Resolved
RESOLVED THAT: (a) Cabinet notes the council is currently projecting an overspend of £583k; and (b) performance for the first six months of 2015/16 is considered.
Cabinet decided this item on Thursday 3 December 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT: (a) Cabinet notes the council is currently projecting an overspend of £583k; and (b) performance for the first six months of 2015/16 is considered.
County-wide
Purpose To consider performance for the first two quarters of 2015/16 and the projected budget outturn for the year.
Recommendation(s)
THAT: (a) Cabinet notes the council is currently projecting an overspend of £583k; and
(b) Performance for the first six months of 2015/16 is considered.
Alternative options 1. Cabinet may: choose to review performance more or less frequently; or request alternative actions to address any identified areas of under-performance, including referral to the relevant scrutiny committee.
Reasons for recommendations 2. To provide assurance that progress is being made towards achievement of the Further information on the subject of this report is available from Peter Robinson, director of resources on (01432) 383514 and Richard Ball, assistant director commissioning on (01432) 260965 agreed outcomes and service delivery targets, and that the reasons for important areas of actual or potential under-performance are understood and are being addressed to the cabinet’s satisfaction.
Key Considerations 3. Council approved the corporate plan 2013-15 in November 2012, framed around the key priorities of: enabling residents to be independent and lead fulfilling lives with resources focussed on supporting the most vulnerable; and creating and maintaining a successful economy. The supporting delivery plan for 2015/16 was approved by cabinet in March 2015. 4. Progress is measured through a number of performance measures. These have been selected because they demonstrate progress towards achievement of the council’s priorities and also provide an overview of the council’s performance from a resident’s perspective. The databooks, which are available on the council’s website, contain the latest performance outturns available. Where monitoring information is only available annually, these measures will be reported at the point it becomes available. 5. The projected outturn based on spend to the end of September 2015 is an overspend of £583k, 0.4% of net budget. It is anticipated that overall spending will come in within budget by year-end. The £700k corporate contingency budget has not been allocated, this may cover the overspend however it is being held until there is more certainty of potential winter pressures.
Projected revenue outturn 2015/16
Directorate Net Net Budget September September Variance Budget Outturn Over / (Under)spend (£000) (£000) (£000) Adults’ wellbeing 53,596 53,689 93 Children’s wellbeing 23,159 24,753 1,594 Economy, communities 53,380 52,876 (504) and corporate Directorates Total 130,135 131,318 1,183 Other budgets and 11,858 11,258 (600) reserves Total 141,993 142,576 583
6. Appendix A provides a further breakdown of the directorate budgets and forecast spend.
7. Appendix E provides an overview of performance during the first six months of 2015/16. Whilst 65% (74% at end of May) of performance measures are showing a positive shift in performance, there remain however 32% (24% at end of May) that are currently performing worse than the same period last year, and consideration needs to be given as to required actions to improve performance.
8. A summary of performance and the challenges faced within each directorate is included below in paragraphs 9-31.
Further information on the subject of this report is available from Peter Robinson, director of resources on (01432) 383514 and Richard Ball, assistant director commissioning on (01432) 260965 Adults’ wellbeing
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
revenue forecastAppendix A | 199 KB | Download |
PDF |
capital forecastAppendix B | 84 KB | Download |
PDF |
treasury management forecastAppendix C | 111 KB | Download |
PDF |
debt write-offsAppendix D | 6 KB | Download |
PDF |
Strategic OverviewAppendix E | 359 KB | Download |
PDF |
Quarter 2 corporate performance and budget report 2015/16Report | 169 KB | DownloadRead as text |
Follow Cabinet at Herefordshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Oct 2026 | MINUTESThat the minutes of the meeting held on 24 September 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 24 Sep 2026 | MINUTESThat the minutes of the meeting held on 30 July 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 30 Jul 2026 | MINUTESThat the minutes of the meeting held on 25 June 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 25 Jun 2026 | MINUTESThat the minutes of the meeting held on 21 May 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
| 21 May 2026 | MINUTESThat the minutes of the meeting held on 30 April 2026 be approved as a correct record and signed by the Chairperson. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.