CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Herefordshire Council
Cabinet, Monday 9 May 2016 at 2.00pm

HEREFORD LIBRARY AND MUSEUM RESPONSE

Approved Executive 2 papers

Cabinet approved this item on Monday 9 May 2016. Below is the council's own wording, with the papers it was decided on.

Item160

Resolved

That: (a) works to enable reinstatement of Hereford library and museum building, and relocation of the Wellbeing Information and Signposting Service (WISH) to the Broad Street site, Hereford be undertaken to a maximum cost of £500k; (b) following completion of the works at recommendation a) above, the balance of the capital allocation be used as match funding for a development scheme, led by HLUG or other partner, subject to the development scheme being approved by the relevant cabinet member within a two year period; and (c) a further report be prepared on the options for shorter term re-opening of the museum and art gallery at the Broad Street site, pending a decision on longer term options for sustainable delivery of the museum and archive service.
Word for word from the decision Herefordshire published for this meeting. Source: councillors.herefordshire.gov.uk

Follow this further

Built from Herefordshire's papers

What the report saysPro

Report to Cabinet

Meeting: Cabinet Meeting date: 9 May 2016 Title of report: Hereford library and museum response Report by: Cabinet member contracts and assets

Classification Open

Key decision This is a key decision because it is likely to be significant in terms of its effect on communities living or working in an area comprising one or more wards in the county. Notice has been served in accordance with Part 3, Section 9 (Publicity in Connection with Key Decisions) of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012. Wards affected County-wide (Central ward location)

Purpose To consider the response to the proposals submitted by Hereford Library Users Group regarding the future operation of Hereford library and museum.

Recommendations THAT, (a) works to enable reinstatement of Hereford library and museum building, and relocation of the Wellbeing Information and Signposting Service (WISH) to the Broad Street site, Hereford be undertaken to a maximum cost of £500k; (b) following completion of the works at recommendation a) above the balance of the capital allocation be used as match funding for a development scheme, led by HLUG or other partner, subject to the development scheme being approved by the relevant cabinet member within a two year period; and (c) a further report be prepared on the options for shorter term re-opening of the museum and art gallery at the Broad Street site, pending a decision on longer term options for sustainable delivery of the museum and archive service. Alternative options 1 The reopening of the building is delayed until funds are raised for the development scheme whilst retaining the temporary provision at Hereford Town Hall and extra hours at Belmont Library. This is not recommended as HLUG advise that the fundraising and new building works could take in the region of four to five years and this will have an impact on users of the services. This would also be viewed as a reduction in service and challenged the authority’s statutory duty to provide “comprehensive and efficient library service” therefore trigger a judicial review instigated by the community who are concerned with any further reduction in service.

Further information on the subject of this report is available from Natalia Silver, Assistant Director – Communities. Tel (01432) 260732 2 The services are withdrawn to meet the authority’s required budget savings. The level of capital spend would also be reduced, though elements of the work would be required to make good the building for alternative use. This is not recommended as it would adversely affect the council’s ability to meet the statutory duty to provide a comprehensive library service in the county. 3 There is no delay in conducting the major works along with reinstatement works. This is not recommended as it would reduce the opportunity to fundraise for a development scheme. 4 The council seeks alternative site(s) to house the services. This is not recommended at this stage, as HLUG have confirmed their preference is to maximise the current Broad Street site with no obvious other alternative presented during the research or consultation. However, to be revised as part of the longer term consideration for the services. 5 The council lead and fund the development scheme presented by HLUG. This is not recommended, as there are insufficient funds and resource to conduct a scheme to that scale without wider community in-put. 6 That the museum and art gallery is not reopened based on the recommendation Review of Museums and Archives Services. This is not recommended, but to work with interested parties to resource the museum and art gallery.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 2 MB Download
PDF
HEREFORD LIBRARY AND MUSEUM RESPONSEReport 407 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

20 of 24 attended
AJ
Councillor AW JohnsonChairperson, present
PM
Councillor PM MorganVice-Chairperson, present
HB
Councillor H BramerMember, present
JL
Councillor JG LesterMember, present
GP
Councillor GJ PowellMember, present
PP
Councillor PD PriceMember, present
PR
Councillor P RoneMember, present
JB
Councillor JM BartlettGroup leader, present
WB
Councillor WLS BowenScrutiny, present
JH
Councillor JA HydeCabinet support, present
TJ
Councillor TM JamesGroup leader, absent
RM
Councillor RI MatthewsGroup leader, present

All 24 on the meeting page

On this subject at Herefordshire

Search all
  1. HEREFORD LIBRARY AND MUSEUM RESPONSEThis decision
  2. 230385 & 230386 - museum, hereford library, broad street, hereford, herefordshire, hr4 9auApproved
  3. Dcse0009/1139/cd - alterations and an extension over two floors to provide council information, library and meeting facilities at ross on wye library, cantilupe road, ross on wye, herefordshire hr9 7anDecided
  4. Dcnw2005/0890/f - new sports hall, changing rooms, cafeteria and library at weobley high school, weobley, hereford, herefordshire, hr4 8stDecided

More from Herefordshire Cabinet

All decisions
MeetingDecisionOutcome
22 Oct 2026 MINUTESThat the minutes of the meeting held on 24 September 2026 be approved as a correct record and signed by the Chairperson. Approved Open
24 Sep 2026 MINUTESThat the minutes of the meeting held on 30 July 2026 be approved as a correct record and signed by the Chairperson. Approved Open
30 Jul 2026 MINUTESThat the minutes of the meeting held on 25 June 2026 be approved as a correct record and signed by the Chairperson. Approved Open
25 Jun 2026 MINUTESThat the minutes of the meeting held on 21 May 2026 be approved as a correct record and signed by the Chairperson. Approved Open
21 May 2026 MINUTESThat the minutes of the meeting held on 30 April 2026 be approved as a correct record and signed by the Chairperson. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies