshire Better Care Fund 2026/27 Narrative Plan and Numerical Template, as submitted to NHS England... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.